Disposition |
Disposition |
Inspection |
Date |
|
Date |
Code |
By |
|
| 4 |
10/06/2021 |
L2 |
STOP WORK ORDER FULLY RESCINDED |
3073 |
10/06/2021 |
| |
|
|
ALL VIOLATING CONDITIONS HAVE BEEN CORRECTED OK TO RESCIND |
|
| 3 |
10/05/2021 |
L3 |
STOP WORK ORDER PARTIALLY RESCINDED |
3284 |
09/30/2021 |
| |
|
|
PROV INSTALL INSP LETTER.OK TO WORK ON 9FL BUT NO USE OF NEEDLE BEAM OR SCAFF ON TOP OF NEEDLE BEAM **SEE 3076 PRIOR* |
|
| 2 |
09/30/2021 |
L3 |
STOP WORK ORDER PARTIALLY RESCINDED |
3284 |
09/30/2021 |
| |
|
|
PROV INSTALL INSP LETTER.OK TO WORK ON 9FL BUT NO USE OF NEEDLE BEAM OR SCAFF ON TOP OF NEEDLE BEAM @EXP2 NORTH/SOUTH |
|
| 1 |
09/28/2021 |
L1 |
PARTIAL STOP WORK ORDER |
3080 |
09/27/2021 |
| |
|
|
NO PERIMETER WORK EXPO 2 NO USE OF SCAFFOLD ON NEEDLE BEAMS, AMEND DRAWINGS, PROVIDE ADEQUATE HOUSEKEPING SECURE HOLES 9FL. |
|