BIS Menu  |  Electrical Inspection Work Order   FAQs  |  Glossary   
DOB Logo - Link to Homepage NYC.gov Logo - Link to Homepage
NYC Department of Buildings
Electrical Application Details for App #: Y148792
NO PRE-BIS PLACE OF ASSEMBLY CERTIFICATES FOUND
Premises: 80 STRONG STREET BRONX BIN: 2015301     Block: 3249   Lot: 25
   

Filed: 80 STRONG ST Census Tract:   267 Health Area:  0320
STREET LEVEL Admin Area:   Y - BRONX Inspection Area:   F
BRONX, NY 10468 Community Board:   208
DOB Cross Street(s):   GOULDEN AVENUE,    UNIVERSITY AVENUE
Status:   C - SIGNOFF IS AWAITING FEE PAYMENT 09/27/2013
Request Type:   A - APPLICATION eFiled:   YES Permit Issued:  10/22/2009 9:28 PM
Application Entered:   10/22/2009 Job Start Date:   10/24/2009
Last Change:   09/27/2013 Job End Date:   07/16/2010
Appointment Status:   
Last Inspection By:   IACOPETTA, JOSEPH       On     09/26/2013      
Field Disp:   C - INSPECTION PASSED
Energize Recommendation:  
Objection Disposition:  

License #: 011662 Licensee Name: HAZRAT ALLY
Firm: 003227 Firm Name: H & D ELECTRICAL CORP.
Firm Phone: 718-343-0239  Firm Address: 206-19 JAMAICA AVENUE JAMAICA NY 11428 

Work Started or Filed by Others: NO
Work Category:   R - REHABILITATION Work To Be Done:  
W - SIDEWALK SHED WIRING & LIGHTING
Total Fee:  $40.00
Other Work:   
Work Related to a New or Amended Certificate of Occupancy:   NO
This Job Regulated by the NYC Energy Conservation Code:  
Building Used As:   L - Five Or More Family
Special Cert Approval:  
Advisory Board Approval:   NOT APPLICABLE
Owner / Occup: SARBJIT KAUR
Owner Business Name: P.J.B CONTRACTING CORP
Authorized Representative:   
Relationship To Owner:   


WORK DESCRIPTION
BUILDING OVERVIEW Are Feeders Being Installed? :   No
(If feeders are being installed, provide a wiring diagram and calculations at the time of inspection)
Building Overview Work Items QUANTITY DESCRIPTION
SERVICE SWITCHES  
A. Up to 100 AMPS  0  
B. 101 Up to 200 AMPS  0  
C. 201 Up to 600 AMPS  0  
D. 601 Up to 1200 AMPS  0  
E. Over 1200 AMPS  0  
SER. ENT. & FDR COND (EACH SET)  
A. Up to #2 CONDUCTOR  0  
B. Over #2 to 1/0  0  
C. Over 1/0 to 250 MCM  0  
D. Over 250 MCM  0  
PANELS  
A. 1 Phase Up to 20-1 or 10-2 Pole Brkrs  0  
B. 1 Phase Over to 21-1 or 10-2 Pole Brkrs  0  
C. 3 Phase Up to 225 AMPS  0  
D. 3 Phase Over 225 AMPS  0  
ELEVATORS / ESCALATORS / MATERIAL LIFTS  
A. Total No. of Elevators / Escalators / Material Lifts  0  
B. Each Additional 10 Floors Or Less  0  
BOILER CONTROLS  0  

FLOOR DESCRIPTIONS
Floor Apt. Number Of Outlets No. Of
Fixtures
Motors / Generators Heaters Transformers
Fixt Receptacles Switch Num Total HP KW Num Total KW Num Total KVA
ATT A/C
GND                     
Buildings Total                     
Total Units : 8 units   

Signs: Field Connect: 0 Field Inspect: 0 Tags:

SERVICE / METER EQUIPMENT
Meter Request to Utility #3-Wire 0 #4-Wire 0 #10-Wire 0
Existing Meters 0 + New Meters 0 - Removed Meters 0 = Total Meters 0

Power Auth Flag: Objection Flag:
Power Requested: Notice:  
Power Issued: Response:  

Follow-Up: K - (CLOSED)
Contractor's Comments:  INSTALL SIDEWALK SHED LIGHTS.

 
Inspection Details
 

*NO PRE-BIS PLACE OF ASSEMBLY CERTIFICATES FOUND
INSPECTION FOR APPLICATION #: Y148792
INSP
ID
FIELD
DATE
DISP
DATE
INSP
ID
FLD
DISP
OBJ
DISP
ENRG
REC
TIME
INSP
REINSP
DATE
NEW
OBJ
APPT
FLAG
 
(1) 09/26/2013 09/27/2013 JIC C (15) (0) Y
INSPECTION COMMENTS: CERT- SHED REMOVED




If you have any questions please review these Frequently Asked Questions, the Glossary, or call the 311 Citizen Service Center by dialing 311 or (212) NEW YORK outside of New York City.


BIS Menu  |  Electrical Inspection Work Order