| 04/14/2022 |
420819886 |
04 |
A2 |
P APPROVED |
04/20/2022 |
|
COHEN |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): BAS
|
| 11/12/2021 |
440554375 |
03 |
A2 |
P APPROVED |
11/16/2021 |
|
GINSBERG |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): 001,BAS
|
| 08/23/2021 |
420819886 |
03 |
A2 |
P APPROVED |
08/26/2021 |
|
COHEN |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): BAS
|
| 07/21/2021 |
420819886 |
02 |
A2 |
P APPROVED |
07/26/2021 |
|
COHEN |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): BAS
|
| 05/14/2020 |
440594581 |
01 |
A2 |
H P/E IN PROCESS |
05/14/2020 |
0037509 RA |
PROFETA |
|
NOT APPLICABLE
|
|
JOB WITHDRAWN 05/20/2020 ROOF RECOVERY SYSTEM INSTALLATION.
|
|
Work on Floor(s): BAS,001,ROF
|
| 05/13/2020 |
440593868 |
01 |
A2 |
X SIGNED OFF |
12/29/2021 |
0037509 RA |
PROFETA |
|
NOT APPLICABLE
|
|
ROOF RECOVERY SYSTEM INSTALLATION.
|
|
Work on Floor(s): BAS,001,ROF
|
| 01/03/2020 |
440554375 |
02 |
A2 |
P APPROVED |
01/27/2020 |
|
GINSBERG |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01 FILING TO UPGRADE THE ACCESSIBILITY AND REN
|
|
Work on Floor(s): 001,BAS
|
| 06/26/2019 |
440554375 |
01 |
A2 |
X SIGNED OFF |
03/07/2022 |
0019534 RA |
GINSBERG |
|
NOT APPLICABLE
|
|
FILING TO UPGRADE THE ACCESSIBILITY AND RENOVATION IN COMMON/EMPLOYEE AREA
|
|
Work on Floor(s): 001,BAS
|
| 06/18/2019 |
440553018 |
01 |
A2 |
D A/P ENTIRE |
06/18/2019 |
0019534 RA |
GINSBERG |
|
NOT APPLICABLE
|
|
JOB WITHDRAWN 06/19/2019 INTERIOR ALTERATION FOR ACCESSIBILITY UPGRADE IN
|
|
Work on Floor(s): 001
|
| 12/07/2016 |
421407953 |
01 |
A2 |
X SIGNED OFF |
08/21/2017 |
0085125 PE |
RUDITSER |
|
NOT APPLICABLE
|
|
INSTALLATION OF DIESEL FIRED GENERATOR.
|
|
Work on Floor(s): 001
|
| 08/21/2014 |
440162823 |
01 |
A2 |
R PERMIT-ENTIRE |
08/25/2014 |
0034659 RA |
FLAUM |
|
NOT APPLICABLE
|
|
REQUIRED SOLID PIPING TO REPLACE FLEXIBLE CONNECTORS AS NOTED IN VIOLATION
|
|
Work on Floor(s): 001
|
| 06/29/2014 |
440145852 |
01 |
A2 |
X SIGNED OFF |
11/17/2015 |
0069428 PE |
KRIGSMAN |
|
NOT APPLICABLE
|
|
REPLACEMENT OF BOILER AND BURNER #2 FOR USE WITH EXISTING NATURAL GAS
|
|
Work on Floor(s): CEL
|
| 05/15/2014 |
440144087 |
01 |
A2 |
H P/E IN PROCESS |
05/15/2014 |
0069428 PE |
KRIGSMAN |
|
NOT APPLICABLE
|
|
JOB WITHDRAWN 05/26/2014 REPLACEMENT OF BOILER AND BURNER #2 FOR USE WITH
|
|
Work on Floor(s): CEL
|
| 01/23/2014 |
440124759 |
01 |
A2 |
X SIGNED OFF |
07/15/2014 |
0034659 RA |
FLAUM |
|
NOT APPLICABLE
|
|
ADD REQUIRED SPRINKLER HEADS TO EXISTING SYSTEM AS PER PLANS FLED HEREWITH
|
|
Work on Floor(s): 001
|
| 04/03/2013 |
420819886 |
01 |
A2 |
X SIGNED OFF |
05/02/2022 |
0078958 PE |
COHEN |
|
NOT APPLICABLE
|
|
INSTALL (1) REPLACEMENT GAS BURNER ON (1) EXISTING LOW PRESSURE BOILER. C
|
|
Work on Floor(s): BAS
|
| 02/05/2013 |
420810180 |
01 |
A2 |
X SIGNED OFF |
02/27/2014 |
0080951 PE |
CONSTANT |
|
NOT APPLICABLE
|
|
INSTALL STAINLESS STEEL CHIMNEY LINER
|
|
Work on Floor(s): CE, RO
|
| 11/08/2010 |
420284178 |
01 |
A2 |
R PERMIT-ENTIRE |
07/06/2011 |
0043644 PE |
GARNER |
|
NOT APPLICABLE
|
|
REMEDIAL REPAIRS TO FACADES TO BUILDING A (320 BEACH 100 ST) AND BUILDING
|
|
Work on Floor(s): 001 thru 014
|
| 04/27/2010 |
420179675 |
01 |
A3 |
R PERMIT-ENTIRE |
05/04/2011 |
0014908 RA |
COMPTON |
|
NOT APPLICABLE
|
|
ERECT PLYWOOD FENCE AS PER PLAN AT 319 BEACH 98 STREET. DURING REMEDIAL RE
|
|
Work on Floor(s): OSP
|
| 04/27/2010 |
420179666 |
01 |
A3 |
R PERMIT-ENTIRE |
05/04/2011 |
0014908 RA |
COMPTON |
|
NOT APPLICABLE
|
|
INSTALLATION OF SIDEWALK SHED A TOTAL OF 150 L.F. AS PER PLAN AT 319 BEACH
|
|
Work on Floor(s): OSP
|
| 06/06/2007 |
402608040 |
01 |
A3 |
X SIGNED OFF |
04/17/2009 |
0081318 PE |
LONGO |
|
NOT APPLICABLE
|
|
INSTALLING CABINET MOUNTED TO NEW STEELPLATFORM WITH LEADER ON THE ROOF
|
|
Work on Floor(s): ROF
|
| 12/21/2004 |
402065457 |
01 |
A2 |
X SIGNED OFF |
01/05/2006 |
0050579 PE |
RUDIKOFF |
|
NOT APPLICABLE
|
|
ABANDON BURIED 20,000 GALLON FUEL OIL TANK. INSTALL REPLACEMENT 12,000 GAL
|
|
Work on Floor(s): 001,OSP
|
| 02/25/2003 |
401083162 |
02 |
A2 |
P APPROVED |
02/28/2003 |
0050579 PE |
RUDIKOFF |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL
|
| 02/12/2001 |
401211577 |
01 |
A3 |
R PERMIT-ENTIRE |
03/01/2001 |
OT |
SINGH |
|
NOT APPLICABLE
|
|
EMERGENCY CONSTRUCTION FO 25LF LIGHT DUTY METAL SHED, NO STORAGE. SHED REQ
|
|
Work on Floor(s): 001
|
| 03/29/2000 |
401083162 |
01 |
A2 |
X SIGNED OFF |
06/17/2003 |
0050579 PE |
RUDIKOFF |
|
NOT APPLICABLE
|
|
REPLACE (1) BOILER AND (2) GAS/OIL BURNE RS ADN CONNECT TO EXISTING GAS
|
|
Work on Floor(s): CEL
|
| 03/27/2000 |
401080600 |
01 |
A3 |
R PERMIT-ENTIRE |
03/29/2000 |
0065430 PE |
HICKEY |
|
NOT APPLICABLE
|
|
INSTALLATION OF A HEAVY DUTY SIDEWALK SH ED 128' DURINGFACADE REPAIRS.
|
| 07/21/1999 |
401001795 |
01 |
A2 |
X SIGNED OFF |
03/27/2003 |
0010010 RA |
DOMAN |
|
NOT APPLICABLE
|
|
REPAIRS TO EXISTING FACADES AS PER L.L. 10/80
|
| 04/10/1997 |
400735503 |
01 |
A3 |
X SIGNED OFF |
07/14/2006 |
0020419 RA |
HULME |
|
NOT APPLICABLE
|
|
INSTALLATION OF SHED: 50 FEET LONG ON B EACH 100 ST., DURING FACADE RE
|
|
Work on Floor(s): GRO
|