| 10/13/2023 |
421808413 |
02 |
A1 |
P APPROVED |
08/01/2024 |
|
PAPA |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01 NO WORK ALT1 FILED TO CHANGE OCCUPANCY FROM
|
|
Work on Floor(s): CEL,BAS 001 thru 005
|
| 04/01/2022 |
421808413 |
01 |
A1 |
R PERMIT-ENTIRE |
07/26/2022 |
0029888 RA |
PAPA |
|
NOT APPLICABLE
|
|
NO WORK ALT1 FILED TO CHANGE OCCUPANCY FROM USE GROUP 3A (DAY CARE) TO USE
|
|
Work on Floor(s): CEL,BAS 001 thru 005
|
| 12/12/2013 |
440119248 |
01 |
A2 |
X SIGNED OFF |
02/27/2014 |
0029888 RA |
PAPA |
|
NOT APPLICABLE
|
|
REPLACEMENT OF EXISTING PACKAGE UNIT IN FIRST FLOOR REAR TERRACE FOR DAYCA
|
|
Work on Floor(s): 001
|
| 02/03/2012 |
420512118 |
02 |
A2 |
P APPROVED |
02/03/2012 |
|
PAPA |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,BAS,001,002,003,004
|
| 12/19/2011 |
420512118 |
01 |
A2 |
X SIGNED OFF |
03/07/2013 |
0029888 RA |
PAPA |
|
NOT APPLICABLE
|
|
APPLICATION FILED TO DO AN INTERIOR BUILDOUT BY ERECTING PARTITIANS AND AD
|
|
Work on Floor(s): CEL,BAS,001,002,003,004
|
| 10/11/2011 |
420066010 |
07 |
NB |
P APPROVED |
10/18/2011 |
|
PAPA |
|
GRANTED 12/02/2009
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,BAS 001 thru 005
|
| 09/13/2011 |
420066010 |
06 |
NB |
P APPROVED |
09/20/2011 |
|
PAPA |
|
GRANTED 12/02/2009
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,BAS 001 thru 005
|
| 09/02/2011 |
420174304 |
02 |
A2 |
P APPROVED |
09/02/2011 |
|
CAMULAIR |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,BAS,001,002,003,004
|
| 09/02/2011 |
420066010 |
05 |
NB |
P APPROVED |
09/20/2011 |
|
PAPA |
|
GRANTED 12/02/2009
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,BAS 001 thru 005
|
| 12/29/2010 |
420291856 |
02 |
A2 |
P APPROVED |
03/02/2011 |
|
PAPA |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): ROF
|
| 12/29/2010 |
420066010 |
04 |
NB |
P APPROVED |
08/22/2011 |
|
PAPA |
|
GRANTED 12/02/2009
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,BAS 001 thru 005
|
| 12/02/2010 |
420291856 |
01 |
A2 |
X SIGNED OFF |
10/04/2011 |
0029888 RA |
PAPA |
|
NOT APPLICABLE
|
|
TO INDICATE BL WORK TYPE WHICH WAS INADVERTANLY OMITTED FROM NB APPLICATIO
|
|
Work on Floor(s): ROF
|
| 07/23/2010 |
420231305 |
01 |
A3 |
X SIGNED OFF |
02/23/2011 |
0014908 RA |
COMPTON |
|
NOT APPLICABLE
|
|
ERECT PIPE SCAFFOLD AS PER PLAN AT 28-34 38 STREET IN CONJUNCTION WITH NB#
|
|
Work on Floor(s): OSP
|
| 06/09/2010 |
420066010 |
03 |
NB |
P APPROVED |
09/10/2010 |
|
PAPA |
|
GRANTED 12/02/2009
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,BAS 001 thru 005
|
| 04/14/2010 |
420174304 |
01 |
A2 |
X SIGNED OFF |
10/24/2011 |
0081443 PE |
CAMULAIR |
|
NOT APPLICABLE
|
|
FIRE SPRINKLER SYSTEM FILED IN CONJUNCTION WITH NB#420066010
|
|
Work on Floor(s): CEL,BAS,001,002,003,004
|
| 01/13/2010 |
420066010 |
02 |
NB |
P APPROVED |
06/09/2010 |
|
PAPA |
|
GRANTED 12/02/2009
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,001,002,003,004,005
|
| 10/26/2009 |
420098673 |
01 |
A3 |
X SIGNED OFF |
05/06/2011 |
0029888 RA |
PAPA |
|
NOT APPLICABLE
|
|
BUILDERS PAVEMENT PLAN. FILED IN CONJUNCTION WITH NB#420066010
|
|
Work on Floor(s): OSP
|
| 10/13/2009 |
420094043 |
01 |
DM |
X SIGNED OFF |
02/02/2010 |
OT |
PRETE |
|
NOT APPLICABLE
|
|
DEMOLITION OF TWO STORY HOUSE
|
|
Work on Floor(s): 001,002
|
| 08/21/2009 |
420066010 |
01 |
NB |
X SIGNED OFF |
10/24/2011 |
0029888 RA |
PAPA |
|
GRANTED 12/02/2009
|
|
PROPOSED FIVE (5) STORY BUILDING WITH CELLAR - BRICK ON STEEEL STRUCTURE
|
|
Work on Floor(s): CEL,BAS 001 thru 005
|