| FILE DATE |
JOB # |
DOC # |
JOB TYPE |
JOB STATUS |
STATUS DATE |
LIC # |
APPLICANT |
IN AUDIT |
ZONING APPROVAL |
| 12/29/2017 |
321704839 |
01 |
A2 |
R PERMIT-ENTIRE |
04/13/2018 |
0093652 PE |
POWERS |
|
NOT APPLICABLE
|
|
INSTALLATION OF A BLOOM ENERGY ES5 OUTDOOR NATURAL GAS CLEAN ENERGY SERVER
|
|
Work on Floor(s): OSP
|
| 02/04/2009 |
310292821 |
01 |
A2 |
X SIGNED OFF |
07/13/2009 |
0041740 PE |
KLEIN |
|
NOT APPLICABLE
|
|
SUBMITTED HEREWITH IS THE FUEL STORAGE PORTION FOR THE EMERGENCY GENERATOR
|
|
Work on Floor(s): OSP
|
| 09/15/2008 |
310198602 |
01 |
A2 |
X SIGNED OFF |
04/29/2009 |
0074116 PE |
FITZPATR |
|
NOT APPLICABLE
|
|
SUBMITTED HEREWITH IS THE HOT WATER BOILERS ONLY. ALL RELATED WORK IS ON
|
|
Work on Floor(s): CEL
|
| 08/13/2008 |
301984422 |
03 |
A2 |
P APPROVED |
09/23/2008 |
|
KLEIN |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,PEN,ROF 001 thru 007
|
| 07/14/2008 |
301916023 |
07 |
NB |
P APPROVED |
09/04/2008 |
|
SELAN |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,PEN 001 thru 007
|
| 06/23/2008 |
301916032 |
03 |
A2 |
G PAA FEE DUE |
06/23/2008 |
|
BRAZIL |
|
NOT APPLICABLE
|
|
DOC WITHDRAWN 08/21/2008
|
|
Work on Floor(s): OSP
|
| 06/23/2008 |
302084152 |
02 |
A2 |
P APPROVED |
08/12/2008 |
0081796 PE |
MOLINA |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,PEN 001 thru 007
|
| 05/15/2008 |
301916023 |
06 |
NB |
P APPROVED |
05/24/2008 |
|
SELAN |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,PEN 001 thru 007
|
| 05/13/2008 |
310140166 |
01 |
A3 |
X SIGNED OFF |
11/18/2008 |
0058106 PE |
YU |
|
NOT APPLICABLE
|
|
ONE 27' WIDE CURB CUT ON CLARKSON AVENUE- 181' EAST OF NEW YORK AVENUE AS
|
|
Work on Floor(s): OSP
|
| 05/13/2008 |
310140157 |
01 |
A3 |
X SIGNED OFF |
11/18/2008 |
0058106 PE |
YU |
|
NOT APPLICABLE
|
|
ONE 27' WIDE CURB CUT ON CLARKSON AVENUE-355' EAST OF NEW YORK AVENUE AS P
|
|
Work on Floor(s): OSP
|
| 05/13/2008 |
310140148 |
01 |
A3 |
X SIGNED OFF |
11/18/2008 |
0058106 PE |
YU |
|
NOT APPLICABLE
|
|
ONE 27' WIDE CURB CUT ON WINTHROP STREET- 298' EAST OF NEW YORK AVENUE AS
|
|
Work on Floor(s): OSP
|
| 03/26/2008 |
301984422 |
02 |
A2 |
P APPROVED |
04/30/2008 |
|
KLEIN |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,PEN 001 thru 007
|
| 03/23/2008 |
301984440 |
04 |
A2 |
P APPROVED |
09/26/2008 |
|
KENNETH |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 02
|
|
Work on Floor(s): CEL,PEN 001 thru 007
|
| 03/23/2008 |
301984440 |
03 |
A2 |
P APPROVED |
07/17/2008 |
|
KENNETH |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,PEN 001 thru 007
|
| 12/19/2007 |
301916023 |
05 |
NB |
P APPROVED |
03/06/2008 |
0010545 RA |
SELAN |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01 WE RESPECTFULLY REQUEST TO REVISE THE SCHED
|
|
Work on Floor(s): CEL,PEN 001 thru 007
|
| 12/18/2007 |
301916032 |
02 |
A2 |
P APPROVED |
03/25/2008 |
0062542 PE |
BRAZIL |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): OSP
|
| 05/17/2007 |
302343453 |
01 |
PA |
U COMPLETED |
04/14/2009 |
0010545 RA |
SELAN |
|
NOT APPLICABLE
|
|
KINGS COUNTY HOSPITAL CENTER BLDG R
|
|
Work on Floor(s): 007
|
| 04/27/2006 |
302148487 |
01 |
A3 |
X SIGNED OFF |
02/04/2008 |
0065430 PE |
HICKEY |
|
NOT APPLICABLE
|
|
INSTALLATION OF A HEAVY DUTY SHED 164' DURING FACADE REPAIR. NO CHANGE I
|
|
Work on Floor(s): 001
|
| 02/24/2006 |
301984440 |
02 |
A2 |
X SIGNED OFF |
02/12/2009 |
0041740 PE |
KENNETH |
|
NOT APPLICABLE
|
|
INSTALLATION OF A NEW COMBINED SPRINKLER STANDPIPE SYSTEM FOR THE NEW
|
|
Work on Floor(s): CEL,PEN 001 thru 007
|
| 02/21/2006 |
302084152 |
01 |
A2 |
X SIGNED OFF |
03/19/2009 |
0081796 PE |
MOLINA |
|
NOT APPLICABLE
|
|
INSTALLATION OF THE STEAM DESTRIBUTION
|
|
Work on Floor(s): CEL,PEN 001 thru 007
|
| 01/27/2006 |
302076349 |
01 |
A2 |
X SIGNED OFF |
05/04/2009 |
0041740 PE |
KLEIN |
|
NOT APPLICABLE
|
|
INSTALLATION FO EMERGENCY GENERATOR ANDTHE ASSOCIATED FUEL STORAGE TANK
|
|
Work on Floor(s): CEL
|
| 11/14/2005 |
302032057 |
01 |
A3 |
X SIGNED OFF |
02/04/2008 |
0020419 RA |
Hulme |
|
NOT APPLICABLE
|
|
Erect a sidewalk shed 640 ft inconjunction with construction of Building R
|
|
Work on Floor(s): 001
|
| 10/14/2005 |
302016627 |
01 |
A2 |
X SIGNED OFF |
03/19/2009 |
0058727 PE |
JORDAN |
|
NOT APPLICABLE
|
|
INSTALLATION OF A NEW FA SYS FOR THE KINGS COUNTY PSYCHIATRIC BLDG
|
|
Work on Floor(s): CEL,PEN 001 thru 007
|
| 10/04/2005 |
301916023 |
04 |
NB |
X SIGNED OFF |
07/21/2009 |
0625421 PE |
BRAZIL |
|
NOT APPLICABLE
|
|
PLACEMENT OF CONCRETE FOR NEW KINGS COUNTY PSYCHIATRIC BUILDING.
|
|
Work on Floor(s): CEL,PEN 001 thru 007
|
| 09/13/2005 |
302003695 |
01 |
A3 |
X SIGNED OFF |
07/17/2009 |
0058106 PE |
YU |
|
NOT APPLICABLE
|
|
TWO (2) 22' WIDE CURB CUTS ON CLARKSON AVENUE 181 EAST AND 355 EAST NEW
|
|
Work on Floor(s): CEL,PEN 001 thru 007
|
| 09/12/2005 |
302003613 |
01 |
A3 |
R PERMIT-ENTIRE |
08/02/2007 |
0581061 PE |
YU |
|
NOT APPLICABLE
|
|
JOB WITHDRAWN 03/17/2009 ONE 27 FT CURB CUT WITH 2'6" SPLAY EACHSIDE
|
|
Work on Floor(s): CEL,PEN 001 thru 007
|
| 09/12/2005 |
302003604 |
01 |
A3 |
R PERMIT-ENTIRE |
08/02/2007 |
0581061 PE |
YU |
|
NOT APPLICABLE
|
|
JOB WITHDRAWN 03/17/2009
|
|
Work on Floor(s): PEN,CEL 001 thru 007
|
| 09/12/2005 |
302003597 |
01 |
A3 |
R PERMIT-ENTIRE |
08/02/2007 |
0581061 PE |
YU |
|
NOT APPLICABLE
|
|
JOB WITHDRAWN 03/17/2009
|
|
Work on Floor(s): CEL,PEN 001 thru 007
|
| 08/04/2005 |
301984440 |
01 |
A2 |
X SIGNED OFF |
02/12/2009 |
0041740 PE |
KENNETH |
|
NOT APPLICABLE
|
|
INSTALLATION OF A NEW COMBINED SPRINKLER-STANDPIPE SYSTEM FOR THE NEW KI
|
|
Work on Floor(s): CEL,PEN 001 thru 007
|
| 08/04/2005 |
301984431 |
01 |
A2 |
J P/E DISAPPROVED |
11/18/2005 |
0041740 PE |
KENNETH |
|
NOT APPLICABLE
|
|
JOB WITHDRAWN 02/06/2006 INSTALLATION OF A NEW STANDPIPE SYSTEMFOR THE NEW
|
|
Work on Floor(s): CEL,PEN 001 thru 007
|
| 08/04/2005 |
301984422 |
01 |
A2 |
X SIGNED OFF |
02/12/2009 |
0041740 PE |
KLEIN |
|
NOT APPLICABLE
|
|
INSTALLATION OF NEW MECHEANICAL AND PLUMBING FOR THE NEW KINGS COUNTY
|
|
Work on Floor(s): CEL,PEN,ROF 001 thru 007
|
| 05/03/2005 |
301928047 |
01 |
A3 |
X SIGNED OFF |
01/09/2009 |
0020419 RA |
Hulme |
|
NOT APPLICABLE
|
|
Erect a temporary plywood fence 1200 ft long incunjunction with constructi
|
|
Work on Floor(s): 001
|
| 04/12/2005 |
301916023 |
02 |
NB |
X SIGNED OFF |
07/21/2009 |
0010545 RA |
BRAZIL |
|
NOT APPLICABLE
|
|
SITE CIVIL WORK FOR THE NEW KINGS COUNTY PSYCHIATRIC BUILDING
|
|
Work on Floor(s): CEL,PEN 001 thru 007
|
| 04/12/2005 |
301916023 |
01 |
NB |
X SIGNED OFF |
07/21/2009 |
0010545 RA |
SELAN |
|
NOT APPLICABLE
|
|
WE RESPECTFULLY REQUEST TO REVISE THE SCHEDULE A FORM
|
|
Work on Floor(s): CEL,PEN 001 thru 007
|
| 03/24/2005 |
301916032 |
01 |
A2 |
X SIGNED OFF |
01/28/2009 |
0062542 PE |
BRAZIL |
|
NOT APPLICABLE
|
|
EXCAVATION AND FOUNDATION FOR THE NEW KI NGS COUNTY PSYCHIATRIC BUILDING
|
|
Work on Floor(s): OSP
|
| 07/25/2001 |
301216805 |
01 |
DM |
X SIGNED OFF |
12/03/2001 |
|
HENAO |
|
NOT APPLICABLE
|
|
Work on Floor(s): ___
|
| 06/19/2001 |
301188970 |
01 |
A3 |
X SIGNED OFF |
08/09/2005 |
0066685 PE |
GORDON |
|
NOT APPLICABLE
|
|
EQUIPMENT USE IN CONJUNCTION WITH ALTERATION PERMIT USING BOBCAT/GEHLS
|
|
Work on Floor(s): 005
|
| 06/19/2001 |
301188961 |
01 |
A2 |
Q PERMIT-PARTIAL |
06/19/2001 |
0066685 PE |
GORDON |
|
NOT APPLICABLE
|
|
JOB WITHDRAWN 06/12/2008 REMOVAL OF EAST, WEST, SOUTHWEST WINGS ALONG WITH
|
|
Work on Floor(s): 005
|
| 05/29/2001 |
301174128 |
01 |
A3 |
X SIGNED OFF |
06/01/2007 |
0065430 PE |
Hickey |
|
NOT APPLICABLE
|
|
INSTALLATION OF A HEAVY DUTY SIDEWALK BRIDGE 275' DURING FACADE REPAIR.
|
|
Work on Floor(s): 001
|
| 05/29/2001 |
301173995 |
01 |
A3 |
X SIGNED OFF |
06/01/2007 |
0065430 PE |
Hickey |
|
NOT APPLICABLE
|
|
INSTALLATION OF AN 8' HIGH PLYWOOD CONSTRUCTION FENCE 750' DURING FACADE R
|
|
Work on Floor(s): 001
|