| FILE DATE |
JOB # |
DOC # |
JOB TYPE |
JOB STATUS |
STATUS DATE |
LIC # |
APPLICANT |
IN AUDIT |
ZONING APPROVAL |
| 06/27/2014 |
402600789 |
11 |
NB |
P APPROVED |
06/27/2014 |
|
ZHAO |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL 001 thru 006
|
| 04/08/2014 |
420966814 |
01 |
A2 |
X SIGNED OFF |
04/23/2014 |
0086301 PE |
ZHAO |
|
NOT APPLICABLE
|
|
FILE STRUCTURAL PLAN, IN CONJUNCTION WITH NEW BUILDING APPLICATION # 40260
|
|
Work on Floor(s): CEL,ROF 001 thru 006
|
| 03/17/2014 |
402600789 |
10 |
NB |
D A/P ENTIRE |
03/17/2014 |
|
ZHAO |
|
NOT APPLICABLE
|
|
DOC WITHDRAWN 03/26/2014
|
|
Work on Floor(s): CEL 001 thru 006
|
| 02/24/2014 |
402600789 |
09 |
NB |
P APPROVED |
03/06/2014 |
|
ZHAO |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL 001 thru 006
|
| 12/24/2013 |
402600789 |
08 |
NB |
P APPROVED |
01/16/2014 |
0086301 PE |
ZHAO |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL 001 thru 006
|
| 12/12/2013 |
420930087 |
01 |
SC |
U COMPLETED |
12/26/2013 |
0086301 PE |
ZHAO |
|
NOT APPLICABLE
|
|
CONDO TAX LOT SUBDIVISION, COMMUNITY FACILITY/MEDICAL OFFICE UNITS TENTATI
|
| 10/04/2013 |
420903614 |
01 |
A3 |
X SIGNED OFF |
01/29/2014 |
0086301 PE |
ZHAO |
|
NOT APPLICABLE
|
|
NSTALLATION OF PIPE SCAFFOLD AS PER PLANS AT 139-30 34TH AVENUE. DURING RE
|
|
Work on Floor(s): OSP
|
| 09/30/2013 |
440107894 |
01 |
A3 |
H P/E IN PROCESS |
09/30/2013 |
0086301 PE |
ZHAO |
|
NOT APPLICABLE
|
|
JOB WITHDRAWN 10/07/2013 NSTALLATION OF PIPE SCAFFOLD AS PER PLANS AT 139-
|
|
Work on Floor(s): OSP
|
| 09/18/2013 |
420480214 |
03 |
A3 |
P APPROVED |
09/23/2013 |
0086301 PE |
ZHAO |
|
NOT APPLICABLE
|
|
DOC WITHDRAWN 04/28/2014
|
|
Work on Floor(s): CEL 001 thru 006
|
| 09/16/2013 |
420480214 |
02 |
A3 |
D A/P ENTIRE |
09/16/2013 |
0086301 PE |
ZHAO |
|
NOT APPLICABLE
|
|
DOC WITHDRAWN 04/28/2014
|
|
Work on Floor(s): CEL 001 thru 006
|
| 09/16/2013 |
420031423 |
03 |
A2 |
P APPROVED |
10/11/2013 |
0086301 PE |
ZHAO |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL 001 thru 006
|
| 05/31/2013 |
420832629 |
02 |
A2 |
P APPROVED |
07/10/2013 |
|
ZHAO |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,ROF 001 thru 006
|
| 04/10/2013 |
420832629 |
01 |
A2 |
X SIGNED OFF |
02/25/2014 |
0086301 PE |
ZHAO |
|
NOT APPLICABLE
|
|
INSTALL SPRINKLER SYSTEM ANIN CONJUNCTION WITH NB 402600789. NO CHANGE IN
|
|
Work on Floor(s): CEL,ROF 001 thru 006
|
| 03/19/2013 |
402600789 |
07 |
NB |
P APPROVED |
03/25/2013 |
|
Chan |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL 001 thru 006
|
| 04/30/2012 |
420031423 |
02 |
A2 |
P APPROVED |
05/01/2012 |
|
CHAN |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL 001 thru 006
|
| 10/13/2011 |
420492657 |
01 |
A2 |
J P/E DISAPPROVED |
10/24/2011 |
0015817 RA |
CHAN |
|
NOT APPLICABLE
|
|
JOB WITHDRAWN 04/11/2013 INSTALL SPRINKLER SYSTEM, IN CONJUNCTION WITH NEW
|
|
Work on Floor(s): CEL 001 thru 006
|
| 09/23/2011 |
402600789 |
06 |
NB |
P APPROVED |
04/04/2012 |
|
Chan |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL 001 thru 006
|
| 09/08/2011 |
420480214 |
01 |
A3 |
R PERMIT-ENTIRE |
04/04/2013 |
0086301 PE |
ZHAO |
|
NOT APPLICABLE
|
|
JOB WITHDRAWN 04/28/2014 FILE STRUCTURAL PLAN, IN CONJUNCTION WITH NEW BUI
|
|
Work on Floor(s): CEL 001 thru 006
|
| 06/27/2011 |
420344201 |
02 |
A3 |
P APPROVED |
06/27/2011 |
|
HICKEY |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): OSP
|
| 04/14/2011 |
420344201 |
01 |
A3 |
X SIGNED OFF |
04/09/2013 |
0065430 PE |
HICKEY |
|
NOT APPLICABLE
|
|
INSTALLATION OF NEEDLE BEAM AS PER PLANS AT 139-30 34TH AVENUE. DURING REM
|
|
Work on Floor(s): OSP
|
| 03/30/2011 |
420338450 |
01 |
A3 |
X SIGNED OFF |
04/05/2013 |
0065430 PE |
HICKEY |
|
NOT APPLICABLE
|
|
INSTALLATION OF PIPE SCAFFOLD AS PER PLANS AT 139-30 34TH AVENUE. DURING
|
|
Work on Floor(s): OSP
|
| 03/22/2011 |
420334828 |
01 |
A3 |
X SIGNED OFF |
04/05/2013 |
0065430 PE |
HICKEY |
|
NOT APPLICABLE
|
|
INSTALLATION OF HEAVY DUTY SIDEWALK SHED APPROXIMATELY 176 L.F. AS PER PLA
|
|
Work on Floor(s): OSP
|
| 02/03/2010 |
420137266 |
01 |
A3 |
X SIGNED OFF |
04/05/2013 |
0065430 PE |
HICKEY |
|
NOT APPLICABLE
|
|
INSTALLATION OF A HEAVY DUTY SIDEWALK SHED 20' LONG (IN CONJUNCTION WITH S
|
|
Work on Floor(s): OSP
|
| 06/16/2009 |
420031423 |
01 |
A2 |
X SIGNED OFF |
04/08/2014 |
0086301 PE |
ZHAO |
|
NOT APPLICABLE
|
|
INSTALL HVAC AND BOILER SYSTEM, IN CONJUNCTION WITH NEW BUILDING APPLICATI
|
|
Work on Floor(s): CEL 001 thru 006
|
| 06/02/2009 |
402600789 |
05 |
NB |
P APPROVED |
06/03/2009 |
|
Chan |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL 001 thru 006
|
| 04/13/2009 |
410108761 |
05 |
A2 |
P APPROVED |
04/13/2009 |
|
LIN |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): OSP
|
| 01/13/2009 |
410214450 |
01 |
A2 |
P APPROVED |
02/12/2009 |
0015817 RA |
CHAN |
|
NOT APPLICABLE
|
|
JOB WITHDRAWN 04/11/2013 INSTALL SPRINKLER SYSTEM, IN CONJUNCTION WITH NEW
|
|
Work on Floor(s): CEL 001 thru 006
|
| 09/12/2008 |
410108761 |
04 |
A2 |
P APPROVED |
11/28/2008 |
|
LIN |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): OSP
|
| 09/12/2008 |
410108761 |
03 |
A2 |
P APPROVED |
09/12/2008 |
|
LIN |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): OSP
|
| 07/28/2008 |
410143795 |
01 |
A3 |
P APPROVED |
07/28/2008 |
0066812 PE |
NG |
|
NOT APPLICABLE
|
|
JOB WITHDRAWN 04/10/2013 FILE STRUCTURAL PLAN, IN CONJUNCTION WITH NEW BUI
|
|
Work on Floor(s): CEL 001 thru 006
|
| 07/21/2008 |
410140404 |
01 |
A3 |
X SIGNED OFF |
04/08/2013 |
0065430 PE |
HICKEY |
|
NOT APPLICABLE
|
|
INSTALLATION OF A HEAVY DUTY SIDEWALK SHED 50' DURING NEW BUILDING CONSTRU
|
|
Work on Floor(s): 001
|
| 07/07/2008 |
402600789 |
04 |
NB |
P APPROVED |
09/15/2008 |
|
Chan |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL 001 thru 006
|
| 06/23/2008 |
410108761 |
02 |
A2 |
P APPROVED |
06/24/2008 |
|
LIN |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): OSP
|
| 05/07/2008 |
410108761 |
01 |
A2 |
X SIGNED OFF |
11/06/2009 |
0072792 PE |
LIN |
|
NOT APPLICABLE
|
|
FILED HEREWITH APPLICATION FOR SHORING IN CONNECTION WITH NB# 402600789. A
|
|
Work on Floor(s): OSP
|
| 03/11/2008 |
402600789 |
03 |
NB |
P APPROVED |
04/08/2008 |
|
Chan |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL 001 thru 006
|
| 01/28/2008 |
402672238 |
01 |
DM |
X SIGNED OFF |
03/24/2008 |
OT |
SINGH |
|
NOT APPLICABLE
|
|
Work on Floor(s): 001,002,ATT
|
| 10/17/2007 |
410018635 |
01 |
A3 |
X SIGNED OFF |
03/26/2014 |
0015817 RA |
Chan |
|
NOT APPLICABLE
|
|
FILE BUILDERS PAVEMENT PLAN, IN CONJUNCTION WITH NEW BUILDING APPLICATION
|
|
Work on Floor(s): OSP
|
| 10/17/2007 |
402600789 |
02 |
NB |
X SIGNED OFF |
06/27/2014 |
0015817 RA |
Chan |
|
NOT APPLICABLE
|
|
Work on Floor(s): OSP
|
| 05/24/2007 |
402600789 |
01 |
NB |
X SIGNED OFF |
06/27/2014 |
0086301 PE |
ZHAO |
|
NOT APPLICABLE
|
|
Work on Floor(s): CEL 001 thru 006
|
| 05/17/2007 |
402595063 |
01 |
DM |
E AP-NPE |
05/17/2007 |
0015817 RA |
Chan |
|
NOT APPLICABLE
|
|
JOB WITHDRAWN 04/04/2013
|
|
Work on Floor(s): CEL 001 thru 002
|