| FILE DATE |
JOB # |
DOC # |
JOB TYPE |
JOB STATUS |
STATUS DATE |
LIC # |
APPLICANT |
IN AUDIT |
ZONING APPROVAL |
| 06/27/2017 |
440415604 |
01 |
A3 |
X SIGNED OFF |
02/01/2018 |
0082770 PE |
BAILEY |
|
NOT APPLICABLE
|
|
PROPOSED INSTALLATION OF HEAVY DUTY SIDEWALK SHED AS PER PLANS. NO CHANGE
|
|
Work on Floor(s): OSP
|
| 07/11/2015 |
420975029 |
03 |
A2 |
P APPROVED |
02/09/2016 |
|
MAKARA |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): OSP
|
| 06/03/2014 |
420975029 |
02 |
A2 |
P APPROVED |
04/30/2015 |
|
MAKARA |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): OSP
|
| 04/30/2014 |
420975029 |
01 |
A2 |
R PERMIT-ENTIRE |
05/12/2014 |
0081532 PE |
MAKARA |
|
NOT APPLICABLE
|
|
INSTALLATION OF GAS BARBEQUE IN THE REAR YARD. NO CHANGE IN USE, EGRESS OR
|
|
Work on Floor(s): OSP
|
| 02/07/2014 |
420938560 |
02 |
A2 |
P APPROVED |
02/12/2014 |
|
MAKARA |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): 020
|
| 01/13/2014 |
420938560 |
01 |
A2 |
X SIGNED OFF |
05/06/2014 |
0081532 PE |
MAKARA |
|
NOT APPLICABLE
|
|
REPLACEMENT OF 1 EXSTG HW STOARGE TANK WITH 2 NEW INDIRECT HW HEATERS IN
|
|
Work on Floor(s): 020
|
| 12/13/2013 |
440118356 |
01 |
A2 |
R PERMIT-ENTIRE |
12/13/2013 |
0028075 RA |
POMPEO |
|
NOT APPLICABLE
|
|
APPLICATION FILED TO REPAIR MINOR WATER DAMAGE IN PENTHOUSE APARTMENT AND
|
|
Work on Floor(s): 015,016,017,018,019
|
| 11/26/2013 |
440117794 |
01 |
A2 |
H P/E IN PROCESS |
11/26/2013 |
0028075 RA |
POMPEO |
|
NOT APPLICABLE
|
|
JOB WITHDRAWN 12/02/2013 APPLICATION FILED TO REPAIR MINOR WATER DAMAGE IN
|
|
Work on Floor(s): 015,016,017,018,019
|
| 08/02/2011 |
402502760 |
06 |
A2 |
P APPROVED |
08/26/2011 |
|
Makara |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): ROF 001 thru 021
|
| 03/31/2011 |
420338566 |
01 |
SC |
U COMPLETED |
03/31/2011 |
0025077 RA |
CARRANO |
|
NOT APPLICABLE
|
|
CONDOMINIUM SUBDIVISION INTO 164 RESIDENTIAL LOTS 1101 TO 1264. NO CHANGE
|
|
Work on Floor(s): 001 thru 020
|
| 09/17/2010 |
402502760 |
05 |
A2 |
P APPROVED |
10/13/2010 |
|
Makara |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): ROF 001 thru 021
|
| 08/03/2010 |
402376102 |
04 |
A2 |
P APPROVED |
01/05/2011 |
0063244 PE |
Gibble |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): UDG
|
| 08/03/2010 |
402287841 |
03 |
NB |
P APPROVED |
09/08/2010 |
|
Carrano |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): 001 thru 020
|
| 06/21/2010 |
402502760 |
04 |
A2 |
P APPROVED |
07/06/2010 |
|
Makara |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): ROF 001 thru 021
|
| 06/03/2010 |
402376102 |
03 |
A2 |
P APPROVED |
07/06/2010 |
|
Gibble |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): UDG
|
| 03/17/2010 |
402503331 |
03 |
A3 |
P APPROVED |
03/30/2010 |
|
Carrano |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): 001
|
| 03/10/2010 |
410066743 |
02 |
A2 |
P APPROVED |
03/29/2010 |
|
Franco |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): OSP
|
| 03/10/2010 |
420147629 |
01 |
A2 |
X SIGNED OFF |
08/02/2011 |
0025077 RA |
CARRANO |
|
NOT APPLICABLE
|
|
THIS APPLICATION IS FILED FOR A TEMPORARY USE PERMIT FOR SALES OFFICE PURS
|
|
Work on Floor(s): 009
|
| 01/14/2010 |
420127017 |
01 |
A3 |
X SIGNED OFF |
09/24/2010 |
0025077 RA |
CARRANO |
|
NOT APPLICABLE
|
|
INSTALLATION OF CURB CUT IN CONJUNCTION WITH NEW BUILDING APPLICATION. NO
|
|
Work on Floor(s): 001
|
| 01/14/2010 |
420127026 |
01 |
A3 |
X SIGNED OFF |
06/30/2010 |
0025077 RA |
CARRANO |
|
NOT APPLICABLE
|
|
FILING FOR FIRE PROTECTION PLAN IN CONJUNCTION WITH NEW BUILDING APPLICATI
|
|
Work on Floor(s): CEL 001 thru 020
|
| 12/01/2009 |
402502760 |
03 |
A2 |
P APPROVED |
01/22/2010 |
|
Makara |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): ROF 001 thru 021
|
| 10/16/2009 |
420095293 |
01 |
A2 |
X SIGNED OFF |
09/24/2010 |
0081532 PE |
MAKARA |
|
NOT APPLICABLE
|
|
INSTALLATION OF BOILERS UNITS ON THE 20TH FL,FILED IN CONJUNCTION WITH NEW
|
|
Work on Floor(s): 020
|
| 10/14/2009 |
402502760 |
02 |
A2 |
P APPROVED |
10/20/2009 |
|
Makara |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): 001 thru 022
|
| 08/28/2009 |
402503331 |
02 |
A3 |
P APPROVED |
09/04/2009 |
|
Carrano |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): 001
|
| 07/02/2009 |
402287841 |
02 |
NB |
P APPROVED |
03/10/2010 |
|
Carrano |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): 001 thru 020
|
| 10/20/2008 |
410131753 |
02 |
A3 |
P APPROVED |
10/21/2008 |
|
STILLER |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): OSP
|
| 08/08/2008 |
410148111 |
01 |
A3 |
X SIGNED OFF |
10/30/2008 |
0021612 RA |
SCHWARTZ |
|
NOT APPLICABLE
|
|
INSTALLATION OF TEMPORAY PIPE SCAFFOLDING IN THE CONFINES OF THE ELEVATOR
|
|
Work on Floor(s): 001 thru 020
|
| 06/26/2008 |
410131753 |
01 |
A3 |
X SIGNED OFF |
01/07/2010 |
0070592 PE |
STILLER |
|
NOT APPLICABLE
|
|
INSTALLATION OF PIPE SCAFFOLD AS PER DRAWINGS FOR NEW BUILDING CONSTRUCTIO
|
|
Work on Floor(s): OSP
|
| 06/26/2008 |
410131995 |
01 |
A2 |
X SIGNED OFF |
04/27/2010 |
0044507 PE |
ZALOUM |
|
NOT APPLICABLE
|
|
EXCAVATION WORK AT SHORING IN CONJUNCTION WITH NEW BUILDING. NO CHANGE IN
|
|
Work on Floor(s): OSP
|
| 02/29/2008 |
410070550 |
01 |
A3 |
X SIGNED OFF |
05/03/2010 |
0050542 PE |
FRANCO |
|
NOT APPLICABLE
|
|
TEMPORARY USE OF 6,000 LB. PERSONNEL/MATERIAL HOIST IN CONJUNCTION WITH NE
|
|
Work on Floor(s): OSP
|
| 02/14/2008 |
410066743 |
01 |
A2 |
X SIGNED OFF |
04/26/2010 |
0050542 PE |
Franco |
|
NOT APPLICABLE
|
|
Erect temporary hoistway for construction operations in conjunction with N
|
|
Work on Floor(s): OSP
|
| 09/17/2007 |
410002367 |
01 |
A2 |
X SIGNED OFF |
04/01/2010 |
0063244 PE |
Gibble |
|
NOT APPLICABLE
|
|
Filing for structural work in conjunction with new building 402287841. Al
|
|
Work on Floor(s): 001 thru 020
|
| 07/25/2007 |
402636616 |
01 |
A3 |
X SIGNED OFF |
05/12/2011 |
0025077 RA |
Carrano |
|
NOT APPLICABLE
|
|
Filing for construction fence in conjunction with New Building 402287841.
|
|
Work on Floor(s): 001
|
| 04/30/2007 |
402585181 |
01 |
A2 |
X SIGNED OFF |
01/12/2010 |
0072187 PE |
TAHSEEN |
|
NOT APPLICABLE
|
|
Filing for shoring in conjunction with New building application 402287841.
|
|
Work on Floor(s): CEL
|
| 04/25/2007 |
402376102 |
02 |
A2 |
P APPROVED |
09/17/2007 |
0063244 PE |
Gibble |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): UDG
|
| 12/04/2006 |
402503331 |
01 |
A3 |
X SIGNED OFF |
11/09/2010 |
0025077 RA |
Carrano |
|
NOT APPLICABLE
|
|
Filing for builders paving plan for 129'0" feet of sidewalk in conjunctio
|
|
Work on Floor(s): 001
|
| 12/01/2006 |
402503322 |
01 |
A3 |
J P/E DISAPPROVED |
12/04/2006 |
0025077 RA |
Carrano |
|
NOT APPLICABLE
|
|
JOB WITHDRAWN 01/12/2010 Installation of curb cut in conjunction with new
|
|
Work on Floor(s): 001
|
| 11/30/2006 |
402502779 |
01 |
A2 |
X SIGNED OFF |
09/12/2011 |
0081532 PE |
Makara |
|
NOT APPLICABLE
|
|
INSTALLATION OF AUTOMAIC SMOKE/HEAT DETECTION & SPRINKLER ALARM SYSTEM
|
|
Work on Floor(s): ROF 001 thru 020
|
| 11/30/2006 |
402502760 |
01 |
A2 |
X SIGNED OFF |
02/07/2012 |
0081532 PE |
Makara |
|
NOT APPLICABLE
|
|
Filing for mechanical,plumbing, sprinkler and standpipe work in conjunctio
|
|
Work on Floor(s): ROF 001 thru 021
|
| 11/24/2006 |
402498828 |
01 |
A3 |
J P/E DISAPPROVED |
12/06/2006 |
0025077 RA |
Carrano |
|
NOT APPLICABLE
|
|
JOB WITHDRAWN 01/12/2010 Filing for fire protection plan in conjunction wi
|
|
Work on Floor(s): CEL 001 thru 020
|