FILE DATE JOB # DOC # JOB TYPE JOB STATUS STATUS DATE LIC # APPLICANT IN AUDIT ZONING APPROVAL
11/05/2018 421696141 01 SC U COMPLETED 12/03/2018 0025376 RA TAN NOT APPLICABLE
 SUBDIVIDE THE CONDOMINIUM BUILDING FROM ONE ZONING LOT TO 37 TAX LOTS(FROM
 Work on Floor(s): CEL,ROF 001 thru 009

06/01/2018 420887570 11 NB P APPROVED 07/11/2018 0068607 PE YU GRANTED 08/28/2014
 POST APPROVAL AMENDMENT FOR 02
 Work on Floor(s): CEL 001 thru 008

03/08/2018 420887570 10 NB P APPROVED 04/02/2018 0073791 PE CHANG GRANTED 08/28/2014
 POST APPROVAL AMENDMENT FOR 04
 Work on Floor(s): CEL,OSP,ROF 001 thru 009

12/01/2017 420887570 09 NB P APPROVED 02/07/2018 TAN GRANTED 08/28/2014
 POST APPROVAL AMENDMENT FOR 01
 Work on Floor(s): CEL,ROF,OSP 001 thru 009

08/28/2017 421355054 02 A2 P APPROVED 10/30/2017 LAU NOT APPLICABLE
 POST APPROVAL AMENDMENT FOR 01 INSTALLATION OF AUTOMATIC SMOKE/HEAT/CO DET
 Work on Floor(s): CEL,ROF 001 thru 009

08/25/2017 420956530 02 A3 P APPROVED 10/24/2017 TAN NOT APPLICABLE
 POST APPROVAL AMENDMENT FOR 01
 Work on Floor(s): OSP

08/21/2017 420887570 08 NB P APPROVED 11/06/2017 0073791 PE CHANG GRANTED 08/28/2014
 POST APPROVAL AMENDMENT FOR 03
 Work on Floor(s): CEL,OSP,ROF 001 thru 009

07/31/2017 420887570 07 NB P APPROVED 08/08/2017 0073791 PE CHANG GRANTED 08/28/2014
 POST APPROVAL AMENDMENT FOR 04
 Work on Floor(s): CEL,OSP,ROF 001 thru 009

04/14/2017 420887570 06 NB P APPROVED 10/31/2017 TAN GRANTED 08/28/2014
 POST APPROVAL AMENDMENT FOR 01
 Work on Floor(s): CEL 001 thru 008

08/23/2016 420887570 05 NB P APPROVED 08/24/2016 0073791 PE CHANG GRANTED 08/28/2014
 POST APPROVAL AMENDMENT FOR 04
 Work on Floor(s): CEL,OSP,ROF 001 thru 009

07/29/2016 421355054 01 A2 X SIGNED OFF 02/07/2018 0074145 PE LAU NOT APPLICABLE
 INSTALLATION OF AUTOMATIC SMOKE/HEAT/CO DETECTION AND SPRINKLER FIRE ALARM
 Work on Floor(s): CEL,ROF 001 thru 009

05/02/2016 440307856 01 A2 X SIGNED OFF 01/22/2018 0073791 PE CHANG NOT APPLICABLE
 INSTALLATION OF TEMPORARY STANDPIPE WITH AN AIR ALARM IN CONJUNCTION WITH
 Work on Floor(s): CEL,ROF 001 thru 009

04/16/2016 440286272 02 A3 P APPROVED 01/03/2018 0026031 RA LENAHAN NOT APPLICABLE
 POST APPROVAL AMENDMENT FOR 01
 Work on Floor(s): OSP

04/13/2016 440304172 01 A3 X SIGNED OFF 12/05/2017 0083278 PE HOQUE NOT APPLICABLE
 INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER PLAN SUBMITTED. WORK SHALL
 Work on Floor(s): OSP

02/25/2016 440286263 02 A3 P APPROVED 02/29/2016 HOQUE NOT APPLICABLE
 POST APPROVAL AMENDMENT FOR 01
 Work on Floor(s): OSP

02/04/2016 440286263 01 A3 X SIGNED OFF 10/12/2017 0083278 PE HOQUE NOT APPLICABLE
 INSTALLATION OF TEMPORARY SIDEWALK SHED AS PER PLAN SUBMITTED. WORK SHALL
 Work on Floor(s): OSP

02/02/2016 440286272 01 A3 X SIGNED OFF 01/03/2018 0026031 RA LENAHAN NOT APPLICABLE
 INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER PLAN SUBMITTED. WORK SHALL
 Work on Floor(s): OSP

10/26/2015 440263457 01 A3 X SIGNED OFF 11/14/2017 0076655 PE LU NOT APPLICABLE
 INSTALLATION OF 4,500 LBS GJJ SC270TD SINGLE CAR PERSONAL/MATERIAL HOIST A
 Work on Floor(s): ROF 001 thru 008

08/07/2014 420887570 04 NB X SIGNED OFF 07/16/2018 0073791 PE CHANG GRANTED 08/28/2014
 ADDITIONAL FILING FOR PLUMBING, & MECHANICAL PLANS.
 Work on Floor(s): CEL,OSP,ROF 001 thru 009

08/07/2014 420887570 03 NB X SIGNED OFF 07/16/2018 0073791 PE CHANG GRANTED 08/28/2014
 ADDITIONAL FILING FOR SPRINKLER AND STANDPIPE.
 Work on Floor(s): CEL,OSP,ROF 001 thru 009

08/07/2014 420887570 02 NB X SIGNED OFF 07/16/2018 0068607 PE YU GRANTED 08/28/2014
 ADDITIONAL STRUCTURAL PLANS FOR NEW BUILDING.
 Work on Floor(s): CEL 001 thru 008

05/16/2014 420956530 01 A3 X SIGNED OFF 04/03/2018 0025376 RA TAN NOT APPLICABLE
 BUILDER'S PAVEMENT PLAN FOR NB#420887570.
 Work on Floor(s): OSP

04/18/2014 440135925 02 A3 P APPROVED 04/21/2014 HOQUE NOT APPLICABLE
 POST APPROVAL AMENDMENT FOR 01
 Work on Floor(s): OSP

03/28/2014 440135925 01 A3 X SIGNED OFF 12/05/2017 0083278 PE HOQUE NOT APPLICABLE
 INSTALLATION OF SIDEWALK SHED AS PER PLANS. WORK SHALL COMPLY WITH 2008 BU
 Work on Floor(s): OSP

10/09/2013 420887570 01 NB X SIGNED OFF 07/16/2018 0025376 RA TAN GRANTED 08/28/2014
 PROPOSED 9 STORY MIXED USE BUILDING
 Work on Floor(s): CEL,ROF,OSP 001 thru 009