| FILE DATE |
JOB # |
DOC # |
JOB TYPE |
JOB STATUS |
STATUS DATE |
LIC # |
APPLICANT |
IN AUDIT |
ZONING APPROVAL |
| 10/27/2023 |
440782609 |
02 |
A2 |
P APPROVED |
11/06/2023 |
RA |
MAKAR |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): ROF
|
| 05/09/2023 |
440782609 |
01 |
A2 |
R PERMIT-ENTIRE |
05/12/2023 |
0104468 RA |
MAKAR |
|
NOT APPLICABLE
|
|
INSTALLATION OF A ROOFTOP SOLAR PANEL PV SYSTEM.
|
|
Work on Floor(s): ROF
|
| 02/17/1998 |
400771606 |
02 |
A1 |
X SIGNED OFF |
04/17/1998 |
0066312 PE |
BASSIRI- |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,001,002
|
| 09/09/1997 |
400771606 |
01 |
A1 |
X SIGNED OFF |
04/17/1998 |
0066312 PE |
BASSIRI- |
|
NOT APPLICABLE
|
|
EXTENSION OF THE SECOND FLOOR IN THE BAC K AND 9 FEET
|
|
Work on Floor(s): CEL,001,002
|