| FILE DATE |
JOB # |
DOC # |
JOB TYPE |
JOB STATUS |
STATUS DATE |
LIC # |
APPLICANT |
IN AUDIT |
ZONING APPROVAL |
| 03/13/2020 |
321093883 |
07 |
A2 |
P APPROVED |
03/13/2020 |
|
RUDITSER |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,ROF 001 thru 008
|
| 06/03/2019 |
321961677 |
01 |
A2 |
X SIGNED OFF |
03/18/2020 |
0081675 PE |
BADINTER |
|
NOT APPLICABLE
|
|
SUPPORT OF EXCAVATION FOR PROPOSED NEW DRYWELL TO BE INSTALLED IN FRONT OF
|
|
Work on Floor(s): OSP
|
| 06/03/2019 |
321961677 |
02 |
A2 |
X SIGNED OFF |
03/18/2020 |
0085125 PE |
RUDITSER |
|
NOT APPLICABLE
|
|
ADDITION OF DRYWELL WITH RELATED PIPING, RECONFIGURATION OF ROOF DRAINS IN
|
|
Work on Floor(s): UDG,OSP
|
| 11/07/2018 |
321093883 |
06 |
A2 |
P APPROVED |
11/09/2018 |
|
RUDITSER |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,ROF 001 thru 008
|
| 10/10/2018 |
320915140 |
06 |
NB |
P APPROVED |
11/09/2018 |
|
PULASKI |
|
AMENDED 01/27/2017
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,ROF 001 thru 008
|
| 04/25/2018 |
321101142 |
03 |
A2 |
P APPROVED |
04/26/2018 |
|
UDITSER |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,ROF 001 thru 008
|
| 03/16/2018 |
321093883 |
05 |
A2 |
P APPROVED |
05/02/2018 |
|
RUDITSER |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,ROF 001 thru 008
|
| 02/15/2018 |
321780612 |
01 |
A2 |
X SIGNED OFF |
08/24/2018 |
0085125 PE |
RUDITSER |
|
NOT APPLICABLE
|
|
APPLICATION FILED TO CREATE A "BOILER" WORK TYPE IN CONJUNCTION WITH PLUMB
|
|
Work on Floor(s): CEL
|
| 01/18/2018 |
321093883 |
04 |
A2 |
P APPROVED |
01/19/2018 |
|
RUDITSER |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,ROF 001 thru 008
|
| 11/09/2017 |
321093883 |
03 |
A2 |
P APPROVED |
12/20/2017 |
|
RUDITSER |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,ROF 001 thru 008
|
| 08/16/2017 |
320915140 |
05 |
NB |
P APPROVED |
09/18/2017 |
|
PULASKI |
|
AMENDED 01/27/2017
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,ROF 001 thru 008
|
| 03/28/2017 |
340487002 |
01 |
A3 |
X SIGNED OFF |
08/03/2018 |
0082770 PE |
BAILEY |
|
NOT APPLICABLE
|
|
PROPOSED INSTALLATION OF INTERIOR PIPE SCAFFOLD AS PER PLANS. NO CHANGE IN
|
|
Work on Floor(s): OSP
|
| 01/11/2017 |
340462289 |
01 |
A3 |
X SIGNED OFF |
02/21/2018 |
0082770 PE |
BAILEY |
|
NOT APPLICABLE
|
|
PROPOSED INSTALLATION OF PIPE SCAFFOLD AS PER PLANS. NO CHANGE IN USE, EGR
|
|
Work on Floor(s): OSP
|
| 12/30/2016 |
320915140 |
04 |
NB |
P APPROVED |
01/27/2017 |
|
PULASKI |
|
AMENDED 01/27/2017
|
|
POST APPROVAL AMENDMENT FOR 01 PROPOSED NEW BUILDING
|
|
Work on Floor(s): CEL,ROF 001 thru 008
|
| 12/29/2016 |
320915140 |
03 |
NB |
P APPROVED |
01/05/2017 |
0069355 PE |
GOLD |
|
AMENDED 01/27/2017
|
|
POST APPROVAL AMENDMENT FOR 02
|
|
Work on Floor(s): CEL,ROF 001 thru 008
|
| 12/14/2016 |
321093883 |
02 |
A2 |
P APPROVED |
06/22/2017 |
|
RUDITSER |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,ROF 001 thru 008
|
| 07/12/2016 |
340400961 |
01 |
A3 |
X SIGNED OFF |
02/22/2018 |
0082770 PE |
BAILEY |
|
NOT APPLICABLE
|
|
PROPOSED INSTALLATION OF HEAVY DUTY SIDEWALK SHED AS PER PLANS. NO CHANGE
|
|
Work on Floor(s): OSP
|
| 07/15/2015 |
321101142 |
02 |
A2 |
P APPROVED |
12/13/2016 |
|
UDITSER |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,ROF 001 thru 008
|
| 03/26/2015 |
321100857 |
01 |
A2 |
X SIGNED OFF |
11/26/2018 |
0085125 PE |
RUDITSER |
|
NOT APPLICABLE
|
|
INSTALLATION OF AN AUTOMATIC SMOKE/HEAT/CO DETECTION AND SPRINKLER ALARM S
|
|
Work on Floor(s): CEL,ROF 001 thru 008
|
| 03/23/2015 |
321101142 |
01 |
A2 |
X SIGNED OFF |
11/19/2018 |
0085125 PE |
UDITSER |
|
NOT APPLICABLE
|
|
INSTALLATION OF SPRINKLER SYSTEM IN CONJUNCTION WITH NB APPLICATION #32091
|
|
Work on Floor(s): CEL,ROF 001 thru 008
|
| 03/19/2015 |
321093883 |
01 |
A2 |
X SIGNED OFF |
11/27/2020 |
0085125 PE |
RUDITSER |
|
NOT APPLICABLE
|
|
INSTALLATION OF PLUMBING AND MECHANICAL SYSTEM IN CONJUNCTION WITH NB
|
|
Work on Floor(s): CEL,ROF 001 thru 008
|
| 03/13/2015 |
320915140 |
02 |
NB |
X SIGNED OFF |
12/24/2020 |
0069355 PE |
GOLD |
|
AMENDED 01/27/2017
|
|
STRUCTURAL DRAWINGS SUBMITTED HEREWITH IN CONJUNCTION WITH NEW BUILDING
|
|
Work on Floor(s): CEL,ROF 001 thru 008
|
| 12/11/2014 |
321047201 |
01 |
A2 |
X SIGNED OFF |
11/02/2018 |
0015029 RA |
RADUSKY |
|
NOT APPLICABLE
|
|
ERECT TEMPORARY CONSTRUCTION FENCE AS SHOWN ON DRAWINGS FILED HEREWITH. N
|
|
Work on Floor(s): OSP
|
| 04/07/2014 |
320915140 |
01 |
NB |
X SIGNED OFF |
12/24/2020 |
0016482 RA |
PULASKI |
|
AMENDED 01/27/2017
|
|
PROPOSED NEW BUILDING
|
|
Work on Floor(s): CEL,ROF 001 thru 008
|
| 04/08/2014 |
340131976 |
01 |
A3 |
X SIGNED OFF |
02/07/2019 |
0016482 RA |
PULASKI |
|
NOT APPLICABLE
|
|
BUILDER'S PAVEMENT PLAN & CHECKLIST SUBMITTED HEREWITH FOR TOTAL LOT FRONT
|
|
Work on Floor(s): OSP
|