Disposition |
Disposition |
Inspection |
Date |
|
Date |
Code |
By |
|
| 6 |
03/08/2023 |
L2 |
STOP WORK ORDER FULLY RESCINDED |
3343 |
03/07/2023 |
| |
|
|
ADJACENT PROPERTY WALL AT EXPOSURE 4 HAS BEEN COMPLETED WITH ENGINEERS REPORT ON ISTE AND VERIFIED |
|
| 5 |
02/24/2023 |
L1 |
PARTIAL STOP WORK ORDER |
2456 |
01/31/2023 |
| |
|
|
***CSE SEE CHIEF B4 L2 JDRIVE SWO NOTES*** |
|
| 4 |
01/31/2023 |
L1 |
PARTIAL STOP WORK ORDER |
2456 |
01/31/2023 |
| |
|
|
***CSE ENGINER AUDIT/SEE CHIEF B4 L2 JDRIVE SWO NOTES*** |
|
| 3 |
01/07/2022 |
L1 |
PARTIAL STOP WORK ORDER |
2748 |
12/31/2021 |
| |
|
|
PARTY WALL DAMAGED DUE TO JOIST INSTALLATION. ONLY WORK ALLO WED IS INSTALLATION OF WALL BRACING 2ND FLR **CSE AUDIT 3076 |
|
| 2 |
01/07/2022 |
L1 |
PARTIAL STOP WORK ORDER |
2748 |
12/31/2021 |
| |
|
|
PARTY WALL DAMAGED DUE TO JOIST INSTALLATION INSTALLATION OF WALL BRACING 2ND FLR ONLY **CSE AUDIT 3076** |
|
| 1 |
12/31/2021 |
L1 |
PARTIAL STOP WORK ORDER |
2748 |
12/31/2021 |
| |
|
|
L1- AT TIME OF INSPECTION OBSERVED ADJACENT BUILDING (160 MOFFAT ST ) PARTY WALL DAMAGED DUE TO JOIST INSTALLATION. PARTY WALL DAMAGED WITH HOLE AND RAIN WATER SIPPING INTO ADJACENT BUILDING FROM ROOF LEVEL AS EXISTING ROOF HAS BEEN REMOVED WITHOUT ANY TEMPORARY PROTECTION. A PARTIAL STOP WORK ORDER ISSUED ON ALL STRUCTURAL WORK. |
|