| FILE DATE |
JOB # |
DOC # |
JOB TYPE |
JOB STATUS |
STATUS DATE |
LIC # |
APPLICANT |
IN AUDIT |
ZONING APPROVAL |
| 03/25/2019 |
340667987 |
01 |
A3 |
H P/E IN PROCESS |
03/25/2019 |
0076655 PE |
LU |
|
NOT APPLICABLE
|
|
ADMIN CLOSED 05/24/2019 INSTALL TEMPORARY ROOF PROTECTION AS PER PLAN IN C
|
|
Work on Floor(s): ROF
|
| 04/29/2013 |
320756133 |
01 |
A2 |
X SIGNED OFF |
11/18/2013 |
0024178 RA |
VEDMED |
|
NOT APPLICABLE
|
|
INSTALLATION OF DRY CHEMICAL FIRE SUPPRESSION SYSTEM IN CONJUNCTION WITH J
|
|
Work on Floor(s): 1ST
|
| 12/03/2012 |
320750852 |
01 |
A2 |
X SIGNED OFF |
10/24/2013 |
0046665 PE |
FRIEDLAN |
|
NOT APPLICABLE
|
|
INSTALL PAINT SPRAY BOOTH AND CONSTRUCT PAINT MIXING ROOM ON FIRST FLOOR.
|
|
Work on Floor(s): 001
|
| 10/04/2012 |
320554128 |
01 |
A2 |
P APPROVED |
10/04/2012 |
0062199 PE |
SHINFELD |
|
NOT APPLICABLE
|
|
INSTALLING LOW PRESSURE STEAM BOILER.
|
|
Work on Floor(s): CEL
|
| 05/27/2011 |
320311747 |
01 |
A3 |
R PERMIT-ENTIRE |
05/27/2011 |
0084178 PE |
ALI |
|
NOT APPLICABLE
|
|
REMOVE AND REPLACE PARAPET WALL APPROX. 70 LF AS PER PLAN. LIFTING THE ECB
|
|
Work on Floor(s): OSP
|