| 01/18/2018 |
320940194 |
02 |
A2 |
D A/P ENTIRE |
01/22/2018 |
|
CHAO |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): 001
|
| 06/11/2014 |
320940194 |
01 |
A2 |
R PERMIT-ENTIRE |
09/28/2016 |
0070181 PE |
CHAO |
Y |
NOT APPLICABLE
|
|
INTERIOR RENOVATION AT EXISTING STORE INCLUDES PLUMBING WORK. NO CHANGE IN
|
|
Work on Floor(s): 001
|
| 04/22/2013 |
320732007 |
02 |
A2 |
P APPROVED |
07/03/2013 |
|
HARDIE |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): 001
|
| 03/18/2013 |
320732007 |
01 |
A2 |
R PERMIT-ENTIRE |
04/10/2013 |
0058324 PE |
HARDIE |
|
NOT APPLICABLE
|
|
NON STRUCTURAL DEMOLITION & GENERAL CONSTRUCTION WORK ASSOCIATED WITH MINO
|
|
Work on Floor(s): 001
|
| 11/19/2012 |
320527658 |
01 |
SC |
U COMPLETED |
12/12/2012 |
0013747 RA |
DANIOS |
|
NOT APPLICABLE
|
|
FILING FOR THREE CONDOMINIUM TAX LOT NUMBERS. CONDOMINIUM NUMER C3303. LO
|
|
Work on Floor(s): 001 thru 006
|
| 10/23/2012 |
320141262 |
10 |
NB |
P APPROVED |
11/15/2012 |
0060293 PE |
ETTINGER |
|
GRANTED 10/21/2010
|
|
POST APPROVAL AMENDMENT FOR 02
|
|
Work on Floor(s): ROF 001 thru 006
|
| 09/18/2012 |
320189791 |
03 |
A3 |
P APPROVED |
10/05/2012 |
|
DANOIS |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): 0OS
|
| 09/18/2012 |
320141262 |
09 |
NB |
P APPROVED |
09/20/2012 |
|
DANOIS |
|
GRANTED 10/21/2010
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): ROF 001 thru 006
|
| 08/31/2012 |
320141262 |
08 |
NB |
P APPROVED |
09/24/2012 |
0060293 PE |
ETTINGER |
|
GRANTED 10/21/2010
|
|
POST APPROVAL AMENDMENT FOR 02
|
|
Work on Floor(s): ROF 001 thru 006
|
| 07/19/2012 |
320141262 |
07 |
NB |
P APPROVED |
08/07/2012 |
0060293 PE |
ETTINGER |
|
GRANTED 10/21/2010
|
|
POST APPROVAL AMENDMENT FOR 02 CONSTRUCT NEW 6 STORY MIXED USE BUILDING. I
|
|
Work on Floor(s): ROF 001 thru 006
|
| 07/14/2012 |
320141262 |
06 |
NB |
P APPROVED |
09/04/2012 |
|
DANOIS |
|
GRANTED 10/21/2010
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): ROF 001 thru 006
|
| 04/05/2012 |
320189791 |
02 |
A3 |
P APPROVED |
05/03/2012 |
|
DANOIS |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): 0OS
|
| 03/12/2012 |
320445416 |
01 |
SI |
J P/E DISAPPROVED |
04/20/2012 |
0013747 RA |
DANOIS |
|
NOT APPLICABLE
|
|
JOB WITHDRAWN 06/12/2012 SUBDIVIDE TAX LOT. FILED IN CONJUNCTION WITH NEW
|
| 03/08/2012 |
320216690 |
02 |
A2 |
P APPROVED |
09/07/2012 |
|
ETTINGER |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): ROF 001 thru 006
|
| 03/06/2012 |
320141262 |
05 |
NB |
P APPROVED |
04/04/2012 |
0060293 PE |
ETTINGER |
|
GRANTED 10/21/2010
|
|
POST APPROVAL AMENDMENT FOR 02
|
|
Work on Floor(s): ROF 001 thru 006
|
| 01/19/2012 |
320141262 |
04 |
NB |
P APPROVED |
02/24/2012 |
0060293 PE |
ETTINGER |
|
GRANTED 10/21/2010
|
|
POST APPROVAL AMENDMENT FOR 02
|
|
Work on Floor(s): ROF 001 thru 006
|
| 12/28/2011 |
320414440 |
01 |
A2 |
X SIGNED OFF |
08/01/2012 |
0016497 RA |
SAVALDI |
|
NOT APPLICABLE
|
|
INSTALLATION OF SOLAR PANELS OVER EXISTING ROOF.
|
|
Work on Floor(s): N/A
|
| 09/15/2011 |
320400188 |
01 |
A3 |
X SIGNED OFF |
01/16/2013 |
0083278 PE |
HOQUE |
|
NOT APPLICABLE
|
|
INSTALLATION OF PIPE SCAFFOLD AS PER PLANS. NO CHANGE IN USE, EGRESS, OR
|
|
Work on Floor(s): 001
|
| 11/19/2010 |
320243704 |
01 |
A3 |
X SIGNED OFF |
09/26/2012 |
0057210 PE |
WAPNER |
|
NOT APPLICABLE
|
|
INSTALLTION OF CONSTRUCTION FENCE IN CONJUNCTION WITH JOB # 320141262
|
|
Work on Floor(s): 001
|
| 09/28/2010 |
320141262 |
03 |
NB |
X SIGNED OFF |
01/16/2013 |
0060006 PE |
WEXLER |
|
GRANTED 10/21/2010
|
|
PLANS FILED FOR FOUNDATION AND SUPERSTRUCTURE OF NEW MIXED USE BUILDING.
|
|
Work on Floor(s): ROF 001 thru 006
|
| 09/20/2010 |
320141262 |
02 |
NB |
X SIGNED OFF |
01/16/2013 |
0060293 PE |
ETTINGER |
|
GRANTED 10/21/2010
|
|
CONSTRUCT NEW 6 STORY MIXED USE BUILDING. INSTALL CONSTRUCTION FENCE INSTA
|
|
Work on Floor(s): ROF 001 thru 006
|
| 09/20/2010 |
320216690 |
01 |
A2 |
X SIGNED OFF |
12/20/2012 |
0060293 PE |
ETTINGER |
|
NOT APPLICABLE
|
|
INSTALL COMBINED STANDPIPE AND SPRINKLER SYSTEM IN NEW MIXED USE BUILDING.
|
|
Work on Floor(s): ROF 001 thru 006
|
| 09/16/2010 |
320215717 |
01 |
A2 |
X SIGNED OFF |
12/08/2012 |
0060293 PE |
ETTINGER |
|
NOT APPLICABLE
|
|
INSTALL SMOKE/HEAT/CO DETECTION AND SPRINKLER FIRE ALARM SYSTEM.
|
|
Work on Floor(s): ROO 001 thru 006
|
| 07/20/2010 |
320189791 |
01 |
A3 |
X SIGNED OFF |
12/11/2012 |
0013747 RA |
DANOIS |
|
NOT APPLICABLE
|
|
BNP 10-173,400' FRONTAGE, NB#320141262 ( SITE C )
|
|
Work on Floor(s): 0OS
|
| 05/04/2010 |
320141262 |
01 |
NB |
X SIGNED OFF |
01/16/2013 |
0013747 RA |
DANOIS |
|
GRANTED 10/21/2010
|
|
CONSTRUCT NEW 6 STORY MIXED USE BUILDING. INSTALL CONSTRUCTION FENCE INSTA
|
|
Work on Floor(s): ROF 001 thru 006
|