BIS Menu  |  Electrical Inspection Work Order   FAQs  |  Glossary   
DOB Logo - Link to Homepage NYC.gov Logo - Link to Homepage
NYC Department of Buildings
Electrical Application Details for App #: Z118516
NO JOBS FOUND WITH YOUR CRITERIA
Premises: 74 PINEHURST AVENUE MANHATTAN BIN: 1064309     Block: 2177   Lot: 136
   
Application Completed and Certified

Filed: 74 PINEHURST AV Census Tract:   265 Health Area:  0300
ENTIRE BLDG Admin Area:   Z - UPPER MANHATTAN Inspection Area:   A
NEW YORK, NY 10033 Community Board:   112
DOB Cross Street(s):   WEST 180 STREET,    WEST 181 STREET
Status:   C - JOB IS SIGNED OFF 07/23/2009
Request Type:   A - APPLICATION eFiled:   YES Permit Issued:  08/06/2008 6:19 PM
Application Entered:   08/06/2008 Job Start Date:   08/08/2008
Last Change:   07/23/2009 Job End Date:   09/21/2008
Appointment Status:   
Last Inspection By:   BANYA, E       On     06/22/2009      
Field Disp:   C - INSPECTION PASSED
Energize Recommendation:  E - ISSUE POWER AUTH
Objection Disposition:  

License #: 012008 Licensee Name: JAROSLAW K KURACH
Firm: 003679 Firm Name: BELMONT ELECTRICAL, INC
Firm Phone: 646-484-6641  Firm Address: 42 WEST 38TH STREET, STE 503 NEW YORK NY 10018 

Work Started or Filed by Others: NO
Work Category:   R - REHABILITATION Work To Be Done:  
1 - SERVICE WORK/NOTIFY UTILITY
6 - GENERAL WIRING
7 - HVAC WIRING
Total Fee:  $835.25
Other Work:   
Work Related to a New or Amended Certificate of Occupancy:   NO
This Job Regulated by the NYC Energy Conservation Code:  
Building Used As:   L - Five Or More Family
Special Cert Approval:  
Advisory Board Approval:   NOT APPLICABLE
Owner / Occup: MICHAEL ABATE
Owner Business Name: 74 PINEHURST LLC
Authorized Representative:   
Relationship To Owner:   


WORK DESCRIPTION
BUILDING OVERVIEW Are Feeders Being Installed? :   Yes
(If feeders are being installed, provide a wiring diagram and calculations at the time of inspection)
Building Overview Work Items QUANTITY DESCRIPTION
SERVICE SWITCHES  
A. Up to 100 AMPS  0  
B. 101 Up to 200 AMPS  0  
C. 201 Up to 600 AMPS  1  600AMP, 3PHASE 120/208
D. 601 Up to 1200 AMPS  0  
E. Over 1200 AMPS  0  
SER. ENT. & FDR COND (EACH SET)  
A. Up to #2 CONDUCTOR  0  
B. Over #2 to 1/0  0  
C. Over 1/0 to 250 MCM  0  
D. Over 250 MCM  2  2 SETS OF 350MCM THHN
PANELS  
A. 1 Phase Up to 20-1 or 10-2 Pole Brkrs  27  20CKT, 100A, 120/208V
B. 1 Phase Over to 21-1 or 10-2 Pole Brkrs  0  
C. 3 Phase Up to 225 AMPS  1  42CKT, 200A, 120/208V
D. 3 Phase Over 225 AMPS  0  
ELEVATORS / ESCALATORS / MATERIAL LIFTS  
A. Total No. of Elevators / Escalators / Material Lifts  0  
B. Each Additional 10 Floors Or Less  0  
BOILER CONTROLS  0  

FLOOR DESCRIPTIONS
Floor Apt. Number Of Outlets No. Of
Fixtures
Motors / Generators Heaters Transformers
Fixt Receptacles Switch Num Total HP KW Num Total KW Num Total KVA
ATT A/C
Buildings Total 60  150  21  60  60                
Total Units : 351 units   

Signs: Field Connect: 0 Field Inspect: 0 Tags:

SERVICE / METER EQUIPMENT
Meter Request to Utility #3-Wire 27 #4-Wire 1 #10-Wire 0
Existing Meters 28 + New Meters 28 - Removed Meters 28 = Total Meters 28

Power Auth Flag: I - ISSUED Objection Flag:
Power Requested: 08/06/2008 Notice:  
Power Issued: 08/06/2008 Response:  

Follow-Up: K - (CLOSED)
Contractor's Comments:  27 METER SERVICE, RISERS AND COMPLETE WIRING IN 7 APARTMENTS.

 
Inspection Details
 

*NO JOBS FOUND WITH YOUR CRITERIA
INSPECTION FOR APPLICATION #: Z118516
INSP
ID
FIELD
DATE
DISP
DATE
INSP
ID
FLD
DISP
OBJ
DISP
ENRG
REC
TIME
INSP
REINSP
DATE
NEW
OBJ
APPT
FLAG
 
(1) 06/22/2009 06/29/2009 EBA C E (60) (0) Y
INSPECTION COMMENTS: NONE




If you have any questions please review these Frequently Asked Questions, the Glossary, or call the 311 Citizen Service Center by dialing 311 or (212) NEW YORK outside of New York City.


BIS Menu  |  Electrical Inspection Work Order