| FILE DATE |
JOB # |
DOC # |
JOB TYPE |
JOB STATUS |
STATUS DATE |
LIC # |
APPLICANT |
IN AUDIT |
ZONING APPROVAL |
| 05/21/2020 |
123708559 |
02 |
A2 |
P APPROVED |
12/29/2020 |
|
JIANG |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): 003
|
| 04/16/2019 |
123708559 |
01 |
A2 |
X SIGNED OFF |
12/30/2020 |
0100081 PE |
JIANG |
|
NOT APPLICABLE
|
|
INTERIOR RENOVATION IN APT#9 ON 3RD FL. PARTITION AND PLUMBING WORK AS PER
|
|
Work on Floor(s): 003
|
| 11/29/2017 |
123163094 |
01 |
A2 |
X SIGNED OFF |
09/07/2018 |
0033885 RA |
CHANG |
|
NOT APPLICABLE
|
|
GENERAL CONSTRUCTION WITH PARTITION WORK, AND REPLACE PLUMBING FIXTURES. N
|
|
Work on Floor(s): 004
|
| 01/02/2013 |
120733741 |
02 |
A2 |
P APPROVED |
02/11/2013 |
|
PACIFICO |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): 007
|
| 06/24/2011 |
120733741 |
01 |
A2 |
X SIGNED OFF |
04/17/2013 |
0066182 PE |
PACIFICO |
|
NOT APPLICABLE
|
|
PROPOSED INSTALLATION OF 42 SHARP 240 WATT SOLAR PANELS ON ROOF
|
|
Work on Floor(s): 007
|