| FILE DATE |
JOB # |
DOC # |
JOB TYPE |
JOB STATUS |
STATUS DATE |
LIC # |
APPLICANT |
IN AUDIT |
ZONING APPROVAL |
| 01/20/2017 |
321041029 |
02 |
A2 |
P APPROVED |
02/16/2017 |
|
ISLAM |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL
|
| 01/04/2017 |
302053952 |
02 |
A3 |
P APPROVED |
01/06/2017 |
0080123 PE |
SYED- NA |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): 001
|
| 07/30/2016 |
340198100 |
03 |
A2 |
P APPROVED |
08/03/2016 |
|
DONSKOY |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,001,002,003,004,ROF
|
| 06/05/2016 |
321263431 |
02 |
A2 |
P APPROVED |
06/17/2016 |
|
SOSKIN |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,001,002,003,004,ROF
|
| 10/29/2015 |
321263431 |
01 |
A2 |
X SIGNED OFF |
09/21/2016 |
0083057 PE |
SOSKIN |
|
NOT APPLICABLE
|
|
FILING FOR INSTALLATION OF AUTOMATIC WET SPRINKLER SYSTEM THROUGHOUT THE
|
|
Work on Floor(s): CEL,001,002,003,004,ROF
|
| 10/01/2015 |
340198100 |
02 |
A2 |
P APPROVED |
11/18/2015 |
|
DONSKOY |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,001,002,003,004,ROF
|
| 12/03/2014 |
321041029 |
01 |
A2 |
X SIGNED OFF |
02/23/2017 |
0070997 PE |
ISLAM |
|
NOT APPLICABLE
|
|
FILING FOR EARTHWORK TO LOWER THE CELLAR LEVEL WITH UNDERPINNING, IN CONJU
|
|
Work on Floor(s): CEL
|
| 10/23/2014 |
340198100 |
01 |
A2 |
X SIGNED OFF |
02/27/2017 |
0027477 RA |
DONSKOY |
|
NOT APPLICABLE
|
|
PROPOSED ALTERATION TO EXIST 4 STORIES RESIDENTIAL BUILDING, INCLUDING REM
|
|
Work on Floor(s): CEL,001,002,003,004,ROF
|
| 08/13/2013 |
340078720 |
01 |
A3 |
X SIGNED OFF |
06/10/2016 |
0080350 PE |
SOLTANIZ |
|
NOT APPLICABLE
|
|
INSTALLATION OF TEMPORARY HEAVY DUTY SIDEWALK SHED FOR REMEDIAL REPAIRS AS
|
|
Work on Floor(s): OSP
|
| 04/11/2013 |
340051703 |
01 |
A3 |
H P/E IN PROCESS |
04/11/2013 |
0080350 PE |
SOLTANIZ |
|
NOT APPLICABLE
|
|
JOB WITHDRAWN 04/18/2013 INSTALLATION OF TEMPORARY HEAVY DUTY SIDEWALK SHE
|
|
Work on Floor(s): OSP
|
| 09/18/2012 |
320586576 |
01 |
A3 |
P APPROVED |
09/18/2012 |
0059739 PE |
SIDDIQUE |
|
NOT APPLICABLE
|
|
JOB WITHDRAWN 01/23/2017 INSTALLATION OF SUPPORTED PIPE SCAFFOLDING AS PER
|
|
Work on Floor(s): 001,004
|
| 05/24/2011 |
320311140 |
01 |
A3 |
X SIGNED OFF |
12/22/2016 |
0016966 RA |
GALLO |
|
NOT APPLICABLE
|
|
INSTALLATION OF PIPE SCAFFOLDING AS PER PLANS. NO CHANGE IN USE, EGRESS, O
|
|
Work on Floor(s): GRD
|
| 02/10/2011 |
320269874 |
01 |
A2 |
R PERMIT-ENTIRE |
10/15/2013 |
0023094 RA |
MUGAVERO |
|
NOT APPLICABLE
|
|
JOB WITHDRAWN 03/04/2017 APPLICATION FILED TO INDICATE THE STRUCTURAL MAIN
|
|
Work on Floor(s): CEL,001,002,003,004,ROF
|
| 10/04/2010 |
302069712 |
02 |
A2 |
P APPROVED |
11/01/2010 |
0017848 RA |
COLE |
|
NOT APPLICABLE
|
|
DOC WITHDRAWN 04/18/2015 RENOVATE APTS 2R AND 4F. REPLACE FIXTURES ON EXIS
|
|
Work on Floor(s): CEL 001 thru 004
|
| 07/22/2010 |
320180950 |
01 |
A3 |
X SIGNED OFF |
07/13/2016 |
0029017 RA |
WESOLOWS |
|
NOT APPLICABLE
|
|
PROPOSED INSTALLATION PIPE SCAFFOLDING ORIGINATE OFF OF SIDEWALK SHED AT T
|
|
Work on Floor(s): 001 thru 004
|
| 07/22/2010 |
320180941 |
01 |
A3 |
X SIGNED OFF |
07/27/2016 |
0029017 RA |
WESOLOWS |
|
NOT APPLICABLE
|
|
INSTALLATION OF TEMPORARY HEAVY DUTY SIDEWALK SHED FOR REMEDIAL REPAIRS AS
|
|
Work on Floor(s): OSP
|
| 08/10/2009 |
320055097 |
01 |
A3 |
X SIGNED OFF |
01/25/2017 |
0080123 PE |
SYED-NAQ |
|
NOT APPLICABLE
|
|
PROPOSED INSTALLATION OF HEAVYDUTY SIDEWALK SHED FILED FOR REMEDIAL REPAIR
|
|
Work on Floor(s): OSP
|
| 02/08/2006 |
302069712 |
01 |
A2 |
R PERMIT-ENTIRE |
11/10/2010 |
0017848 RA |
COLE |
|
NOT APPLICABLE
|
|
JOB WITHDRAWN 04/18/2015 RENOVATE APTS 2R AND 4F. REPLACE FIXTURES ON EXIS
|
|
Work on Floor(s): CEL 001 thru 004
|
| 12/23/2005 |
302053952 |
01 |
A3 |
X SIGNED OFF |
01/31/2017 |
0080123 PE |
SYED- NA |
|
NOT APPLICABLE
|
|
INSTALLATION OF 25' SIDEWALK SHED FOR THE PURPOSE OF FACADE INSPECTION T
|
|
Work on Floor(s): 001
|