BIS Menu  |  Applications  |  Property Permits  |  Back   FAQs  |  Glossary   
DOB Logo - Link to Homepage NYC.gov Logo - Link to Homepage
NYC Department of Buildings
Job Overview
NO PREVIOUSLY ISSUED PERMITS FOUND FOR THIS PROPERTY
Page: 1 of 1
Premises: 106 FRANKLIN STREET MANHATTAN BIN: 1001981    Block: 178    Lot: 6

To start overview at new date, select Month:   Day:   Year:  

         

FILE DATE JOB # DOC # JOB TYPE JOB STATUS STATUS DATE LIC # APPLICANT IN AUDIT ZONING APPROVAL
06/28/2022 121241227 14 A1 P APPROVED 06/30/2022 BERNSTEI GRANTED 03/02/2018
 POST APPROVAL AMENDMENT FOR 01
 Work on Floor(s): CEL,ROF 001 thru 005

03/08/2022 121241227 13 A1 P APPROVED 03/31/2022 BERNSTEI GRANTED 03/02/2018
 POST APPROVAL AMENDMENT FOR 01
 Work on Floor(s): CEL,ROF 001 thru 005

08/09/2021 121241227 12 A1 P APPROVED 11/22/2021 BERNSTEI GRANTED 03/02/2018
 POST APPROVAL AMENDMENT FOR 01
 Work on Floor(s): CEL,ROF 001 thru 005

09/03/2020 121241227 11 A1 P APPROVED 11/18/2020 BERNSTEI GRANTED 03/02/2018
 POST APPROVAL AMENDMENT FOR 01
 Work on Floor(s): CEL,ROF 001 thru 005

06/05/2020 121241227 10 A1 P APPROVED 08/14/2020 0016854 RA BERNSTEI GRANTED 03/02/2018
 POST APPROVAL AMENDMENT FOR 01
 Work on Floor(s): CEL,ROF 001 thru 005

02/18/2020 121241227 09 A1 P APPROVED 02/21/2020 0071681 PE TUCCI GRANTED 03/02/2018
 POST APPROVAL AMENDMENT FOR 02
 Work on Floor(s): UDG,CEL,ROF,OSP 001 thru 005

10/18/2019 121241227 08 A1 P APPROVED 10/18/2019 0071681 PE TUCCI GRANTED 03/02/2018
 POST APPROVAL AMENDMENT FOR 02
 Work on Floor(s): UDG,CEL,ROF,OSP 001 thru 005

09/12/2019 121241227 07 A1 P APPROVED 10/18/2019 0071681 PE TUCCI GRANTED 03/02/2018
 POST APPROVAL AMENDMENT FOR 02
 Work on Floor(s): UDG,CEL,ROF,OSP 001 thru 005

09/11/2019 140672270 02 A2 P APPROVED 10/17/2019 TUCCI NOT APPLICABLE
 POST APPROVAL AMENDMENT FOR 01
 Work on Floor(s): CEL,OSP,ROF 001 thru 005

08/26/2019 121241227 06 A1 P APPROVED 08/29/2019 0060234 PE CAMBOURA GRANTED 03/02/2018
 POST APPROVAL AMENDMENT FOR 03
 Work on Floor(s): CEL,ROF,OSP 001 thru 005

08/20/2019 121241227 05 A1 P APPROVED 08/22/2019 0016854 RA BERNSTEI GRANTED 03/02/2018
 POST APPROVAL AMENDMENT FOR 01
 Work on Floor(s): CEL,ROF 001 thru 005

06/21/2019 123872728 01 A2 X SIGNED OFF 02/19/2021 0060234 PE CAMBOURA NOT APPLICABLE
 FILING FOR PROPOSED ADDITIONAL STRUCTURAL SUPPORT ON FIRST FLOOR AND SIDEW
 Work on Floor(s): 001,OSP

11/28/2017 123174117 01 A2 X SIGNED OFF 05/09/2018 0016854 RA BERNSTEI NOT APPLICABLE
 TEMPORARY MOCK UP AS SHOWN ON PLANS.
 Work on Floor(s): ROF

07/24/2017 121241227 04 A1 X SIGNED OFF 07/07/2022 0060234 PE CAMBOURA GRANTED 03/02/2018
 SUPPORT OF EXCAVATION WORK
 Work on Floor(s): OSP,CEL,001

07/24/2017 121241227 03 A1 X SIGNED OFF 07/07/2022 0060234 PE CAMBOURA GRANTED 03/02/2018
 STRUCTURAL AND FOUNDATION WORK AS SHOWN ON PLANS FILED HEREWITH
 Work on Floor(s): CEL,ROF,OSP 001 thru 005

07/24/2017 123345870 01 A2 X SIGNED OFF 07/21/2020 0071681 PE TUCCI NOT APPLICABLE
 AUTOMATIC SMOKE/HEAT CO DETECTION SPRINKLER ALARM SYSTEM.
 Work on Floor(s): CEL,ROF 001 thru 005

07/24/2017 121241227 02 A1 X SIGNED OFF 07/07/2022 0071681 PE TUCCI GRANTED 03/02/2018
 MECHANICAL AND PLUMBING WORK AS SHOWN ON PLANS FILED HEREWITH
 Work on Floor(s): UDG,CEL,ROF,OSP 001 thru 005

07/21/2017 140672270 01 A2 X SIGNED OFF 12/31/2019 0071681 PE TUCCI NOT APPLICABLE
 MODIFICATION TO EXISTING SPRINKLER SYSTEM AS SHOWN ON PLANS FILED HEREWITH
 Work on Floor(s): CEL,OSP,ROF 001 thru 005

06/01/2017 121241227 01 A1 X SIGNED OFF 07/07/2022 0016854 RA BERNSTEI GRANTED 03/02/2018
 INSTALL NEW ELEVATOR STAIR. CONVERSION OF BUILDING FROM COMMERCIAL TO
 Work on Floor(s): CEL,ROF 001 thru 005

05/26/2017 121231247 01 A2 X SIGNED OFF 10/17/2018 0016854 RA BERNSTEI NOT APPLICABLE
 APPLICATION FILED FOR DEMOLITION OF INTERIOR NON-BEARING PARTITIONS AND RE
 Work on Floor(s): CEL 001 thru 005

10/22/2012 121417644 01 A3 X SIGNED OFF 10/18/2013 0089902 PE NINNISAI NOT APPLICABLE
 INSTALLATION OF SIDEWALK SHED AS PER PLANS. WORK SHALL COMPLY WITH 2008 BU
 Work on Floor(s): OSP

05/01/2012 121063491 01 A2 J P/E DISAPPROVED 08/03/2012 0076805 PE CHRYSLER NOT APPLICABLE
 JOB WITHDRAWN 10/05/2012 INSTALL HOSE RACK ON EXISTING SPRINKLER SYSTEM FI
 Work on Floor(s): CEL,OSP 001 thru 005

06/23/2011 120260886 02 A2 J P/E DISAPPROVED 05/08/2012 CHRYSLER NOT APPLICABLE
 DOC WITHDRAWN 07/12/2020
 Work on Floor(s): CEL,001,002,003,OSP

02/08/2010 120260886 01 A2 R PERMIT-ENTIRE 03/02/2016 0076805 PE CHRYSLER NOT APPLICABLE
 JOB WITHDRAWN 07/12/2020 FILE FOR SPRINKLER SYSTEM AS PER PLANS. NO CHANGE
 Work on Floor(s): CEL,001,002,003,OSP



If you have any questions please review these Frequently Asked Questions, the Glossary, or call the 311 Citizen Service Center by dialing 311 or (212) NEW YORK outside of New York City.

BIS Menu  |  Applications  |  Property Permits  |  Back