BIS Menu  |  Elevators  |  Electrical Applications  |  Electrical Inspection Work Order  |  Back   FAQs  |  Glossary   
DOB Logo - Link to Homepage NYC.gov Logo - Link to Homepage
NYC Department of Buildings
Electrical Application Details for App #: Z068586
NO PRE-BIS PLACE OF ASSEMBLY CERTIFICATES FOUND
Premises: 113 WEST 106 STREET MANHATTAN BIN: 1055962     Block: 1861   Lot: 25
   
Application Completed and Certified

Filed: 113 W 106 ST Census Tract:   193 Health Area:  2320
2 5 6,1FLR REAR Admin Area:   Z - UPPER MANHATTAN Inspection Area:   C
NEW YORK, NY 10025 Community Board:   107
DOB Cross Street(s):   COLUMBUS AVENUE,    AMSTERDAM AVENUE
Status:   C - JOB IS SIGNED OFF 04/22/2004
Request Type:   C - COMPLAINT eFiled:   NO
Application Entered:   02/25/2004 Job Start Date:   02/23/2004
Last Change:   04/27/2004 Job End Date:   06/01/2004
Appointment Status:   
Last Inspection By:   PETER GREENE       On     04/20/2004      
Field Disp:   C - INSPECTION PASSED
Energize Recommendation:  
Objection Disposition:  R - REMOVED

License #: 011471 Licensee Name: PHONG NGUYEN
Firm: 002935 Firm Name: PHONG ELECTRIC INC.
Firm Phone: 718-686-0013  Firm Address: 252 JAVA STREET STE 113B BROOKLYN NY 11222 

Work Started or Filed by Others: NO
Work Category:   R - REHABILITATION Work To Be Done:  
6 - GENERAL WIRING
9 - OTHER
Total Fee:  $40.00
Other Work:   REMOVAL OF VIOLATION
Work Related to a New or Amended Certificate of Occupancy:   NO
This Job Regulated by the NYC Energy Conservation Code:  
Building Used As:   C - Three Family
Special Cert Approval:  
Advisory Board Approval:  
Owner / Occup: NASSER FAHADIAN
Owner Business Name: FARAGON
Authorized Representative:   
Relationship To Owner:   


WORK DESCRIPTION
BUILDING OVERVIEW Are Feeders Being Installed? :   
(If feeders are being installed, provide a wiring diagram and calculations at the time of inspection)
Building Overview Work Items QUANTITY DESCRIPTION
SERVICE SWITCHES  
A. Up to 100 AMPS  0  
B. 101 Up to 200 AMPS  0  
C. 201 Up to 600 AMPS  0  
D. 601 Up to 1200 AMPS  0  
E. Over 1200 AMPS  0  
SER. ENT. & FDR COND (EACH SET)  
A. Up to #2 CONDUCTOR  0  
B. Over #2 to 1/0  0  
C. Over 1/0 to 250 MCM  0  
D. Over 250 MCM  0  
PANELS  
A. 1 Phase Up to 20-1 or 10-2 Pole Brkrs  0  
B. 1 Phase Over to 21-1 or 10-2 Pole Brkrs  0  
C. 3 Phase Up to 225 AMPS  0  
D. 3 Phase Over 225 AMPS  0  
ELEVATORS / ESCALATORS / MATERIAL LIFTS  
A. Total No. of Elevators / Escalators / Material Lifts  0  
B. Each Additional 10 Floors Or Less  0  
BOILER CONTROLS  0  

FLOOR DESCRIPTIONS
Floor Apt. Number Of Outlets No. Of
Fixtures
Motors / Generators Heaters Transformers
Fixt Receptacles Switch Num Total HP KW Num Total KW Num Total KVA
ATT A/C
Buildings Total                       
Total Units : 1 units   

Signs: Field Connect: 0 Field Inspect: 0 Tags:

SERVICE / METER EQUIPMENT
Meter Request to Utility #3-Wire 0 #4-Wire 0 #10-Wire 0
Existing Meters 0 + New Meters 0 - Removed Meters 0 = Total Meters 0

Power Auth Flag: Objection Flag:
Power Requested: Notice:  11/25/1997
Power Issued: Response: F - FILED TO REMOVE OBJECTION 02/25/2004

Follow-Up: X - FILED APPL,NOW CLOSED 02/25/2004
Contractor's Comments:  

 
Inspection Details
 

*NO PRE-BIS PLACE OF ASSEMBLY CERTIFICATES FOUND
INSPECTION FOR APPLICATION #: Z068586
INSP
ID
FIELD
DATE
DISP
DATE
INSP
ID
FLD
DISP
OBJ
DISP
ENRG
REC
TIME
INSP
REINSP
DATE
NEW
OBJ
APPT
FLAG
 
(1) 12/17/1996 12/27/1996 RID W (45) (2)
INSPECTION COMMENTS: No Inspection Comments For This Application
 
(4) 11/25/1997 12/01/1997 RID F (15) (0)
INSPECTION COMMENTS: No Inspection Comments For This Application
 
(5) 04/20/2004 04/22/2004 PGR C R (25) (0) Y
INSPECTION COMMENTS: No Inspection Comments For This Application