Premises: 85 JAY STREET BROOKLYN BIN: 3425091    Block: 54    Lot: 1

To start overview at new date, select Month:   Day:   Year:  

         

FILE DATE JOB # DOC # JOB TYPE JOB STATUS STATUS DATE LIC # APPLICANT IN AUDIT ZONING APPROVAL
12/07/2023 321188415 24 NB P APPROVED 12/21/2023 ADJMI GRANTED 03/26/2018
 POST APPROVAL AMENDMENT FOR 01
 Work on Floor(s): SC1,CEL,MEZ,ROF 001 thru 021

09/12/2023 321188415 23 NB P APPROVED 10/03/2023 ADJMI GRANTED 03/26/2018
 POST APPROVAL AMENDMENT FOR 01
 Work on Floor(s): SC1,CEL,MEZ,ROF 001 thru 021

06/08/2023 321188415 22 NB P APPROVED 11/09/2023 0058375 PE MASS GRANTED 03/26/2018
 POST APPROVAL AMENDMENT FOR 05
 Work on Floor(s): SC1,CEL,MEZ 001 thru 022

04/12/2023 321188415 21 NB P APPROVED 06/26/2023 ADJMI GRANTED 03/26/2018
 POST APPROVAL AMENDMENT FOR 01
 Work on Floor(s): SC1,CEL,MEZ,ROF 001 thru 021

02/23/2023 321188415 20 NB P APPROVED 03/21/2023 ADJMI GRANTED 03/26/2018
 POST APPROVAL AMENDMENT FOR 01
 Work on Floor(s): SC1,CEL,MEZ,ROF 001 thru 021

10/26/2022 322025759 03 A2 P APPROVED 11/03/2022 SEGAL NOT APPLICABLE
 POST APPROVAL AMENDMENT FOR 01
 Work on Floor(s): GND,ROF,SC, SC1,MEZ 002 thru 021

06/09/2022 321188415 19 NB P APPROVED 08/31/2022 ADJMI GRANTED 03/26/2018
 POST APPROVAL AMENDMENT FOR 01
 Work on Floor(s): SC1,CEL,MEZ,ROF 001 thru 021

05/04/2022 340815158 06 A2 D A/P ENTIRE 05/12/2022 SCHMERZL NOT APPLICABLE
 POST APPROVAL AMENDMENT FOR 01
 Work on Floor(s): SC1,CEL,MEX,ROF 001 thru 021

03/17/2022 321188415 18 NB P APPROVED 04/06/2022 ADJMI GRANTED 03/26/2018
 POST APPROVAL AMENDMENT FOR 01
 Work on Floor(s): SC1,CEL,MEZ,ROF 001 thru 021

03/16/2022 340815158 05 A2 P APPROVED 04/04/2022 SCHMERZL NOT APPLICABLE
 POST APPROVAL AMENDMENT FOR 01
 Work on Floor(s): SC1,CEL,MEX,ROF 001 thru 021

03/09/2022 340815158 04 A2 P APPROVED 03/11/2022 SCHMERZL NOT APPLICABLE
 POST APPROVAL AMENDMENT FOR 01
 Work on Floor(s): SC1,CEL,MEX,ROF 001 thru 021

01/10/2022 340815158 03 A2 P APPROVED 01/22/2022 SCHMERZL NOT APPLICABLE
 POST APPROVAL AMENDMENT FOR 01
 Work on Floor(s): SC1,CEL,MEX,ROF 001 thru 021

09/29/2021 340566346 03 A3 P APPROVED 10/15/2021 VITOLANO NOT APPLICABLE
 POST APPROVAL AMENDMENT FOR 01
 Work on Floor(s): OSP

08/31/2021 322027766 03 A2 P APPROVED 09/09/2021 SEGAL NOT APPLICABLE
 POST APPROVAL AMENDMENT FOR 01
 Work on Floor(s): GND,MEZ,ROF,SC1,SUB 002 thru 021

08/13/2021 340815158 02 A2 P APPROVED 09/29/2021 SCHMERZL NOT APPLICABLE
 POST APPROVAL AMENDMENT FOR 01
 Work on Floor(s): SC1,CEL,MEX,ROF 001 thru 021

07/13/2021 321188415 17 NB P APPROVED 08/05/2021 0058375 PE MASS GRANTED 03/26/2018
 POST APPROVAL AMENDMENT FOR 05
 Work on Floor(s): SC1,CEL,MEZ 001 thru 022

06/29/2021 340566346 02 A3 P APPROVED 07/30/2021 VITOLANO NOT APPLICABLE
 POST APPROVAL AMENDMENT FOR 01
 Work on Floor(s): OSP

06/29/2021 321188415 16 NB P APPROVED 07/12/2021 ADJMI GRANTED 03/26/2018
 POST APPROVAL AMENDMENT FOR 01
 Work on Floor(s): SC1,CEL,MEZ,ROF 001 thru 021

06/18/2021 321188415 15 NB P APPROVED 06/28/2021 0058375 PE MASS GRANTED 03/26/2018
 POST APPROVAL AMENDMENT FOR 05
 Work on Floor(s): SC1,CEL,MEZ 001 thru 022

06/16/2021 340815158 01 A2 R PERMIT-ENTIRE 11/29/2021 0020635 RA SCHMERZL NOT APPLICABLE
 HEREWITH FILING TENANT PROTECTION PLAN IN CONJUNCTION WITH NB APPLICATION
 Work on Floor(s): SC1,CEL,MEX,ROF 001 thru 021

05/04/2021 322095567 01 SC U COMPLETED 05/11/2021 0020005 RA ADJMI NOT APPLICABLE
 APPLICATION FILED FOR CONDOMINIUM SUBDIVISION. TAX LOT 1 TO BE SUBDIVIDED
 Work on Floor(s): SUB,CEL,MEZ,ROF 001 thru 021

04/30/2021 321188415 14 NB P APPROVED 06/14/2021 ADJMI GRANTED 03/26/2018
 POST APPROVAL AMENDMENT FOR 01
 Work on Floor(s): SC1,CEL,MEZ,ROF 001 thru 021

04/01/2021 322025759 02 A2 P APPROVED 08/10/2021 SEGAL NOT APPLICABLE
 POST APPROVAL AMENDMENT FOR 01
 Work on Floor(s): GND,ROF,SC, SC1,MEZ 002 thru 021

03/24/2021 321188415 13 NB P APPROVED 03/26/2021 ADJMI GRANTED 03/26/2018
 POST APPROVAL AMENDMENT FOR 01
 Work on Floor(s): SC1,CEL,MEZ,ROF 001 thru 021

03/11/2021 321188415 12 NB P APPROVED 03/19/2021 ADJMI GRANTED 03/26/2018
 POST APPROVAL AMENDMENT FOR 01
 Work on Floor(s): SC1,CEL,MEZ,ROF 001 thru 021

11/24/2020 322027766 02 A2 P APPROVED 12/03/2020 SEGAL NOT APPLICABLE
 POST APPROVAL AMENDMENT FOR 01
 Work on Floor(s): GND,MEZ,ROF,SC1,SUB 002 thru 021

09/30/2020 321188415 11 NB P APPROVED 03/19/2021 0058375 PE MASS GRANTED 03/26/2018
 POST APPROVAL AMENDMENT FOR 05
 Work on Floor(s): SC1,CEL,MEZ 001 thru 022

09/01/2020 340758585 01 A2 X SIGNED OFF 01/12/2022 0090287 PE LOMBARDO NOT APPLICABLE
 INSTALLATION AND USE OF ADDITIONAL TEMPORARY MOBILE EQUIPMENT AS PER PLANS
 Work on Floor(s): ROF 002 thru 021

05/12/2020 340725638 01 A2 X SIGNED OFF 01/12/2022 0090287 PE LOMBARDO NOT APPLICABLE
 INSTALLATION AND USE OF TEMPORARY MOBILE EQUIPMENT AS PER PLANS FILED HERE
 Work on Floor(s): ROF 002 thru 021

04/22/2020 340725629 01 A2 D A/P ENTIRE 04/22/2020 0090287 PE LOMBARDO NOT APPLICABLE
 JOB WITHDRAWN 04/22/2020 INSTALLATION AND USE OF TEMPORARY MOBILE EQUIPMEN
 Work on Floor(s): ROF 002 thru 021

04/20/2020 340725246 01 A3 D A/P ENTIRE 04/20/2020 0079601 PE MCERLEAN NOT APPLICABLE
 JOB WITHDRAWN 08/26/2020 INSTALLATION OF A TEMPORARY OVERHEAD PROTECTION F
 Work on Floor(s): OSP

02/06/2020 321188415 10 NB P APPROVED 07/21/2020 ADJMI GRANTED 03/26/2018
 POST APPROVAL AMENDMENT FOR 01
 Work on Floor(s): SC1,CEL,MEZ,ROF 001 thru 021

01/14/2020 340713259 01 A3 P APPROVED 01/14/2020 0101795 PE KETCHO Y NOT APPLICABLE
 JOB WITHDRAWN 07/07/2022 INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER DR
 Work on Floor(s): OSP

12/17/2019 340699792 02 A3 P APPROVED 01/22/2020 KETCHO NOT APPLICABLE
 POST APPROVAL AMENDMENT FOR 01
 Work on Floor(s): OSP

10/22/2019 340692842 02 A3 P APPROVED 10/24/2019 MCERLEAN NOT APPLICABLE
 POST APPROVAL AMENDMENT FOR 01
 Work on Floor(s): OSP

10/22/2019 340692646 02 A3 P APPROVED 10/24/2019 MCERLEAN NOT APPLICABLE
 POST APPROVAL AMENDMENT FOR 01
 Work on Floor(s): OSP

10/10/2019 340700539 01 A3 H P/E IN PROCESS 10/10/2019 0082512 PE VALJATO NOT APPLICABLE
 ADMIN CLOSED 12/09/2019 INSTALLATION OF LOADING PLATFORM IN CONJUNCTION WI
 Work on Floor(s): 005 thru 017

10/10/2019 340700511 01 A3 H P/E IN PROCESS 10/10/2019 0082512 PE VALJATO NOT APPLICABLE
 JOB WITHDRAWN 10/10/2019 INSTALLATION OF LOADING PLATFORM AS PER PLANS FIL
 Work on Floor(s): 005 thru 017

10/04/2019 340699792 01 A3 X SIGNED OFF 01/24/2022 0101795 PE KETCHO NOT APPLICABLE
 INSTALLATION OF TEMPORARY SUSPENDED SCAFFOLD AS PER DRAWINGS. TEMPORARY
 Work on Floor(s): OSP

10/01/2019 340682185 02 A3 P APPROVED 10/04/2019 MCERLEAN NOT APPLICABLE
 POST APPROVAL AMENDMENT FOR 01
 Work on Floor(s): OSP