| FILE DATE |
JOB # |
DOC # |
JOB TYPE |
JOB STATUS |
STATUS DATE |
LIC # |
APPLICANT |
IN AUDIT |
ZONING APPROVAL |
| 05/02/2014 |
320966558 |
01 |
A2 |
X SIGNED OFF |
11/09/2015 |
0061276 PE |
GYEBI |
|
NOT APPLICABLE
|
|
INSTALL FIXTURES IN EXISTING PLUMBING ROUGHING IN COOKING SPACES IN DWELLI
|
|
Work on Floor(s): CEL 001 thru 004
|
| 10/16/2013 |
302046523 |
02 |
A2 |
P APPROVED |
11/13/2013 |
0633676 PE |
STASZEWS |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01 INSTALLATION OF CLASS "J" FA SYSTEM. FLOOR
|
|
Work on Floor(s): CEL,ROF 001 thru 004
|
| 03/15/2012 |
320449190 |
01 |
A2 |
X SIGNED OFF |
08/14/2013 |
0061276 PE |
GYEBI |
|
NOT APPLICABLE
|
|
CONSTRUCTION OF STAIRS & HANDICAPPED RAMP FROM GRADE TO CELLAR. NO CHANGE
|
|
Work on Floor(s): OSP,CEL
|
| 02/28/2012 |
320440518 |
01 |
A2 |
R PERMIT-ENTIRE |
11/12/2013 |
0061276 PE |
GYEBI |
|
NOT APPLICABLE
|
|
FUEL STORAGE
|
|
Work on Floor(s): OSP
|
| 02/27/2012 |
320234812 |
02 |
PA |
P APPROVED |
04/04/2012 |
|
GYEBI |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL
|
| 11/15/2010 |
320234812 |
01 |
PA |
U COMPLETED |
04/24/2012 |
0061276 PE |
GYEBI |
|
NOT APPLICABLE
|
|
Work on Floor(s): CEL
|
| 05/04/2010 |
320154051 |
01 |
A3 |
X SIGNED OFF |
06/06/2012 |
0061276 PE |
GYEBI |
|
NOT APPLICABLE
|
|
TO FILE FIRE PROTECTION PLAN AND FIRE SAFETY PLAN IN CONJUNCTION WITH ALTE
|
|
Work on Floor(s): 001 thru 002 003 thru 004
|
| 12/28/2009 |
301773668 |
03 |
A1 |
P APPROVED |
12/31/2009 |
|
GYEBI |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,001,002,003,004
|
| 11/30/2009 |
302015753 |
05 |
A2 |
P APPROVED |
11/30/2009 |
|
GYEBI |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL 001 thru 004
|
| 08/06/2009 |
302015753 |
04 |
A2 |
P APPROVED |
08/06/2009 |
|
GYEBI |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL 001 thru 004
|
| 06/23/2009 |
302015753 |
03 |
A2 |
P APPROVED |
07/08/2009 |
|
GYEBI |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL 001 thru 004
|
| 12/23/2008 |
310245375 |
01 |
A2 |
X SIGNED OFF |
02/23/2010 |
0050579 PE |
RUDIKOFF |
|
NOT APPLICABLE
|
|
INSTALL TWO (2) NEW GAS HOT WATER BOILERS, AND TWO (2) NEW HOT WATER STORA
|
|
Work on Floor(s): CEL
|
| 10/02/2008 |
302015753 |
02 |
A2 |
P APPROVED |
03/11/2009 |
|
GYEBI |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): BAS 001 thru 004
|
| 09/24/2008 |
302015762 |
02 |
A2 |
P APPROVED |
11/14/2008 |
0061276 PE |
GYEBI |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): BAS,001,002,003,004
|
| 04/09/2007 |
301773668 |
02 |
A1 |
P APPROVED |
09/07/2007 |
0061276 PE |
GYEBI |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,001,002,003,004
|
| 01/20/2006 |
302046523 |
01 |
A2 |
X SIGNED OFF |
11/13/2013 |
0633676 PE |
STASZEWS |
|
NOT APPLICABLE
|
|
INSTALLATION OF CLASS "J" FA SYSTEM. FLOOR CHANGE TO C,1-4,R.
|
|
Work on Floor(s): CEL,ROF 001 thru 004
|
| 10/06/2005 |
302015762 |
01 |
A2 |
X SIGNED OFF |
10/15/2013 |
0077896 PE |
GYEBI |
|
NOT APPLICABLE
|
|
APPLICATION FILED FOR SPRINKLER SYSTEMSPRINKLER DRAWINGS & SCHEDULE B
|
|
Work on Floor(s): BAS,001,002,003,004
|
| 10/05/2005 |
302015753 |
01 |
A2 |
X SIGNED OFF |
01/11/2010 |
0061276 PE |
GYEBI |
|
NOT APPLICABLE
|
|
APPLICATION FILED FOR PLUMBING & HVAC SYSTEMS SCHEDULE'B' & PLUMBING/HVA
|
|
Work on Floor(s): CEL 001 thru 004
|
| 03/23/2004 |
301773668 |
01 |
A1 |
X SIGNED OFF |
11/21/2013 |
0061276 PE |
GYEBI |
|
NOT APPLICABLE
|
|
ERECTION OF INTERIOR PARTITION & CONVERSION OF EXISTING FACTORY B
|
|
Work on Floor(s): CEL,001,002,003,004
|
| 03/11/2004 |
301814115 |
01 |
A2 |
X SIGNED OFF |
03/22/2010 |
0061276 PE |
GYEBI |
|
NOT APPLICABLE
|
|
APPLICATION FILED TO CREATE OPENING FOR NEW WINDOWS @ EXIST WALL; REPAIR
|
|
Work on Floor(s): CEL 001 thru 004
|