BIS Menu  |  Marquee Query  |  Electrical Inspection Work Order  |  Back   FAQs  |  Glossary   
DOB Logo - Link to Homepage NYC.gov Logo - Link to Homepage
NYC Department of Buildings
Electrical Application Details for App #: M388486
NO PRE-BIS PLACE OF ASSEMBLY CERTIFICATES FOUND
Premises: 475 BROADWAY MANHATTAN BIN: 1007051     Block: 474   Lot: 7505
   

DOB NOW: Inspections

Application Completed and Certified

Filed: 475 BROADWAY Census Tract:   47 Health Area:  6800
475 BROADWAY Admin Area:   M - MANHATTAN Inspection Area:   U
NEW YORK, NY 10013 Community Board:   102
DOB Cross Street(s):   GRAND STREET,    BROOME STREET
Status:   C - JOB IS SIGNED OFF 02/09/2018
Request Type:   A - APPLICATION eFiled:   YES Permit Issued:  11/02/2016 8:58 AM
Application Entered:   11/02/2016 Job Start Date:   11/02/2016
Last Change:   02/09/2018 Job End Date:   11/07/2016
Appointment Status:   
Last Inspection By:   CAMPBELL, C       On     11/03/2017      
Field Disp:   C - INSPECTION PASSED
Energize Recommendation:  
Objection Disposition:  R - REMOVED

License #: 010373 Licensee Name: PATSY L RICCI
Firm: 004559 Firm Name: NETWORK ONE ELECL CONTNG
Firm Phone: 718-792-4733  Firm Address: 2526A BUTLER PLACE BRONX NY 10461 

Work Started or Filed by Others: NO
Work Category:   R - REHABILITATION Work To Be Done:  
6 - GENERAL WIRING
Total Fee:  $40.00
Other Work:   
Work Related to a New or Amended Certificate of Occupancy:   NO
This Job Regulated by the NYC Energy Conservation Code:   No
Building Used As:   K - Store
Store / Other:   RETAIL
Special Cert Approval:  
Advisory Board Approval:   NOT APPLICABLE
Owner / Occup: RICHARD CIALLELLA
Owner Business Name: 475 BROADWAY SOHO LLC
Authorized Representative:  RICHARD CIALLELLA
Relationship To Owner:   PROPERTY MANAGER


WORK DESCRIPTION
BUILDING OVERVIEW Are Feeders Being Installed? :   No
(If feeders are being installed, provide a wiring diagram and calculations at the time of inspection)
Building Overview Work Items QUANTITY DESCRIPTION
SERVICE SWITCHES  
A. Up to 100 AMPS  0  
B. 101 Up to 200 AMPS  0  
C. 201 Up to 600 AMPS  0  
D. 601 Up to 1200 AMPS  0  
E. Over 1200 AMPS  0  
SER. ENT. & FDR COND (EACH SET)  
A. Up to #2 CONDUCTOR  0  
B. Over #2 to 1/0  0  
C. Over 1/0 to 250 MCM  0  
D. Over 250 MCM  0  
PANELS  
A. 1 Phase Up to 20-1 or 10-2 Pole Brkrs  0  
B. 1 Phase Over to 21-1 or 10-2 Pole Brkrs  0  
C. 3 Phase Up to 225 AMPS  0  
D. 3 Phase Over 225 AMPS  0  
ELEVATORS / ESCALATORS / MATERIAL LIFTS  
A. Total No. of Elevators / Escalators / Material Lifts  0  
B. Each Additional 10 Floors Or Less  0  
BOILER CONTROLS  0  

FLOOR DESCRIPTIONS
Floor Apt. Number Of Outlets No. Of
Fixtures
Motors / Generators Heaters Transformers
Fixt Receptacles Switch Num Total HP KW Num Total KW Num Total KVA
ATT A/C
BAS                  10     
Buildings Total                   10      
Total Units : 10 units   

Signs: Field Connect: 0 Field Inspect: 0 Tags:

SERVICE / METER EQUIPMENT
Meter Request to Utility #3-Wire 0 #4-Wire 0 #10-Wire 0
Existing Meters 0 + New Meters 0 - Removed Meters 0 = Total Meters 0

Power Auth Flag: Objection Flag:
Power Requested: Notice: 1 - FIRST NOTICE 10/19/2017
Power Issued: Response:  

Follow-Up: K - (CLOSED)
Contractor's Comments:  

 
Inspection Details
 

*NO PRE-BIS PLACE OF ASSEMBLY CERTIFICATES FOUND
INSPECTION FOR APPLICATION #: M388486
INSP
ID
FIELD
DATE
DISP
DATE
INSP
ID
FLD
DISP
OBJ
DISP
ENRG
REC
TIME
INSP
REINSP
DATE
NEW
OBJ
APPT
FLAG
 
(1) 10/18/2017 10/19/2017 STP V (45) (1)
INSPECTION COMMENTS: FAIL. CONTRACTOR HAD NO TOOL TO OPEN HEATER. HEATER NOT INSPECTED.
 
(2) 11/03/2017 11/06/2017 CLC C R (30) (0)
INSPECTION COMMENTS: INSPECTION PASS

OBJECTION FOR APPLICATION #: M388486
OBJECTION ID OBJECTION CODE OBJECTION DESCRIPTION & COMMENTS STAT FIRST LATEST RESLVD
 
001 (999) OTHER
(BASEMENT) HEATERS NO DISCONNECT MEANS PROVIDED 424.19
RSLV 10/18/2017 10/18/2017 11/03/2017



If you have any questions please review these Frequently Asked Questions, the Glossary, or call the 311 Citizen Service Center by dialing 311 or (212) NEW YORK outside of New York City.


BIS Menu  |  Marquee Query  |  Electrical Inspection Work Order  |  Back