| FILE DATE |
JOB # |
DOC # |
JOB TYPE |
JOB STATUS |
STATUS DATE |
LIC # |
APPLICANT |
IN AUDIT |
ZONING APPROVAL |
| 02/11/2026 |
321196200 |
21 |
NB |
P APPROVED |
03/13/2026 |
|
ADJMI |
|
GRANTED 11/01/2016
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): SUB,CEL,ROF 001 thru 014
|
| 10/05/2021 |
321196200 |
20 |
NB |
P APPROVED |
10/08/2021 |
0073548 PE |
GLICKMAN |
|
GRANTED 11/01/2016
|
|
POST APPROVAL AMENDMENT FOR 03
|
|
Work on Floor(s): SUB,CEL,ROF 001 thru 014
|
| 05/18/2021 |
340597982 |
04 |
A2 |
P APPROVED |
05/21/2021 |
|
GLICKMAN |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,ROF,SUB 001 thru 014
|
| 04/01/2021 |
321196200 |
19 |
NB |
P APPROVED |
04/15/2021 |
|
ADJMI |
|
GRANTED 11/01/2016
|
|
POST APPROVAL AMENDMENT FOR 01 CONSTRUCT NEW 14 STORY BUILDING AS PER PLAN
|
|
Work on Floor(s): SUB,CEL,ROF 001 thru 014
|
| 02/01/2021 |
321196200 |
18 |
NB |
P APPROVED |
02/10/2021 |
|
ADJMI |
|
GRANTED 11/01/2016
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): SUB,CEL,ROF 001 thru 014
|
| 01/05/2021 |
321196200 |
17 |
NB |
P APPROVED |
01/11/2021 |
|
ADJMI |
|
GRANTED 11/01/2016
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): SUB,CEL,ROF 001 thru 014
|
| 10/30/2020 |
321196200 |
16 |
NB |
P APPROVED |
11/19/2020 |
0073548 PE |
GLICKMAN |
|
GRANTED 11/01/2016
|
|
POST APPROVAL AMENDMENT FOR 03
|
|
Work on Floor(s): SUB,CEL,ROF 001 thru 014
|
| 10/22/2020 |
321196200 |
15 |
NB |
P APPROVED |
10/26/2020 |
0073548 PE |
GLICKMAN |
|
GRANTED 11/01/2016
|
|
POST APPROVAL AMENDMENT FOR 03
|
|
Work on Floor(s): SUB,CEL,ROF 001 thru 014
|
| 09/10/2020 |
321196200 |
14 |
NB |
P APPROVED |
09/17/2020 |
0073548 PE |
GLICKMAN |
|
GRANTED 11/01/2016
|
|
POST APPROVAL AMENDMENT FOR 03
|
|
Work on Floor(s): SUB,CEL,ROF 001 thru 014
|
| 03/13/2020 |
340597982 |
03 |
A2 |
P APPROVED |
07/02/2020 |
|
GLICKMAN |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01 INSTALL COMBINED SPRINKLER/STANDPIPE SYSTEM
|
|
Work on Floor(s): CEL,ROF,SUB 001 thru 014
|
| 01/28/2020 |
340597982 |
02 |
A2 |
P APPROVED |
02/10/2020 |
|
GLICKMAN |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,ROF,SUB 001 thru 014
|
| 11/07/2019 |
321196200 |
13 |
NB |
P APPROVED |
11/18/2019 |
0073548 PE |
GLICKMAN |
|
GRANTED 11/01/2016
|
|
POST APPROVAL AMENDMENT FOR 03
|
|
Work on Floor(s): SUB,CEL,ROF 001 thru 014
|
| 11/06/2019 |
322005646 |
01 |
A2 |
P APPROVED |
11/06/2019 |
0020005 RA |
ADJMI |
|
NOT APPLICABLE
|
|
TENANT PROTECTION PLAN FILED IN CONJUNCTION WITH NB #321196200. NO CHANGE
|
|
Work on Floor(s): SUB,CEL,ROF 001 thru 014
|
| 08/20/2019 |
321196200 |
12 |
NB |
P APPROVED |
10/07/2019 |
|
ADJMI |
|
GRANTED 11/01/2016
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): SUB,CEL,ROF 001 thru 014
|
| 07/18/2019 |
321664150 |
02 |
A2 |
P APPROVED |
07/08/2020 |
|
GLICKMAN |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01 INSTALLATION OF AUTOMATIC SMOKE/HEAT/CO DET
|
|
Work on Floor(s): SUB,CEL,013,014,PEN,ROF 001 thru 012
|
| 06/12/2019 |
321196200 |
11 |
NB |
P APPROVED |
06/26/2019 |
0073548 PE |
GLICKMAN |
|
GRANTED 11/01/2016
|
|
POST APPROVAL AMENDMENT FOR 03
|
|
Work on Floor(s): SUB,CEL,ROF 001 thru 014
|
| 04/23/2019 |
340673747 |
01 |
A2 |
J P/E DISAPPROVED |
06/10/2019 |
0020005 RA |
ADJMI |
|
NOT APPLICABLE
|
|
JOB WITHDRAWN 05/19/2021 THIS APPLICATION IS FILED FOR A TEMPORARY USE PER
|
|
Work on Floor(s): 001 thru 003
|
| 02/19/2019 |
321524445 |
01 |
A3 |
P APPROVED |
03/21/2019 |
0079385 PE |
ALGENDE |
|
NOT APPLICABLE
|
|
FPP- FIRE PROTECTION PLAN AS SHOWN ON DRAWINGS. JOB FILE IN CONJUNCTION WI
|
|
Work on Floor(s): SUB,CEL,ROF 001 thru 014
|
| 11/08/2018 |
340645074 |
01 |
A2 |
X SIGNED OFF |
04/29/2021 |
0090287 PE |
LOMBARDO |
|
NOT APPLICABLE
|
|
INSTALLATION OF MINI CRANE AS PER PLANS FILED HEREWITH. NO CHANGE IN USE,
|
|
Work on Floor(s): 015
|
| 07/30/2018 |
321816184 |
01 |
SC |
U COMPLETED |
08/28/2018 |
0020005 RA |
ADJMI |
|
NOT APPLICABLE
|
|
SUBDIVIDE EXISTING TAX LOT INTO FIFTY (50) CONDO TAX LOTS. NO CHANGE TO ZO
|
| 04/17/2018 |
340598133 |
01 |
A3 |
X SIGNED OFF |
06/09/2021 |
0084781 PE |
O'CONNOR |
|
NOT APPLICABLE
|
|
INSTALLATION OF ADJACENT BUILDING ROOF PROTECTION AS PER PLANS DURING NB
|
|
Work on Floor(s): OSP
|
| 04/17/2018 |
340597982 |
01 |
A2 |
X SIGNED OFF |
10/14/2021 |
0073548 PE |
GLICKMAN |
|
NOT APPLICABLE
|
|
INSTALL COMBINED SPRINKLER/STANDPIPE SYSTEM AS PER PLANS FILED. NO CHANGE
|
|
Work on Floor(s): CEL,ROF,SUB 001 thru 014
|
| 04/16/2018 |
340598099 |
01 |
A3 |
H P/E IN PROCESS |
04/16/2018 |
0084781 PE |
O'CONNOR |
|
NOT APPLICABLE
|
|
JOB WITHDRAWN 04/16/2018 INSTALLATION OF ADJACENT BUILDING ROOF PROTECTION
|
|
Work on Floor(s): OSP
|
| 02/23/2018 |
340586280 |
01 |
A3 |
X SIGNED OFF |
06/09/2021 |
0084781 PE |
O'CONNOR |
|
NOT APPLICABLE
|
|
INSTALLATION OF FRACO SEH 6000 DUAL CAR 6K CAPACITY PERSONNEL MATERIAL HOI
|
|
Work on Floor(s): OSP
|
| 01/11/2018 |
321664212 |
01 |
A2 |
R PERMIT-ENTIRE |
02/16/2018 |
0073548 PE |
GLICKMAN |
|
NOT APPLICABLE
|
|
JOB WITHDRAWN 02/04/2022 INSTALLATION OF REPEATER AUXILIARY RADIO COMMUNIC
|
|
Work on Floor(s): CEL,ROF,SUB 001 thru 014
|
| 12/15/2017 |
321664150 |
01 |
A2 |
R PERMIT-ENTIRE |
05/30/2018 |
0073548 PE |
GLICKMAN |
|
NOT APPLICABLE
|
|
INSTALLATION OF AUTOMATIC SMOKE/HEAT/CO DETECTION AND SPRINKLER FIRE ALARM
|
|
Work on Floor(s): SUB,CEL,013,014,PEN,ROF 001 thru 012
|
| 07/12/2017 |
321196200 |
10 |
NB |
P APPROVED |
07/24/2017 |
0080220 PE |
POEPPEL |
|
GRANTED 11/01/2016
|
|
POST APPROVAL AMENDMENT FOR 05
|
|
Work on Floor(s): OSP
|
| 07/12/2017 |
321196200 |
09 |
NB |
P APPROVED |
07/24/2017 |
0073403 PE |
HAYDA |
|
GRANTED 11/01/2016
|
|
POST APPROVAL AMENDMENT FOR 04
|
|
Work on Floor(s): SUB,CEL,ROF 001 thru 014
|
| 07/12/2017 |
321196200 |
08 |
NB |
P APPROVED |
07/24/2017 |
0073548 PE |
GLICKMAN |
|
GRANTED 11/01/2016
|
|
POST APPROVAL AMENDMENT FOR 03
|
|
Work on Floor(s): SUB,CEL,ROF 001 thru 014
|
| 07/12/2017 |
321196200 |
07 |
NB |
P APPROVED |
07/24/2017 |
0073403 PE |
HAYDA |
|
GRANTED 11/01/2016
|
|
POST APPROVAL AMENDMENT FOR 02
|
|
Work on Floor(s): SUB,CEL,ROF 001 thru 014
|
| 07/12/2017 |
321196200 |
06 |
NB |
P APPROVED |
07/24/2017 |
|
ADJMI |
|
GRANTED 11/01/2016
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): SUB,CEL,ROF 001 thru 014
|
| 07/12/2017 |
340522303 |
01 |
A3 |
X SIGNED OFF |
06/09/2021 |
0084781 PE |
O'CONNOR |
|
NOT APPLICABLE
|
|
INSTALLATION OF 120 LINEAR FEET TEMPORARY HEAVY DUTY SIDEWALK BRIDGE AS PE
|
|
Work on Floor(s): OSP
|
| 07/11/2017 |
340522161 |
01 |
A3 |
H P/E IN PROCESS |
07/11/2017 |
0084781 PE |
O'CONNOR |
|
NOT APPLICABLE
|
|
JOB WITHDRAWN 07/12/2017 INSTALLATION OF 120 LINEAR FEET TEMPORARY HEAVY D
|
|
Work on Floor(s): OSP
|
| 06/30/2017 |
340361487 |
02 |
A3 |
P APPROVED |
07/17/2017 |
|
VITOLANO |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): OSP
|
| 02/16/2017 |
321528343 |
01 |
A2 |
X SIGNED OFF |
09/29/2021 |
0073548 PE |
GLICKMAN |
|
NOT APPLICABLE
|
|
INSTALL TEMPORARY DRY STANDPIPE DURING CONSTRUCTION AS PER PLANS FILED. NO
|
|
Work on Floor(s): CEL,ROF,SUB 001 thru 014
|
| 04/22/2016 |
340361487 |
01 |
A3 |
R PERMIT-ENTIRE |
06/05/2017 |
0081589 PE |
VITOLANO |
|
NOT APPLICABLE
|
|
PROVIDE BUILDERS PAVEMENT PLAN (BPP) FOR A TOTAL FRONTAGE OF 75 FEET
|
|
Work on Floor(s): OSP
|
| 03/09/2016 |
321323322 |
01 |
A2 |
D A/P ENTIRE |
03/09/2016 |
0073548 PE |
GLICKMAN |
|
NOT APPLICABLE
|
|
JOB WITHDRAWN 05/12/2017 INSTALL FIRE ALARM SYSTEM AS PER PLANS FILED. NO
|
|
Work on Floor(s): SUB,CEL,ROF 001 thru 014
|
| 03/08/2016 |
340359828 |
01 |
A2 |
J P/E DISAPPROVED |
03/22/2016 |
0073548 PE |
GLICKMAN |
|
NOT APPLICABLE
|
|
JOB WITHDRAWN 04/15/2021 INSTALL COMBINED SPRINKLER/STANDPIPE SYSTEM AS PE
|
|
Work on Floor(s): SUB,CEL,ROF 001 thru 014
|
| 03/01/2016 |
321196200 |
04 |
NB |
R PERMIT-ENTIRE |
06/20/2017 |
0073403 PE |
HAYDA |
|
GRANTED 11/01/2016
|
|
STRUCTURAL WORK AS PER PLANS FILED
|
|
Work on Floor(s): SUB,CEL,ROF 001 thru 014
|
| 03/01/2016 |
321196200 |
05 |
NB |
R PERMIT-ENTIRE |
06/20/2017 |
0080220 PE |
POEPPEL |
|
GRANTED 11/01/2016
|
|
SUPPORT OF EXCAVATION (SOE) AS PER PLANS FILED.
|
|
Work on Floor(s): OSP
|