| FILE DATE |
JOB # |
DOC # |
JOB TYPE |
JOB STATUS |
STATUS DATE |
LIC # |
APPLICANT |
IN AUDIT |
ZONING APPROVAL |
| 02/26/2020 |
321081306 |
11 |
NB |
P APPROVED |
02/27/2020 |
|
MALLEA |
|
GRANTED 06/04/2015
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,ROF 001 thru 008
|
| 01/15/2020 |
321081306 |
10 |
NB |
P APPROVED |
01/16/2020 |
|
MALLEA |
|
GRANTED 06/04/2015
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,ROF 001 thru 008
|
| 11/26/2019 |
321081306 |
09 |
NB |
P APPROVED |
11/29/2019 |
0062815 PE |
PATEL |
|
GRANTED 06/04/2015
|
|
POST APPROVAL AMENDMENT FOR 03
|
|
Work on Floor(s): CEL,ROF,OSP 001 thru 008
|
| 11/26/2019 |
340267428 |
02 |
A2 |
P APPROVED |
12/02/2019 |
|
PATEL |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,ROF,OSP 001 thru 008
|
| 09/27/2019 |
321081306 |
08 |
NB |
P APPROVED |
11/13/2019 |
0062815 PE |
PATEL |
|
GRANTED 06/04/2015
|
|
POST APPROVAL AMENDMENT FOR 03
|
|
Work on Floor(s): CEL,ROF 001 thru 008
|
| 09/27/2019 |
321081306 |
07 |
NB |
G PAA FEE DUE |
09/27/2019 |
0062815 PE |
PATEL |
|
GRANTED 06/04/2015
|
|
DOC WITHDRAWN 09/27/2019
|
|
Work on Floor(s): CEL,ROF 001 thru 008
|
| 02/12/2019 |
321118642 |
02 |
A2 |
P APPROVED |
02/27/2019 |
|
APAYDIN |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,ROF 001 thru 008
|
| 09/24/2018 |
321081306 |
06 |
NB |
P APPROVED |
06/05/2019 |
0062815 PE |
PATEL |
|
GRANTED 06/04/2015
|
|
POST APPROVAL AMENDMENT FOR 03
|
|
Work on Floor(s): CEL,ROF 001 thru 008
|
| 09/24/2018 |
321833094 |
01 |
SC |
U COMPLETED |
09/28/2018 |
0020506 RA |
MALLEA |
|
NOT APPLICABLE
|
|
HEREBY FILING FOR CONDOMINIUM SUBDIVISION IN CONJUNCTION WITH NB APPLICATI
|
|
Work on Floor(s): ALL
|
| 05/11/2017 |
340500050 |
01 |
A3 |
X SIGNED OFF |
10/31/2019 |
0094567 PE |
HAIDER |
|
NOT APPLICABLE
|
|
PROPOSED INSTALLATION OF TEMPORARY PIPE SCAFFOLD FOR NEW BUILDING AS PER P
|
|
Work on Floor(s): OSP
|
| 09/30/2016 |
321459300 |
01 |
A3 |
X SIGNED OFF |
12/09/2019 |
0088950 PE |
ACAR |
|
NOT APPLICABLE
|
|
INSTALLATION OF ROOF PROTECTION AS PER PLANS IN CONJUNCTION WITH NB
|
|
Work on Floor(s): ROF
|
| 09/06/2016 |
321446869 |
01 |
A3 |
X SIGNED OFF |
12/04/2019 |
0072914 PE |
AHMED |
|
NOT APPLICABLE
|
|
INSTALLATION OF A HEAVY DUTY SIDEWALK SHED APPROXIMATELY 150' LONG AS PER
|
|
Work on Floor(s): 001
|
| 05/03/2016 |
321081306 |
05 |
NB |
P APPROVED |
05/10/2016 |
0088621 PE |
AUYENG |
|
GRANTED 06/04/2015
|
|
POST APPROVAL AMENDMENT FOR 02
|
|
Work on Floor(s): CEL,ROF 001 thru 008
|
| 07/23/2015 |
321175928 |
01 |
A2 |
R PERMIT-ENTIRE |
11/24/2015 |
0062815 PE |
PATEL |
|
NOT APPLICABLE
|
|
JOB WITHDRAWN 12/31/2019 INSTALLATION OF MANUAL/AUTOMATIC SMOKE DETECTION
|
|
Work on Floor(s): 001
|
| 07/21/2015 |
340267428 |
01 |
A2 |
X SIGNED OFF |
01/02/2020 |
0062815 PE |
PATEL |
|
NOT APPLICABLE
|
|
INSTALLATION OF COMBINED SPRINKLER/STANDPIPE (CLASS 1) SYSTEM IN CONJUNCT
|
|
Work on Floor(s): CEL,ROF,OSP 001 thru 008
|
| 06/05/2015 |
321081306 |
04 |
NB |
X SIGNED OFF |
03/12/2020 |
0060229 PE |
BROOKER |
|
GRANTED 06/04/2015
|
|
FILING S.O.E. SPECIFICATIONS IN CONJUNCTION WITH NB
|
|
Work on Floor(s): CEL,ROF,OSP 001 thru 008
|
| 06/04/2015 |
340265698 |
01 |
A3 |
X SIGNED OFF |
09/11/2019 |
0083278 PE |
HOQUE |
|
NOT APPLICABLE
|
|
PROPOSED INSTALLATION OF HEAVY DUTY SIDEWALK SHED AS PER PLANS. LIVE LOAD
|
|
Work on Floor(s): OSP
|
| 06/04/2015 |
340265689 |
01 |
A3 |
X SIGNED OFF |
10/04/2019 |
0083278 PE |
HOQUE |
|
NOT APPLICABLE
|
|
PROPOSED INSTALLATION OF HEAVY DUTY SIDEWALK SHED AS PER PLANS. LIVE LOAD
|
|
Work on Floor(s): OSP
|
| 06/04/2015 |
340265670 |
01 |
A3 |
X SIGNED OFF |
10/31/2019 |
0083278 PE |
HOQUE |
|
NOT APPLICABLE
|
|
PROPOSED INSTALLATION OF HEAVY DUTY SIDEWALK SHED AS PER PLANS. LIVE LOAD
|
|
Work on Floor(s): OSP
|
| 05/29/2015 |
321081306 |
03 |
NB |
X SIGNED OFF |
03/12/2020 |
0062815 PE |
PATEL |
|
GRANTED 06/04/2015
|
|
MECHANICAL AND PLUMBING SPECIFICATIONS FILED SUBSEQUENT TO JOB # 321081306
|
|
Work on Floor(s): CEL,ROF,OSP 001 thru 008
|
| 05/06/2015 |
321118642 |
01 |
A2 |
X SIGNED OFF |
09/27/2019 |
0083782 PE |
APAYDIN |
|
NOT APPLICABLE
|
|
INSTALLATION OF AN AUTOMATIC SMOKE/HEAT DETECTION AND SPRINKLER FIRE ALARM
|
|
Work on Floor(s): CEL,ROF 001 thru 008
|
| 03/16/2015 |
321095961 |
01 |
A3 |
X SIGNED OFF |
11/01/2019 |
0020506 RA |
MALLEA |
|
NOT APPLICABLE
|
|
BPP FILED IN CONJUNCTION WITH NB, TOTAL STREET FRONTAGE 92'
|
|
Work on Floor(s): OSP
|
| 02/17/2015 |
321081306 |
02 |
NB |
X SIGNED OFF |
03/12/2020 |
0088621 PE |
AUYENG |
|
GRANTED 06/04/2015
|
|
FILING SOE, FOUNDING & STRUCTURAL SPECIFICATIONS IN CONJUNCTION WITH NB
|
|
Work on Floor(s): CEL,ROF 001 thru 008
|
| 02/03/2015 |
321081306 |
01 |
NB |
X SIGNED OFF |
03/12/2020 |
0020506 RA |
MALLEA |
|
GRANTED 06/04/2015
|
|
PROPOSED 8 STORY AND CELLAR RESIDENTIAL/COMMUNITY FACILITY BUILDING TOTAL
|
|
Work on Floor(s): CEL,ROF 001 thru 008
|