| FILE DATE |
JOB # |
DOC # |
JOB TYPE |
JOB STATUS |
STATUS DATE |
LIC # |
APPLICANT |
IN AUDIT |
ZONING APPROVAL |
| 12/11/2014 |
340214958 |
01 |
A3 |
X SIGNED OFF |
11/30/2015 |
0083278 PE |
HOQUE |
|
NOT APPLICABLE
|
|
INSTALLATION OF PIPE SCAFFOLDING AS PER PLANS. WORK SHALL COMPLY WITH 2008
|
|
Work on Floor(s): OSP
|
| 12/11/2014 |
340214930 |
01 |
A3 |
X SIGNED OFF |
11/30/2015 |
0083278 PE |
HOQUE |
|
NOT APPLICABLE
|
|
INSTALLATION OF SIDEWALK SHED AS PER PLANS. WORK SHALL COMPLY WITH 2008 BU
|
|
Work on Floor(s): OSP
|
| 09/24/2014 |
320979018 |
01 |
DM |
X SIGNED OFF |
04/28/2015 |
0074354 PE |
WANG |
|
NOT APPLICABLE
|
|
FULL DEMOLITION OF A FOUR STORY MASONRY BUILDING
|
|
Work on Floor(s): CEL,BAS 001 thru 004
|
| 11/26/2008 |
310227000 |
01 |
A3 |
X SIGNED OFF |
12/09/2010 |
0078402 PE |
BLINN |
|
NOT APPLICABLE
|
|
INSTALLATION OF HEAVY DUTY SIDEWALK SHED 50'LINER FEET BY 16'TALL DURING N
|
|
Work on Floor(s): 001
|