FILE DATE |
JOB # |
DOC # |
JOB TYPE |
JOB STATUS |
STATUS DATE |
LIC # |
APPLICANT |
IN AUDIT |
ZONING APPROVAL |
06/12/2024 |
210179705 |
13 |
NB |
P APPROVED |
10/17/2024 |
0088155 PE |
ALVAREZ |
|
AMENDED 03/13/2023
|
|
POST APPROVAL AMENDMENT FOR 02
|
|
Work on Floor(s): CEL,ROF 001 thru 019
|
03/27/2024 |
240253658 |
04 |
A2 |
P APPROVED |
04/18/2024 |
|
ALVAREZ |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): ROF,CEL 001 thru 019
|
10/02/2023 |
210179705 |
12 |
NB |
J P/E DISAPPROVED |
03/19/2024 |
|
AUFGANG |
|
AMENDED 03/13/2023
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,ROF 001 thru 019
|
09/25/2023 |
210179705 |
11 |
NB |
P APPROVED |
11/21/2023 |
0088155 PE |
ALVAREZ |
|
AMENDED 03/13/2023
|
|
POST APPROVAL AMENDMENT FOR 02
|
|
Work on Floor(s): CEL,ROF 001 thru 019
|
06/06/2023 |
210179705 |
10 |
NB |
P APPROVED |
08/22/2023 |
0088155 PE |
ALVAREZ |
|
AMENDED 03/13/2023
|
|
POST APPROVAL AMENDMENT FOR 02
|
|
Work on Floor(s): CEL,ROF 001 thru 019
|
06/05/2023 |
240253658 |
03 |
A2 |
P APPROVED |
08/16/2023 |
|
ALVAREZ |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): ROF,CEL 001 thru 019
|
05/03/2023 |
240256138 |
02 |
A3 |
P APPROVED |
01/11/2024 |
|
BROOKER |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): OSP
|
03/16/2023 |
210179705 |
09 |
NB |
P APPROVED |
09/01/2023 |
|
AUFGANG |
|
AMENDED 03/13/2023
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,ROF 001 thru 019
|
02/09/2023 |
240253658 |
02 |
A2 |
P APPROVED |
04/10/2023 |
|
ALVAREZ |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): ROF,CEL 001 thru 019
|
10/28/2022 |
210179705 |
08 |
NB |
P APPROVED |
04/26/2023 |
0088155 PE |
ALVAREZ |
|
AMENDED 03/13/2023
|
|
POST APPROVAL AMENDMENT FOR 02
|
|
Work on Floor(s): CEL,ROF 001 thru 019
|
09/02/2022 |
210179705 |
07 |
NB |
P APPROVED |
03/13/2023 |
|
AUFGANG |
|
AMENDED 03/13/2023
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,ROF 001 thru 019
|
04/20/2022 |
210179705 |
06 |
NB |
B A/P UNPAID |
08/22/2023 |
0060229 PE |
BROOKER |
|
AMENDED 03/13/2023
|
|
POST APPROVAL AMENDMENT FOR 05
|
|
Work on Floor(s): OSP
|
06/18/2021 |
240298628 |
02 |
A3 |
D A/P ENTIRE |
07/23/2021 |
|
O'CONNOR |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01 INSTALLATION OF DUAL TEMPORARY PERSONNEL/MA
|
|
Work on Floor(s): OSP
|
04/30/2021 |
220212598 |
01 |
SC |
U COMPLETED |
05/18/2021 |
0032789 RA |
AUFGANG |
|
NOT APPLICABLE
|
|
THIS IS A NO WORK APPLICATION TO SUBDIVIDE TAX LOT 73 INTO THREE (3) CONDO
|
|
Work on Floor(s): ENT
|
01/07/2021 |
240298628 |
01 |
A3 |
R PERMIT-ENTIRE |
01/22/2021 |
0084781 PE |
O'CONNOR |
|
NOT APPLICABLE
|
|
INSTALLATION OF DUAL TEMPORARY PERSONNEL/MATERIAL HOIST FOR WORKER ACCESS
|
|
Work on Floor(s): OSP
|
07/02/2019 |
240256138 |
01 |
A3 |
R PERMIT-ENTIRE |
06/16/2020 |
0060229 PE |
BROOKER |
|
NOT APPLICABLE
|
|
BUILDERS PAVEMENT PLAN FOR 179 LF OF FRONTAGE IN CONJUNCTION WITH NB JOB N
|
|
Work on Floor(s): OSP
|
07/02/2019 |
240253658 |
01 |
A2 |
X SIGNED OFF |
06/14/2024 |
0088155 PE |
ALVAREZ |
|
NOT APPLICABLE
|
|
INSTALLATION OF PERMANENT SPRINKLER-STANDPIPE SYSTEM IN CONJUNCTION WITH N
|
|
Work on Floor(s): ROF,CEL 001 thru 019
|
04/19/2019 |
210179705 |
05 |
NB |
R PERMIT-ENTIRE |
08/12/2020 |
0060229 PE |
BROOKER |
|
AMENDED 03/13/2023
|
|
TAKING RESPONSIBILITY FOR SUPPORT OF EXCAVATION WORK AT NEW BUILDING FILED
|
|
Work on Floor(s): OSP
|
04/18/2019 |
220699304 |
01 |
A2 |
D A/P ENTIRE |
04/18/2019 |
0088155 PE |
ALVAREZ |
|
NOT APPLICABLE
|
|
JOB WITHDRAWN 07/29/2024 AUTOMATIC SMOKE/HEAT/CO DETECTION AND SPRINKLER A
|
|
Work on Floor(s): ROF 001 thru 019
|
04/16/2019 |
220698608 |
01 |
A2 |
R PERMIT-ENTIRE |
08/12/2020 |
0088155 PE |
ALVAREZ |
|
NOT APPLICABLE
|
|
INSTALLATION OF TEMPORARY STANDPIPE SYSTEM IN CONJUNCTION WITH NB JOB NUMB
|
|
Work on Floor(s): ROF 001 thru 019
|
03/28/2019 |
210179705 |
04 |
NB |
R PERMIT-ENTIRE |
08/12/2020 |
0060229 PE |
BROOKER |
|
AMENDED 03/13/2023
|
|
TAKING RESPONSIBILITY FOR FOUNDATION/EARTHWORK AT NEW BUILDING FILED UNDER
|
|
Work on Floor(s): CEL
|
03/28/2019 |
210179705 |
03 |
NB |
R PERMIT-ENTIRE |
08/12/2020 |
0060229 PE |
BROOKER |
|
AMENDED 03/13/2023
|
|
TAKING RESPONSIBILITY FOR STRUCTURAL WORK DONE AT NEW BUILDING FILED UNDER
|
|
Work on Floor(s): CEL,ROF 001 thru 019
|
03/20/2019 |
210179705 |
02 |
NB |
R PERMIT-ENTIRE |
08/18/2020 |
0088155 PE |
ALVAREZ |
|
AMENDED 03/13/2023
|
|
MECHANICAL AND PLUMBING WORK-TYPE UNDER NB JOB NUMBER 210179705.
|
|
Work on Floor(s): CEL,ROF 001 thru 019
|
02/21/2019 |
210179705 |
01 |
NB |
R PERMIT-ENTIRE |
07/17/2023 |
0032789 RA |
AUFGANG |
|
AMENDED 03/13/2023
|
|
NEW NINETEEN (19) STORY MIXED USE DWELLING.
|
|
Work on Floor(s): CEL,ROF 001 thru 019
|