| FILE DATE |
JOB # |
DOC # |
JOB TYPE |
JOB STATUS |
STATUS DATE |
LIC # |
APPLICANT |
IN AUDIT |
ZONING APPROVAL |
| 12/11/2019 |
421778936 |
01 |
A2 |
X SIGNED OFF |
08/13/2020 |
0079022 PE |
LEE |
|
NOT APPLICABLE
|
|
FACADE REPAIR TO INCLUDE RAILINGS AND BALCONIES TO ADDRESS RELATED FACADE
|
|
Work on Floor(s): FAC
|
| 12/18/2017 |
421576690 |
01 |
A2 |
X SIGNED OFF |
02/11/2020 |
0075954 PE |
SIMONIEL |
|
NOT APPLICABLE
|
|
FILING FOR ROOFTOP RAILING REPLACEMENT; NO CHANGE TO USE, EGRESS OR OCCUPA
|
|
Work on Floor(s): ROF
|
| 10/12/2016 |
421386565 |
01 |
A3 |
X SIGNED OFF |
05/17/2018 |
0090372 PE |
ZDANCEWI |
|
NOT APPLICABLE
|
|
INSTALLATION OF TEMPORARY SIDEWALK SHED AS PER PLAN SUBMITTED. WORK SHALL
|
|
Work on Floor(s): OSP
|
| 04/16/2016 |
421309257 |
02 |
A3 |
P APPROVED |
04/18/2016 |
|
HALL |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): OSP
|
| 04/01/2016 |
421309257 |
01 |
A3 |
P APPROVED |
04/01/2016 |
0071543 PE |
HALL |
|
NOT APPLICABLE
|
|
INSTALLATION OF CONSTRUCTION SHED IN CONJUNCTION WITH 12 STORY NEW BUILDIN
|
|
Work on Floor(s): OSP
|
| 01/23/2014 |
420792949 |
02 |
A2 |
P APPROVED |
03/06/2014 |
|
ZIMMERMA |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): OSP
|
| 12/06/2012 |
420792949 |
01 |
A2 |
X SIGNED OFF |
09/03/2014 |
0014327 RA |
ZIMMERMA |
|
NOT APPLICABLE
|
|
GROUND LEVEL INTERIOR COURTYARD PLANTER WALL BRICK REPLACEMENT. NO CHANGE
|
|
Work on Floor(s): OSP
|
| 09/21/2010 |
402437065 |
23 |
NB |
P APPROVED |
09/23/2010 |
0015609 RA |
Newman |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,ROF 001 thru 012
|
| 05/12/2010 |
402437065 |
22 |
NB |
P APPROVED |
05/12/2010 |
0054124 |
Smolinsk |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 02
|
|
Work on Floor(s): CEL,ROF 001 thru 012
|
| 09/10/2009 |
402437065 |
21 |
NB |
P APPROVED |
09/16/2009 |
0062063 PE |
DiBari |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 03
|
|
Work on Floor(s): CEL,ROF 001 thru 012
|
| 09/08/2009 |
420075803 |
01 |
A3 |
X SIGNED OFF |
04/09/2010 |
0015609 RA |
NEWMAN |
|
NOT APPLICABLE
|
|
IT IS PROPOSED TO INSTALL 23' CURB CUT ON 49TH AVE 137 FEET FROM THE
|
|
Work on Floor(s): OSP
|
| 05/14/2009 |
402437065 |
20 |
NB |
P APPROVED |
05/15/2009 |
0062063 PE |
DiBari |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 03
|
|
Work on Floor(s): CEL,ROF 001 thru 012
|
| 04/24/2009 |
402437065 |
19 |
NB |
P APPROVED |
04/29/2009 |
0062063 PE |
DiBari |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 03
|
|
Work on Floor(s): CEL,ROF 001 thru 012
|
| 04/08/2009 |
402437065 |
18 |
NB |
P APPROVED |
04/10/2009 |
0062063 PE |
DiBari |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 03
|
|
Work on Floor(s): CEL,ROF 001 thru 012
|
| 03/12/2009 |
402437065 |
17 |
NB |
P APPROVED |
03/12/2009 |
|
Newman |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,ROF 001 thru 012
|
| 02/26/2009 |
402437065 |
16 |
NB |
P APPROVED |
02/26/2009 |
|
Newman |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,ROF 001 thru 012
|
| 02/25/2009 |
402437065 |
15 |
NB |
P APPROVED |
02/25/2009 |
0062063 PE |
DiBari |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 03
|
|
Work on Floor(s): CEL,ROF 001 thru 012
|
| 02/11/2009 |
402437065 |
14 |
NB |
P APPROVED |
02/18/2009 |
0062063 PE |
DiBari |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 03
|
|
Work on Floor(s): CEL,ROF 001 thru 012
|
| 02/05/2009 |
402437065 |
13 |
NB |
P APPROVED |
02/10/2009 |
0062063 PE |
DiBari |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 03
|
|
Work on Floor(s): CEL,ROF 001 thru 012
|
| 02/04/2009 |
402437065 |
12 |
NB |
P APPROVED |
02/10/2009 |
|
Newman |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,ROF 001 thru 012
|
| 01/20/2009 |
402437065 |
11 |
NB |
P APPROVED |
01/28/2009 |
0062063 PE |
DiBari |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 03
|
|
Work on Floor(s): CEL,ROF 001 thru 012
|
| 01/20/2009 |
402556088 |
03 |
A2 |
P APPROVED |
02/05/2009 |
|
DiBari |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,ROF 001 thru 012
|
| 01/09/2009 |
402437065 |
10 |
NB |
P APPROVED |
01/30/2009 |
|
Newman |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,ROF 001 thru 012
|
| 12/11/2008 |
402556088 |
02 |
A2 |
P APPROVED |
01/07/2009 |
|
DiBari |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,ROF 001 thru 012
|
| 10/22/2008 |
410182920 |
01 |
A3 |
X SIGNED OFF |
03/26/2010 |
0015609 RA |
NEWMAN |
|
NOT APPLICABLE
|
|
PROPOSED TO FILE FIRE PROTECTION PLAN IN CONJUNCTION WITH NEW BUILDING #
|
|
Work on Floor(s): 001 thru 012
|
| 10/20/2008 |
402437065 |
09 |
NB |
P APPROVED |
11/07/2008 |
0062063 PE |
DiBari |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 03
|
|
Work on Floor(s): CEL,ROF 001 thru 012
|
| 10/20/2008 |
402437065 |
08 |
NB |
P APPROVED |
11/07/2008 |
|
Newman |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,ROF 001 thru 012
|
| 09/04/2008 |
402437065 |
07 |
NB |
P APPROVED |
09/22/2008 |
|
Newman |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,ROF 001 thru 012
|
| 08/05/2008 |
410149708 |
01 |
SC |
U COMPLETED |
09/22/2008 |
0015609 RA |
NEWMAN |
Y |
NOT APPLICABLE
|
|
CONDO LOT SUBDIVISON SEE SECTION # 24
|
|
Work on Floor(s): CEL,ROF 001 thru 012
|
| 06/17/2008 |
410125653 |
01 |
A3 |
X SIGNED OFF |
10/14/2009 |
0020419 RA |
HULME |
|
NOT APPLICABLE
|
|
INSTALLATION OF TEMPORARY WORK PLATFORM IN CONJUNCTION WITH NB # 402437065
|
|
Work on Floor(s): 1
|
| 04/15/2008 |
410099771 |
01 |
A2 |
X SIGNED OFF |
05/18/2009 |
0620063 PE |
DI BARI |
|
NOT APPLICABLE
|
|
INSTALLATION OF (2) LOW PRESSURE GAS FIRED DHW BIOLERS. ALL PL & OT WORK T
|
|
Work on Floor(s): ROO
|
| 02/12/2008 |
410062765 |
01 |
A2 |
X SIGNED OFF |
08/14/2009 |
0080474 PE |
LEONID |
|
NOT APPLICABLE
|
|
INSTALLATION OF THE SPRINKLER ALARM SYSTEM WITH CENTRAL OFFICE CONNECTIO
|
|
Work on Floor(s): CEL,ROF 001 thru 012
|
| 01/24/2008 |
410055014 |
01 |
A3 |
X SIGNED OFF |
11/25/2009 |
0051969 PE |
SAULINO |
|
NOT APPLICABLE
|
|
INSTALLATION OF PIPE SCAFFOLD TO ORINGANATE FROM SECOND FLOOR TO ROOF. S
|
|
Work on Floor(s): OSP
|
| 01/23/2008 |
402437065 |
06 |
NB |
P APPROVED |
02/07/2008 |
0062063 PE |
DiBari |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 03
|
|
Work on Floor(s): CEL,ROF 001 thru 012
|
| 11/13/2007 |
402437065 |
05 |
NB |
P APPROVED |
11/29/2007 |
0015609 RA |
Newman |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,ROF 001 thru 012
|
| 08/14/2007 |
402648989 |
01 |
A3 |
X SIGNED OFF |
04/15/2009 |
0020419 RA |
Hulme |
|
NOT APPLICABLE
|
|
INSTALL HEAVY DUTY SIDEWALK SHED 215 FT LONG AT 48-15 11TH STREET. DURING
|
|
Work on Floor(s): 001
|
| 07/02/2007 |
402625156 |
01 |
A3 |
X SIGNED OFF |
12/04/2008 |
0079601 PE |
McERLEAN |
|
NOT APPLICABLE
|
|
INSTALLATION OF 6000LBS PERSONNEL & MATERIAL HOIST AT 48-15 11 STREET. DUR
|
|
Work on Floor(s): 001
|
| 05/09/2007 |
402437065 |
04 |
NB |
P APPROVED |
06/11/2007 |
0062063 PE |
DiBari |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 03
|
|
Work on Floor(s): CEL,ROF 001 thru 012
|
| 03/13/2007 |
402556088 |
01 |
A2 |
X SIGNED OFF |
06/02/2009 |
0062063 PE |
DiBari |
|
NOT APPLICABLE
|
|
It is proposed to install sprinkler and standpipe systems for new 12 story
|
|
Work on Floor(s): CEL,ROF 001 thru 012
|
| 02/26/2007 |
402548221 |
01 |
A2 |
X SIGNED OFF |
04/21/2009 |
0074354 PE |
Wang |
|
NOT APPLICABLE
|
|
Shoring as per plans filed herewith. No change to egress, use or occupancy
|
|
Work on Floor(s): 001
|