| FILE DATE |
JOB # |
DOC # |
JOB TYPE |
JOB STATUS |
STATUS DATE |
LIC # |
APPLICANT |
IN AUDIT |
ZONING APPROVAL |
| 06/21/2023 |
122657892 |
02 |
A2 |
P APPROVED |
06/27/2023 |
0015609 RA |
NEWMAN |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): 002
|
| 02/08/2016 |
122657892 |
01 |
A2 |
R PERMIT-ENTIRE |
05/26/2016 |
0015609 RA |
NEWMAN |
Y |
NOT APPLICABLE
|
|
INTERIOR RENOVATION ON SECOND FLOOR AND INSTALLATION OF AIR CONDITIONING U
|
|
Work on Floor(s): 002
|
| 11/30/2015 |
122284955 |
02 |
A2 |
P APPROVED |
12/02/2015 |
|
NAKHLA |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): 001
|
| 03/02/2015 |
122284955 |
01 |
A2 |
X SIGNED OFF |
11/22/2016 |
0086711 PE |
NAKHLA |
|
NOT APPLICABLE
|
|
GENERAL CONSTRUCTION, SPRINKLER, MECHANICAL & PLUMBING MODIFICATIONS AS PE
|
|
Work on Floor(s): 001
|
| 07/31/2014 |
103673543 |
29 |
A1 |
P APPROVED |
12/16/2014 |
|
NEWMAN |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,ROF 001 thru 019
|
| 02/10/2014 |
103673543 |
28 |
A1 |
P APPROVED |
02/14/2014 |
0620631 PE |
DIBARI |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 03
|
|
Work on Floor(s): CEL,ROF 001 thru 019
|
| 08/09/2013 |
103673543 |
27 |
A1 |
P APPROVED |
08/13/2013 |
0620631 PE |
DIBARI |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 03
|
|
Work on Floor(s): CEL,ROF 001 thru 019
|
| 08/07/2013 |
103673543 |
26 |
A1 |
P APPROVED |
08/13/2013 |
|
NEWMAN |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,ROF 001 thru 019
|
| 05/13/2013 |
103673543 |
25 |
A1 |
P APPROVED |
05/15/2013 |
|
NEWMAN |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,ROF 001 thru 019
|
| 04/01/2013 |
103673543 |
24 |
A1 |
P APPROVED |
04/03/2013 |
0620631 PE |
DIBARI |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 03
|
|
Work on Floor(s): CEL,ROF 001 thru 019
|
| 03/21/2013 |
110059775 |
03 |
A2 |
P APPROVED |
03/22/2013 |
|
DiBari |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): SUB 001 thru 010
|
| 02/07/2013 |
121403276 |
02 |
A3 |
P APPROVED |
02/07/2013 |
|
HOQUE |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): OSP
|
| 02/07/2013 |
103673543 |
23 |
A1 |
P APPROVED |
02/07/2013 |
0620631 PE |
DIBARI |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 03
|
|
Work on Floor(s): CEL,ROF 001 thru 019
|
| 02/04/2013 |
103673543 |
22 |
A1 |
P APPROVED |
02/06/2013 |
|
NEWMAN |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): SUB,CEL,ROF 001 thru 019
|
| 02/01/2013 |
121523093 |
01 |
A2 |
X SIGNED OFF |
02/06/2019 |
0620631 PE |
DIBARI |
|
NOT APPLICABLE
|
|
FILING FOR INSTALLATION OF BOILER IN CONJUNCTION WITH ALT 1 APPLICATION #
|
|
Work on Floor(s): CEL,ROF 001 thru 019
|
| 01/22/2013 |
103673543 |
21 |
A1 |
P APPROVED |
01/23/2013 |
0620631 PE |
DIBARI |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 03
|
|
Work on Floor(s): CEL,ROF 001 thru 019
|
| 01/16/2013 |
103673543 |
20 |
A1 |
P APPROVED |
01/17/2013 |
0620631 PE |
DIBARI |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 03
|
|
Work on Floor(s): CEL,ROF 001 thru 019
|
| 01/14/2013 |
103673543 |
19 |
A1 |
P APPROVED |
01/15/2013 |
0620631 PE |
DIBARI |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 03
|
|
Work on Floor(s): CEL,ROF 001 thru 019
|
| 11/19/2012 |
103673543 |
18 |
A1 |
P APPROVED |
01/17/2013 |
0060728 PE |
SMILOW |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 02
|
|
Work on Floor(s): SUB,CEL,ROF 001 thru 010
|
| 10/09/2012 |
121403276 |
01 |
A3 |
R PERMIT-ENTIRE |
10/09/2012 |
0083278 PE |
HOQUE |
Y |
NOT APPLICABLE
|
|
INSTALLATION OF PIPE SCAFFOLD AS PER PLANS. ALL WORK SHALL BE ACCORDING TO
|
|
Work on Floor(s): OSP
|
| 08/30/2012 |
121361506 |
01 |
SC |
U COMPLETED |
10/01/2012 |
0015609 RA |
NEWMAN |
|
NOT APPLICABLE
|
|
FILING CONDO LOT SUBDIVISION, CONDO LOTS 1001-1016
|
|
Work on Floor(s): 001 thru 019
|
| 08/09/2012 |
121337570 |
01 |
A3 |
P APPROVED |
11/21/2012 |
0015609 RA |
NEWMAN |
|
NOT APPLICABLE
|
|
FILING FIRE PROTECTION PLAN IN RELATION TO ALTERATION 1 APPLICATION #10367
|
|
Work on Floor(s): SUB,CEL,ROF 001 thru 019
|
| 07/13/2012 |
121150379 |
01 |
A3 |
X SIGNED OFF |
02/19/2015 |
0066791 PE |
PARIHAR |
|
NOT APPLICABLE
|
|
PROPOSED INSTALLATION OF PIPE SCAFFOLD FOR REMEDIAL REPAIRS AS PER PLANS.
|
|
Work on Floor(s): OSP
|
| 06/14/2012 |
120319878 |
03 |
A3 |
P APPROVED |
06/18/2012 |
|
SHAPIRO |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): ROF 001 thru 019
|
| 02/02/2012 |
103673543 |
17 |
A1 |
P APPROVED |
02/08/2012 |
|
NEWMAN |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): SUB,CEL,ROF 001 thru 019
|
| 01/03/2012 |
120178100 |
02 |
A3 |
P APPROVED |
01/04/2012 |
|
PITERA |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): OSP
|
| 09/21/2011 |
110455560 |
02 |
A3 |
P APPROVED |
09/21/2011 |
|
HOQUE |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): OSP
|
| 08/09/2011 |
120788772 |
01 |
A3 |
X SIGNED OFF |
02/19/2015 |
0072827 PE |
PITERA |
|
NOT APPLICABLE
|
|
INSTALLATION A PIPE SCAFFOLD AS PER PLAN AT 67 LIBERTY STREET. DURING REME
|
|
Work on Floor(s): OSP
|
| 07/28/2011 |
110059775 |
02 |
A2 |
P APPROVED |
07/29/2011 |
|
DiBari |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): SUB 001 thru 010
|
| 06/30/2011 |
103673543 |
16 |
A1 |
P APPROVED |
07/08/2011 |
0620631 PE |
DIBARI |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 03
|
|
Work on Floor(s): SUB,CEL,ROF 001 thru 010
|
| 06/22/2011 |
103673543 |
15 |
A1 |
P APPROVED |
06/23/2011 |
0060728 PE |
SMILOW |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 02
|
|
Work on Floor(s): SUB,CEL,ROF 001 thru 010
|
| 05/14/2011 |
103673543 |
14 |
A1 |
D A/P ENTIRE |
05/17/2011 |
0060728 PE |
SMILOW |
|
NOT APPLICABLE
|
|
DOC WITHDRAWN 01/25/2012
|
|
Work on Floor(s): SUB,CEL,ROF 001 thru 010
|
| 05/14/2011 |
120319878 |
02 |
A3 |
P APPROVED |
05/16/2011 |
|
SHAPIRO |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): ROF 001 thru 019
|
| 02/24/2011 |
103673543 |
13 |
A1 |
P APPROVED |
03/16/2011 |
0015609 RA |
Newman |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): SUB,CEL,ROF 001 thru 010
|
| 02/10/2011 |
103673543 |
12 |
A1 |
P APPROVED |
02/10/2011 |
0015609 RA |
Newman |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): SUB,CEL,ROF 001 thru 010
|
| 04/21/2010 |
120325665 |
01 |
A3 |
X SIGNED OFF |
02/19/2015 |
0072827 PE |
PITERA |
|
NOT APPLICABLE
|
|
INSTALLATION OF OVERHEAD ROOF PROTECTION AS PER DRAWINGS. OVERHEAD ROOF
|
|
Work on Floor(s): OSP
|
| 04/12/2010 |
120319878 |
01 |
A3 |
X SIGNED OFF |
10/07/2013 |
0060597 PE |
SHAPIRO |
|
NOT APPLICABLE
|
|
INSTALLATION OF AN ALIMAK SCANDO 20/30 TD SN#20811 PERSONNEL/MATERIAL HOIS
|
|
Work on Floor(s): ROF 001 thru 019
|
| 10/19/2009 |
120178100 |
01 |
A3 |
X SIGNED OFF |
03/05/2015 |
0072827 PE |
PITERA |
|
NOT APPLICABLE
|
|
INSTALLATION OF OVERHEAD ROOF PROTECTION AS PER DRAWINGS. OVERHEAD ROOF
|
|
Work on Floor(s): OSP
|
| 08/26/2009 |
120140392 |
01 |
A2 |
X SIGNED OFF |
12/20/2018 |
0620631 PE |
DIBARI |
|
NOT APPLICABLE
|
|
PROPOSE TO FILE FOR THE NEW TEMPORAL 3 CODED FIRE ALARM SYSTEM AS PER PLAN
|
|
Work on Floor(s): CEL,ROF 001 thru 019
|
| 07/15/2009 |
120105233 |
01 |
A3 |
X SIGNED OFF |
10/19/2010 |
0060597 PE |
SHAPIRO |
|
NOT APPLICABLE
|
|
INSTALLATION OF AN ALIMAK SCANDO 20/30 TD SN#20811 PERSONNEL/ MATERIAL HOI
|
|
Work on Floor(s): ROF 001 thru 019
|