| FILE DATE |
JOB # |
DOC # |
JOB TYPE |
JOB STATUS |
STATUS DATE |
LIC # |
APPLICANT |
IN AUDIT |
ZONING APPROVAL |
| 08/12/2022 |
320915943 |
15 |
NB |
P APPROVED |
09/16/2022 |
|
CHAN |
|
GRANTED 03/13/2015
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,ROF 001 thru 005
|
| 06/21/2022 |
320915943 |
14 |
NB |
P APPROVED |
07/06/2022 |
|
CHAN |
|
GRANTED 03/13/2015
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,ROF 001 thru 005
|
| 09/10/2021 |
340674693 |
04 |
A2 |
P APPROVED |
09/21/2021 |
|
SHAH |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,ROF 001 thru 005
|
| 08/18/2021 |
320915943 |
13 |
NB |
P APPROVED |
08/19/2021 |
0090137 PE |
SHAH |
|
GRANTED 03/13/2015
|
|
POST APPROVAL AMENDMENT FOR 02
|
|
Work on Floor(s): CEL,ROO 001 thru 005
|
| 07/20/2021 |
340674693 |
03 |
A2 |
P APPROVED |
08/30/2021 |
|
SHAH |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,ROF 001 thru 005
|
| 07/20/2021 |
320915943 |
12 |
NB |
P APPROVED |
08/05/2021 |
|
CHAN |
|
GRANTED 03/13/2015
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,ROF 001 thru 005
|
| 05/25/2021 |
340674693 |
02 |
A2 |
P APPROVED |
07/01/2021 |
|
SHAH |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,ROF 001 thru 005
|
| 05/21/2021 |
320915943 |
11 |
NB |
P APPROVED |
06/01/2021 |
0090137 PE |
SHAH |
|
GRANTED 03/13/2015
|
|
POST APPROVAL AMENDMENT FOR 02
|
|
Work on Floor(s): CEL,ROO 001 thru 005
|
| 05/11/2021 |
321059484 |
04 |
A2 |
D A/P ENTIRE |
06/08/2021 |
|
SHAH |
|
NOT APPLICABLE
|
|
DOC WITHDRAWN 09/22/2021
|
|
Work on Floor(s): CEL,ROF 001 thru 005
|
| 03/23/2021 |
320915943 |
10 |
NB |
P APPROVED |
03/26/2021 |
|
CHAN |
|
GRANTED 03/13/2015
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,ROF 001 thru 005
|
| 11/09/2020 |
320915943 |
09 |
NB |
P APPROVED |
12/31/2020 |
|
CHAN |
|
GRANTED 03/13/2015
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,ROF 001 thru 005
|
| 09/29/2020 |
340770598 |
01 |
A3 |
X SIGNED OFF |
08/10/2021 |
0090372 PE |
ZDANCEWI |
|
NOT APPLICABLE
|
|
INSTALLATION OF TEMPORARY NEEDLE BEAM AS PER PLANS. WORK SHALL COMPLY WITH
|
|
Work on Floor(s): OSP
|
| 08/21/2020 |
320915943 |
08 |
NB |
P APPROVED |
08/28/2020 |
0090137 PE |
SHAH |
|
GRANTED 03/13/2015
|
|
POST APPROVAL AMENDMENT FOR 02
|
|
Work on Floor(s): CEL,ROO 001 thru 005
|
| 08/12/2020 |
340159358 |
02 |
A3 |
D A/P ENTIRE |
10/16/2020 |
|
CHAN |
|
NOT APPLICABLE
|
|
DOC WITHDRAWN 09/22/2021
|
|
Work on Floor(s): OSP
|
| 05/26/2020 |
340729992 |
01 |
A3 |
H P/E IN PROCESS |
05/26/2020 |
0090372 PE |
ZDANCEWI |
|
NOT APPLICABLE
|
|
ADMIN CLOSED 07/25/2020 INSTALLATION OF TEMPORARY NEEDLE BEAM AS PER PLANS
|
|
Work on Floor(s): OSP
|
| 03/16/2020 |
321564721 |
03 |
A2 |
D A/P ENTIRE |
08/19/2021 |
|
WANG |
|
NOT APPLICABLE
|
|
DOC WITHDRAWN 09/22/2021
|
|
Work on Floor(s): CEL
|
| 02/05/2020 |
340641988 |
02 |
A3 |
P APPROVED |
02/14/2020 |
|
DOOLING |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): OSP
|
| 07/24/2019 |
320915943 |
07 |
NB |
P APPROVED |
08/28/2019 |
0090137 PE |
SHAH |
|
GRANTED 03/13/2015
|
|
POST APPROVAL AMENDMENT FOR 02
|
|
Work on Floor(s): CEL,ROO 001 thru 005
|
| 05/03/2019 |
340674693 |
01 |
A2 |
X SIGNED OFF |
04/25/2022 |
0090137 PE |
SHAH |
|
NOT APPLICABLE
|
|
HEREWITH FILE SPRINKLER AND STANDPIPE TO SUPERSEDE EXPIRED APPLICATION#340
|
|
Work on Floor(s): CEL,ROF 001 thru 005
|
| 03/26/2019 |
321059484 |
03 |
A2 |
P APPROVED |
10/28/2019 |
|
CHEN |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01 INSTALLATION OF MANUAL & AUTOMATIC SMOKE/HE
|
|
Work on Floor(s): CEL,ROF 001 thru 005
|
| 10/22/2018 |
340641988 |
01 |
A3 |
X SIGNED OFF |
08/10/2021 |
0019131 RA |
DOOLING |
|
NOT APPLICABLE
|
|
INSTALLATION OF NEEDLE BEAM AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCU
|
|
Work on Floor(s): OSP
|
| 05/07/2018 |
320915943 |
06 |
NB |
P APPROVED |
08/10/2018 |
|
CHAN |
|
GRANTED 03/13/2015
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL 001 thru 005
|
| 04/20/2018 |
320915943 |
05 |
NB |
P APPROVED |
08/10/2018 |
0090137 PE |
SHAH |
|
GRANTED 03/13/2015
|
|
POST APPROVAL AMENDMENT FOR 02
|
|
Work on Floor(s): CEL,ROO 001 thru 005
|
| 04/19/2018 |
321059484 |
02 |
A2 |
P APPROVED |
05/21/2018 |
|
SHAH |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,ROF 001 thru 005
|
| 05/11/2017 |
321564721 |
02 |
A2 |
X SIGNED OFF |
09/23/2021 |
0074354 PE |
WANG |
|
NOT APPLICABLE
|
|
SUBSEQUENT FILE FOR FOUNDATION WORK
|
|
Work on Floor(s): OSP
|
| 04/27/2017 |
321564721 |
01 |
A2 |
X SIGNED OFF |
09/23/2021 |
0074354 PE |
WANG |
|
NOT APPLICABLE
|
|
FILING FOR THE SOE IN CONJUNCTION WITH NEW BUILDING NUMBER 320915943. IN
|
|
Work on Floor(s): OSP
|
| 03/08/2017 |
340474659 |
01 |
A2 |
J P/E DISAPPROVED |
04/07/2017 |
0074354 PE |
WANG |
|
NOT APPLICABLE
|
|
JOB WITHDRAWN 04/19/2017 FILING FOR THE FOUNDATION IN CONJUNCTION WITH NEW
|
|
Work on Floor(s): OSP
|
| 04/14/2015 |
320915943 |
04 |
NB |
P APPROVED |
07/07/2017 |
0061890 PE |
DOSHI |
|
GRANTED 03/13/2015
|
|
POST APPROVAL AMENDMENT FOR 03
|
|
Work on Floor(s): CEL 001 thru 005
|
| 02/04/2015 |
340228809 |
01 |
A2 |
D A/P ENTIRE |
02/04/2015 |
0081443 PE |
CAMULAIR |
|
NOT APPLICABLE
|
|
JOB WITHDRAWN 05/20/2015 SHORING & EXCAVATION PLANS FILED IN CONJUNCTION W
|
|
Work on Floor(s): OSP
|
| 01/23/2015 |
321059484 |
01 |
A2 |
X SIGNED OFF |
04/25/2022 |
0090137 PE |
SHAH |
|
NOT APPLICABLE
|
|
INSTALLATION OF MANUAL & AUTOMATIC SMOKE/HEAT/CO DETECTION AND SPRINKLER F
|
|
Work on Floor(s): CEL,ROF 001 thru 005
|
| 01/20/2015 |
320915943 |
03 |
NB |
X SIGNED OFF |
12/09/2022 |
0061890 PE |
DOSHI |
|
GRANTED 03/13/2015
|
|
HEREWITH FILE STRUCTURE PLANS FOR NEW BUILDING.
|
|
Work on Floor(s): CEL 001 thru 005
|
| 11/14/2014 |
320915943 |
02 |
NB |
X SIGNED OFF |
12/09/2022 |
0090137 PE |
SHAH |
|
GRANTED 03/13/2015
|
|
HEREWITH FILE PLUMBING AND MECHANICAL FOR NEW BUILDING
|
|
Work on Floor(s): CEL,ROO 001 thru 005
|
| 11/10/2014 |
340204861 |
01 |
A2 |
P APPROVED |
01/21/2015 |
0090137 PE |
SHAH |
|
NOT APPLICABLE
|
|
JOB WITHDRAWN 09/22/2021 HEREWITH FILE SPRINKLER AND STANDPIPE IN CONJUNCT
|
|
Work on Floor(s): CEL,ROF 001 thru 005
|
| 11/05/2014 |
340204111 |
01 |
A3 |
X SIGNED OFF |
08/10/2021 |
0083278 PE |
HOQUE |
|
NOT APPLICABLE
|
|
INSTALLATION OF SIDEWALK SHED AS PER PLANS. WORK SHALL COMPLY WITH 2008 BU
|
|
Work on Floor(s): OSP
|
| 11/04/2014 |
340203470 |
01 |
A2 |
J P/E DISAPPROVED |
12/20/2014 |
0081443 PE |
CAMULAIR |
|
NOT APPLICABLE
|
|
JOB WITHDRAWN 01/29/2015 FILING STRUCTURAL PLANS FOR NEW BUILDING
|
|
Work on Floor(s): CEL,ROF,SUB 001 thru 005
|
| 08/15/2014 |
320933807 |
01 |
DM |
X SIGNED OFF |
04/05/2015 |
OT |
SAN MIGU |
|
NOT APPLICABLE
|
|
FILING FOR DEMOLITION
|
|
Work on Floor(s): 001 thru 002
|
| 08/01/2014 |
321159429 |
01 |
A3 |
X SIGNED OFF |
08/18/2021 |
0063652 PE |
KARANTIN |
|
NOT APPLICABLE
|
|
FILING FOR FENCE FOR THE SAFETY OF THE PUBLIC.
|
|
Work on Floor(s): OSP
|
| 07/02/2014 |
340159456 |
01 |
A3 |
X SIGNED OFF |
08/23/2021 |
0015817 RA |
CHAN |
|
NOT APPLICABLE
|
|
INSTALL 22'-0" CURBCUT INCLUDING (2) 2'-6" SPLAYS 340' FROM INTERSECTION O
|
|
Work on Floor(s): OSP
|
| 07/02/2014 |
340159385 |
01 |
A3 |
X SIGNED OFF |
08/23/2021 |
0015817 RA |
CHAN |
|
NOT APPLICABLE
|
|
INSTALL 30' CURBCUT, INCLUDING (2) 2'-6" SPLAYS 298' FROM THE INTERSECTION
|
|
Work on Floor(s): OSP
|
| 07/02/2014 |
340159358 |
01 |
A3 |
X SIGNED OFF |
11/16/2021 |
0015817 RA |
CHAN |
|
NOT APPLICABLE
|
|
BUILDERS PAVEMENT PLAN IN CONJUNCTION WITH NEW BUILDING # 320915943. NO CH
|
|
Work on Floor(s): OSP
|