| FILE DATE |
JOB # |
DOC # |
JOB TYPE |
JOB STATUS |
STATUS DATE |
LIC # |
APPLICANT |
IN AUDIT |
ZONING APPROVAL |
| 12/21/2018 |
420948782 |
26 |
NB |
P APPROVED |
01/17/2019 |
|
CHAN |
|
GRANTED 04/06/2015
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,ROF 001 thru 008
|
| 12/18/2018 |
421084579 |
04 |
A2 |
P APPROVED |
02/19/2019 |
|
WANG |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): 001 thru 008
|
| 12/17/2018 |
420948782 |
25 |
NB |
P APPROVED |
12/17/2018 |
|
CHAN |
|
GRANTED 04/06/2015
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,ROF 001 thru 008
|
| 11/05/2018 |
420948782 |
24 |
NB |
P APPROVED |
11/16/2018 |
0082390 PE |
DENG |
|
GRANTED 04/06/2015
|
|
POST APPROVAL AMENDMENT FOR 03
|
|
Work on Floor(s): CEL,ROF 001 thru 008
|
| 10/04/2018 |
420948782 |
23 |
NB |
P APPROVED |
10/22/2018 |
|
CHAN |
|
GRANTED 04/06/2015
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,ROF 001 thru 008
|
| 10/03/2018 |
420948782 |
22 |
NB |
P APPROVED |
10/22/2018 |
0082390 PE |
DENG |
|
GRANTED 04/06/2015
|
|
POST APPROVAL AMENDMENT FOR 03
|
|
Work on Floor(s): CEL,ROF 001 thru 008
|
| 07/26/2018 |
420948782 |
21 |
NB |
P APPROVED |
08/15/2018 |
|
CHAN |
|
GRANTED 04/06/2015
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,ROF 001 thru 008
|
| 07/20/2018 |
420948782 |
20 |
NB |
P APPROVED |
08/01/2018 |
0082390 PE |
DENG |
|
GRANTED 04/06/2015
|
|
POST APPROVAL AMENDMENT FOR 03
|
|
Work on Floor(s): CEL,ROF 001 thru 008
|
| 07/10/2018 |
421033081 |
02 |
A3 |
P APPROVED |
08/15/2018 |
|
CHAN |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): OSP
|
| 06/19/2018 |
420948782 |
19 |
NB |
P APPROVED |
06/26/2018 |
0082390 PE |
DENG |
|
GRANTED 04/06/2015
|
|
POST APPROVAL AMENDMENT FOR 03
|
|
Work on Floor(s): CEL,ROF 001 thru 008
|
| 06/14/2018 |
420948782 |
18 |
NB |
P APPROVED |
06/26/2018 |
|
CHAN |
|
GRANTED 04/06/2015
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,ROF 001 thru 008
|
| 05/17/2018 |
420948782 |
17 |
NB |
P APPROVED |
05/25/2018 |
0082390 PE |
DENG |
|
GRANTED 04/06/2015
|
|
POST APPROVAL AMENDMENT FOR 03
|
|
Work on Floor(s): CEL,ROF 001 thru 008
|
| 04/04/2018 |
420948782 |
16 |
NB |
P APPROVED |
04/12/2018 |
|
CHAN |
|
GRANTED 04/06/2015
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,ROF 001 thru 008
|
| 12/05/2017 |
420948782 |
15 |
NB |
P APPROVED |
12/20/2017 |
|
CHAN |
|
GRANTED 04/06/2015
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,ROF 001 thru 008
|
| 10/17/2017 |
440340659 |
02 |
A3 |
P APPROVED |
10/26/2017 |
|
AHMED |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): GRD
|
| 10/04/2017 |
420948782 |
14 |
NB |
P APPROVED |
10/31/2017 |
|
CHAN |
|
GRANTED 04/06/2015
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,ROF 001 thru 008
|
| 09/18/2017 |
421324347 |
02 |
A2 |
P APPROVED |
11/06/2017 |
|
DENG |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01 FURNISH AND INSTALL AUTOMATIC SMOKE/HEAT/CO
|
|
Work on Floor(s): CEL,ROF 001 thru 008
|
| 12/27/2016 |
440350674 |
02 |
A3 |
P APPROVED |
12/29/2016 |
|
UDDIN |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): OSP
|
| 12/22/2016 |
440346305 |
02 |
A3 |
P APPROVED |
12/30/2016 |
|
AHMED |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): GRD
|
| 10/28/2016 |
420948782 |
13 |
NB |
P APPROVED |
01/10/2017 |
0082390 PE |
DENG |
|
GRANTED 04/06/2015
|
|
POST APPROVAL AMENDMENT FOR 03
|
|
Work on Floor(s): CEL,ROF 001 thru 008
|
| 10/28/2016 |
440357338 |
01 |
A3 |
X SIGNED OFF |
05/14/2018 |
0072914 PE |
AHMED |
|
NOT APPLICABLE
|
|
OUTRIGGER BEAM INSTALLATION AS PER PLANS. NO CHANGE IN USE, EGRESS, OR
|
|
Work on Floor(s): 002,003
|
| 10/25/2016 |
420948782 |
12 |
NB |
P APPROVED |
01/10/2017 |
|
CHAN |
|
GRANTED 04/06/2015
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,ROF 001 thru 008
|
| 10/18/2016 |
440350674 |
01 |
A3 |
X SIGNED OFF |
05/03/2018 |
0071719 PE |
UDDIN |
|
NOT APPLICABLE
|
|
INSTALLATION OF SINGLE 6000 LB PERSONNEL/MATERIAL HOIST AS PER PLANS DURIN
|
|
Work on Floor(s): OSP
|
| 09/22/2016 |
440346305 |
01 |
A3 |
X SIGNED OFF |
05/14/2018 |
0072914 PE |
AHMED |
|
NOT APPLICABLE
|
|
INSTALLATION OF PIPE SCAFFOLD AS PER PLANS. NO CHANGE IN USE, EGRESS, OR
|
|
Work on Floor(s): GRD
|
| 09/01/2016 |
440340659 |
01 |
A3 |
X SIGNED OFF |
05/14/2018 |
0072914 PE |
AHMED |
|
NOT APPLICABLE
|
|
INSTALLATION OF HEAVY DUTY SIDEWALK SHED AS PER PLANS. NO CHANGE IN USE, E
|
|
Work on Floor(s): GRD
|
| 07/30/2016 |
420948782 |
11 |
NB |
P APPROVED |
08/29/2016 |
0082390 PE |
DENG |
|
GRANTED 04/06/2015
|
|
POST APPROVAL AMENDMENT FOR 03
|
|
Work on Floor(s): CEL,ROF 001 thru 008
|
| 05/25/2016 |
420948782 |
10 |
NB |
P APPROVED |
06/09/2016 |
0082390 PE |
DENG |
|
GRANTED 04/06/2015
|
|
POST APPROVAL AMENDMENT FOR 03
|
|
Work on Floor(s): CEL,ROF 001 thru 008
|
| 05/13/2016 |
420948782 |
09 |
NB |
D A/P ENTIRE |
05/23/2016 |
0082390 PE |
DENG |
|
GRANTED 04/06/2015
|
|
DOC WITHDRAWN 05/24/2016
|
|
Work on Floor(s): CEL,ROF 001 thru 008
|
| 05/13/2016 |
421324347 |
01 |
A2 |
X SIGNED OFF |
01/16/2019 |
0082390 PE |
DENG |
|
NOT APPLICABLE
|
|
FURNISH AND INSTALL AUTOMATIC SMOKE/HEAT/CO DETECTION AND SPRINKLER MONITO
|
|
Work on Floor(s): CEL,ROF 001 thru 008
|
| 04/23/2016 |
421084579 |
03 |
A2 |
P APPROVED |
04/27/2016 |
|
WANG |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): 001 thru 008
|
| 03/08/2016 |
420948782 |
08 |
NB |
P APPROVED |
03/25/2016 |
0083189 PE |
HUANG |
|
GRANTED 04/06/2015
|
|
POST APPROVAL AMENDMENT FOR 02
|
|
Work on Floor(s): CEL,ROF 001 thru 008
|
| 03/07/2016 |
421084579 |
02 |
A2 |
P APPROVED |
03/18/2016 |
|
WANG |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): 001 thru 008
|
| 03/02/2016 |
420948782 |
07 |
NB |
P APPROVED |
03/24/2016 |
|
CHAN |
|
GRANTED 04/06/2015
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,ROF 001 thru 008
|
| 10/06/2015 |
420948782 |
06 |
NB |
P APPROVED |
10/14/2015 |
0083189 PE |
HUANG |
|
GRANTED 04/06/2015
|
|
POST APPROVAL AMENDMENT FOR 02
|
|
Work on Floor(s): CEL,ROF 001 thru 008
|
| 09/24/2015 |
420948782 |
05 |
NB |
P APPROVED |
10/14/2015 |
|
CHAN |
|
GRANTED 04/06/2015
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,ROF 001 thru 008
|
| 04/23/2015 |
421153717 |
01 |
A2 |
X SIGNED OFF |
11/28/2018 |
0091045 PE |
FAYBYSHE |
|
NOT APPLICABLE
|
|
INSTALLATION OF TEMPORARY STANDPIPE WITH AN AIR ALARM, AS PER LOCAL LAWS 6
|
|
Work on Floor(s): CEL,ROF 001 thru 008
|
| 04/20/2015 |
420948782 |
04 |
NB |
P APPROVED |
04/23/2015 |
|
CHAN |
|
GRANTED 04/06/2015
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,ROF 001 thru 008
|
| 03/03/2015 |
421084579 |
01 |
A2 |
X SIGNED OFF |
03/06/2019 |
0074354 PE |
WANG |
|
NOT APPLICABLE
|
|
FILING OF SUPPORT OF EXCAVATION DRAWINGS IN CONJUNCTION WITH NB FILE UNDER
|
|
Work on Floor(s): 001 thru 008
|
| 11/14/2014 |
420948782 |
03 |
NB |
X SIGNED OFF |
03/18/2019 |
0082390 PE |
DENG |
|
GRANTED 04/06/2015
|
|
SUB-FILING FOR PLUMBING/SPRINKLER/STANDPIPE/MECHANICAL/BOILER.
|
|
Work on Floor(s): CEL,ROF 001 thru 008
|
| 11/12/2014 |
420948782 |
02 |
NB |
X SIGNED OFF |
03/18/2019 |
0083189 PE |
HUANG |
|
GRANTED 04/06/2015
|
|
SUBSEQUENT FILING FOR STRUCTURAL
|
|
Work on Floor(s): CEL,ROF 001 thru 008
|