10/08/2014 |
340194603 |
01 |
A2 |
R PERMIT-ENTIRE |
10/08/2014 |
0084178 PE |
ALI |
Y |
NOT APPLICABLE
|
|
INTERIOR RENOVATION OF EXISTING APARTMENT 2 ON THE 2ND FLOOR AS PER PLAN.
|
|
Work on Floor(s): 002
|
12/09/2009 |
320099326 |
01 |
A2 |
Q PERMIT-PARTIAL |
12/16/2009 |
0016966 RA |
GALLO |
|
NOT APPLICABLE
|
|
INTERIOR RENOVATION TO INCLUDE THE REMOVAL AND INSTALLATION OF NON-LOAD BE
|
|
Work on Floor(s): 001
|
07/07/2008 |
310139962 |
02 |
A2 |
P APPROVED |
07/08/2008 |
|
HAHN |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): 001
|
05/12/2008 |
310139962 |
01 |
A2 |
X SIGNED OFF |
08/28/2008 |
0053541 PE |
HAHN |
|
NOT APPLICABLE
|
|
INSTALL KITCHEN FIRE SUPPRESSION SYSTEM IN CONJUNCTION WITH JOB#310059860,
|
|
Work on Floor(s): 001
|
11/29/2007 |
310059860 |
01 |
A2 |
X SIGNED OFF |
09/05/2008 |
0010971 RA |
Ruderman |
|
NOT APPLICABLE
|
|
Convert cleaning store UG6 to Eating & Drinking Place UG6. No change to eg
|
|
Work on Floor(s): 001 001 thru 001
|
08/17/2004 |
301599394 |
01 |
A2 |
X SIGNED OFF |
05/23/2005 |
0007531 PE |
SCHNALL |
|
NOT APPLICABLE
|
|
REPLACE BOILER & BURNER NO CHANGE TO EGRESS OCCUPANCY
|
|
Work on Floor(s): CEL
|
11/29/2000 |
301102385 |
01 |
A2 |
X SIGNED OFF |
02/27/2001 |
0050579 PE |
RUDIKOFF |
|
NOT APPLICABLE
|
|
REPLACE OIL FIRED HIGH BOILER. NO CHANGE IN EGRESS,OCCUPANCY OR
|
|
Work on Floor(s): CEL
|
02/09/2000 |
300995715 |
01 |
A2 |
X SIGNED OFF |
03/08/2000 |
0050579 PE |
RUDIKOFF |
|
NOT APPLICABLE
|
|
REPLACE DRY CLEANING MACHNIE IN EXISTING DRY CLEANING STORE UG 6 NO CHA
|
|
Work on Floor(s): CEL,001
|
08/05/1998 |
300775472 |
01 |
A1 |
J P/E DISAPPROVED |
09/03/1998 |
0015011 RA |
MUROFF |
|
NOT APPLICABLE
|
|
ADMIN CLOSED 10/24/2012 FILING FOR CHANGE OF USE AT FIRST FLOOR FROM COMME
|
|
Work on Floor(s): 004
|
03/02/1998 |
300708893 |
01 |
A2 |
X SIGNED OFF |
06/19/1998 |
0074129 PE |
HOURIZAD |
|
NOT APPLICABLE
|
|
ADDITION OF BATHROOM AND A DOOR OPENING TO APARTMENT 3L (EAST APARTMENT
|
|
Work on Floor(s): 3
|