| FILE DATE |
JOB # |
DOC # |
JOB TYPE |
JOB STATUS |
STATUS DATE |
LIC # |
APPLICANT |
IN AUDIT |
ZONING APPROVAL |
| 06/23/2021 |
421516238 |
06 |
A1 |
P APPROVED |
06/28/2021 |
|
ZHAO |
|
GRANTED 11/27/2017
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,001,002,003,ROF
|
| 05/17/2021 |
421516238 |
05 |
A1 |
P APPROVED |
05/18/2021 |
|
ZHAO |
|
GRANTED 11/27/2017
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,001,002,003,ROF
|
| 10/14/2020 |
421516238 |
04 |
A1 |
P APPROVED |
12/16/2020 |
|
ZHAO |
|
GRANTED 11/27/2017
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,001,002,003,ROF
|
| 06/18/2018 |
421516238 |
03 |
A1 |
P APPROVED |
05/31/2019 |
|
ZHAO |
|
GRANTED 11/27/2017
|
|
POST APPROVAL AMENDMENT FOR 01 HORIZONTAL & VERTICAL EXTENSION FOR EXISTIN
|
|
Work on Floor(s): CEL,001,002,003,ROF
|
| 02/21/2018 |
421516238 |
02 |
A1 |
P APPROVED |
04/10/2018 |
|
ZHAO |
|
GRANTED 11/27/2017
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,001,002,003,ROF
|
| 08/15/2017 |
421540327 |
01 |
A3 |
X SIGNED OFF |
12/17/2020 |
0086301 PE |
ZHAO |
|
NOT APPLICABLE
|
|
BUILDERS PAVEMENT PLAN 20' STREET FRONTAGE IN CONJUNCTION WITH NB JOB
|
|
Work on Floor(s): OSP
|
| 07/06/2017 |
421516238 |
01 |
A1 |
X SIGNED OFF |
06/29/2021 |
0086301 PE |
ZHAO |
|
GRANTED 11/27/2017
|
|
HORIZONTAL & VERTICAL EXTENSION FOR EXISTING 2 FAMILY CONVERT 2 TO 3 FAMI
|
|
Work on Floor(s): CEL,001,002,003,ROF
|
| 08/23/2007 |
402384576 |
03 |
A1 |
P APPROVED |
08/23/2007 |
0028697 RA |
Bosch |
|
NOT APPLICABLE
|
|
DOC WITHDRAWN 04/02/2021
|
|
Work on Floor(s): CEL,001,002
|
| 06/02/2006 |
402384576 |
02 |
A1 |
P APPROVED |
06/02/2006 |
0028697 RA |
Bosch |
|
NOT APPLICABLE
|
|
DOC WITHDRAWN 04/02/2021
|
|
Work on Floor(s): CEL,001,002
|
| 05/16/2006 |
402384576 |
01 |
A1 |
R PERMIT-ENTIRE |
07/27/2006 |
0028697 RA |
Bosch |
|
NOT APPLICABLE
|
|
JOB WITHDRAWN 04/02/2021 Convert from Two Family to Three Family Dwelling.
|
|
Work on Floor(s): CEL,001,002
|