| NYC Department of Buildings | ||
| Overview for Complaint #:3A60665 = RESOLVED | ||
| Complaint at: 275 ATLANTIC AVENUE | BIN: 3000605 | Borough: BROOKLYN | ZIP: 11201 | |||
| Re: I reporting this city project that is causing a great deal of inconvenience(have been going on for years) from fire proofing materials, construction debris/dirt that is blowing unto our patio, we have kids and this is not safe. The netting that they have is not effective-does not work. We need DOB to come by and see exactly what is taking place, because have kids playing close by. ped netting-orange foam--This building way taller than our our building and you can just imagine all of that dust and debris blowing(no netting) these materials are toxic. Please assist | ||||||
| Category Code: | 03 ADJACENT BUILDINGS - NOT PROTECTED | |
| CONSTRUCTION IN PROGRESS : ADJACENT BUILDING UNPROTECTED - NETTING MISSING | ||
| Assigned To: | CONSTRUCTION SAFETY ENFORCMENT | Priority: A |
| 311 Reference Number: 311-27379019 | ||
| Received: | 05/05/2026 | Block: 175 | Lot: 1 | Community Board: 302 | ||
| Owner: | DEPARTMENT OF CORRECTIONS 60 | |||||
| Last Inspection: | 05/08/2026 - - BY BADGE # 3149 |
| Disposition: | 05/08/2026 - L2 - STOP WORK ORDER FULLY RESCINDED |
| Comments: | Means and method for safe garbage disposal and cleaning operation was provided, the broken safety netting was replaced and stop work order was full rescinded |
| Prev ECB Violation #: | 39553850J |
| Complaint Disposition History |
| # | Disposition | Disposition | Inspection | Date | |
| Date | Code | By | |||
| 3 | 05/08/2026 | L2 | STOP WORK ORDER FULLY RESCINDED | 3149 | 05/08/2026 |
| Means and method for safe garbage disposal and cleaning operation was provided, the broken safety netting was replaced and stop work order was full rescinded | |||||
| 2 | 05/06/2026 | L1 | PARTIAL STOP WORK ORDER | 3149 | 05/06/2026 |
| Time of inspection in response to complaint where construction debris fallen into a building at 53 Boerum place roof and patio, inspection reveal inadequate house keeping and safety netting on the jobsite, failure to provide and maintain adequate safety measure during construction activities led to the incident this creates unsafe condition Stop all work on exposure #2 15 feet back from 9th floor to top floor provide adequate safety measures going forward and request CSE for re inspection #2555 | |||||
| 1 | 05/06/2026 | EJ | COMPLAINT ASSIGNED TO CONSTRUCTION SAFETY ENFORCEMENT | 2283 | 05/06/2026 |
| REFER TO CSE 17 STY NB | |||||