| FILE DATE |
JOB # |
DOC # |
JOB TYPE |
JOB STATUS |
STATUS DATE |
LIC # |
APPLICANT |
IN AUDIT |
ZONING APPROVAL |
| 09/19/2022 |
322107144 |
02 |
DM |
X SIGNED OFF |
03/28/2023 |
0092183 PE |
PATTERSO |
|
NOT APPLICABLE
|
|
SUBSEQUENT FILING FOR MECHANICAL MEANS WILL BE USED, TO ASSIST WITH DEMOL
|
|
Work on Floor(s): ENT
|
| 05/05/2022 |
322107144 |
01 |
DM |
X SIGNED OFF |
03/28/2023 |
0092183 PE |
PATTERSO |
|
NOT APPLICABLE
|
|
FULL DEMOLITION OF ONE-STORY STRUCTURE.
|
|
Work on Floor(s): ENT
|
| 09/03/2013 |
320855311 |
03 |
A2 |
X SIGNED OFF |
12/09/2014 |
0073350 PE |
LEVIN |
|
NOT APPLICABLE
|
|
MECHANICAL WORK IN CONJUNCTION WITH 1ST FLOOR INTERIOR RENOVATION TO EXIST
|
|
Work on Floor(s): 001,ROF
|
| 09/03/2013 |
320855311 |
02 |
A2 |
X SIGNED OFF |
12/09/2014 |
0069933 PE |
MURRAY |
|
NOT APPLICABLE
|
|
STRUCTURAL ROOF SUPPORT FOR NEW ROOFTOP HVAC UNITS. NO CHANGE TO USE, EGRE
|
|
Work on Floor(s): ROF
|
| 09/03/2013 |
320855311 |
01 |
A2 |
X SIGNED OFF |
12/09/2014 |
0026010 RA |
ANZALONE |
|
NOT APPLICABLE
|
|
INTERIOR RENOVATION TO EXISTING BUILDING. GENERAL CONSTRUCTION AND PLUMBIN
|
|
Work on Floor(s): 001
|
| 08/01/2013 |
320591203 |
01 |
A1 |
J P/E DISAPPROVED |
09/06/2013 |
0026010 RA |
ANZALONE |
|
NOT APPLICABLE
|
|
JOB WITHDRAWN 05/07/2026 LEGALIZE THE REMOVAL OF EXISTING FREE STANDING "S
|
|
Work on Floor(s): 001,MEZ
|
| 05/23/2007 |
302338646 |
04 |
A1 |
X SIGNED OFF |
04/10/2009 |
0007878 RA |
Blaufeux |
|
NOT APPLICABLE
|
|
N/A
|
|
Work on Floor(s): MEZ
|
| 05/14/2007 |
302338646 |
03 |
A1 |
X SIGNED OFF |
04/10/2009 |
0051094 PE |
Katz |
|
NOT APPLICABLE
|
|
Alter existing sprinkler system for new heads below storage lofts
|
|
Work on Floor(s): 001
|
| 05/14/2007 |
302338646 |
02 |
A1 |
X SIGNED OFF |
04/10/2009 |
0060234 PE |
Camboura |
|
NOT APPLICABLE
|
|
Structural design of Storage Lofts
|
|
Work on Floor(s): MEZ
|
| 05/14/2007 |
302338646 |
01 |
A1 |
X SIGNED OFF |
04/10/2009 |
0007878 RA |
Blaufeux |
|
NOT APPLICABLE
|
|
Erect storage lofts; erect walls & partitions.
|
|
Work on Floor(s): MEZ
|
| 11/03/2000 |
301093714 |
01 |
A2 |
R PERMIT-ENTIRE |
12/26/2000 |
0046665 PE |
FRIEDLAN |
|
NOT APPLICABLE
|
|
JOB WITHDRAWN 03/20/2009 INSTALL PAINT SPRAY BOOTH ON 1ST FLOOR NO CHANGE
|
|
Work on Floor(s): 1
|
| 07/15/1993 |
300184119 |
05 |
A1 |
P APPROVED |
07/15/1993 |
0007878 RA |
BLAUFEUX |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): 1, MEZ,Z
|
| 05/10/1993 |
300184119 |
04 |
A1 |
P APPROVED |
05/12/1993 |
0007878 RA |
BLAUFEUX |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): 1, MEZ,Z
|
| 11/02/1992 |
300184119 |
03 |
A1 |
P APPROVED |
11/06/1992 |
0007878 RA |
BLAUFEUX |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): 1, MEZ,Z
|
| 11/02/1992 |
300184119 |
02 |
A1 |
P APPROVED |
11/06/1992 |
0007878 RA |
BLAUFEUX |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01 FOOTINGS, STRUCTURAL STEEL,AND COMPOSITE
|
|
Work on Floor(s): 1, MEZ,Z
|
| 06/15/1992 |
300184119 |
01 |
A1 |
X SIGNED OFF |
09/02/1993 |
0007878 RA |
BLAUFEUX |
|
NOT APPLICABLE
|
|
FOOTINGS, STRUCTURAL STEEL,AND COMPOSITE DECK DESIGN FOR NEW MEZZANINE
|
|
Work on Floor(s): 1, MEZ,Z
|