| FILE DATE |
JOB # |
DOC # |
JOB TYPE |
JOB STATUS |
STATUS DATE |
LIC # |
APPLICANT |
IN AUDIT |
ZONING APPROVAL |
| 10/28/2022 |
210177841 |
11 |
NB |
P APPROVED |
11/01/2022 |
0068464 PE |
RINI |
|
GRANTED 06/18/2019
|
|
POST APPROVAL AMENDMENT FOR 03
|
|
Work on Floor(s): CEL,ROF 001 thru 011
|
| 08/04/2022 |
210177841 |
10 |
NB |
P APPROVED |
09/30/2022 |
0068464 PE |
RINI |
|
GRANTED 06/18/2019
|
|
POST APPROVAL AMENDMENT FOR 03
|
|
Work on Floor(s): CEL,ROF 001 thru 011
|
| 11/24/2021 |
240248941 |
03 |
A2 |
P APPROVED |
01/18/2022 |
|
RINI |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,ROF 001 thru 010
|
| 09/28/2021 |
240289549 |
02 |
A2 |
P APPROVED |
10/28/2021 |
|
STOUT |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): ROF
|
| 09/16/2021 |
220693471 |
02 |
A2 |
P APPROVED |
01/10/2022 |
|
RINI |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,ROF 001 thru 010
|
| 08/19/2021 |
210177841 |
09 |
NB |
P APPROVED |
08/26/2021 |
0068464 PE |
RINI |
|
GRANTED 06/18/2019
|
|
POST APPROVAL AMENDMENT FOR 03
|
|
Work on Floor(s): CEL,ROF 001 thru 011
|
| 07/27/2021 |
210177841 |
08 |
NB |
P APPROVED |
08/02/2021 |
|
YAKAS |
|
GRANTED 06/18/2019
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,ROF 001 thru 010
|
| 06/24/2021 |
240248941 |
02 |
A2 |
P APPROVED |
07/19/2021 |
|
RINI |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,ROF 001 thru 010
|
| 05/13/2021 |
240253872 |
02 |
A3 |
P APPROVED |
05/18/2021 |
|
MENZER |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): OSP
|
| 04/16/2021 |
220212561 |
01 |
SC |
U COMPLETED |
06/18/2021 |
0018047 RA |
YAKAS |
|
NOT APPLICABLE
|
|
THIS IS A NO WORK APPLICATION TO SUBDIVIDE TAX LOT 27 INTO THREE (3) CONDO
|
|
Work on Floor(s): ENT
|
| 03/22/2021 |
210177841 |
07 |
NB |
P APPROVED |
04/06/2021 |
|
YAKAS |
|
GRANTED 06/18/2019
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,ROF 001 thru 010
|
| 12/23/2020 |
240298851 |
01 |
A2 |
J P/E DISAPPROVED |
12/30/2020 |
0033977 RA |
LAU |
|
NOT APPLICABLE
|
|
JOB WITHDRAWN 01/10/2021 PROPOSE GENERAL CONSTRUCTION WORKS FOR A NEW SUPE
|
|
Work on Floor(s): CEL,001
|
| 10/09/2020 |
240289549 |
01 |
A2 |
X SIGNED OFF |
11/17/2021 |
0021633 RA |
STOUT |
|
NOT APPLICABLE
|
|
INSTALLATION OF SOLAR PANELS ON EXISTING ROOF STRUCTURE. NO CHANGE IN EGRE
|
|
Work on Floor(s): ROF
|
| 07/22/2020 |
220695629 |
02 |
A2 |
P APPROVED |
09/17/2021 |
0028321 PE |
WHELAN |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,ROF 001 thru 010
|
| 03/12/2020 |
240270522 |
01 |
A3 |
X SIGNED OFF |
06/16/2021 |
0019131 RA |
DOOLING |
|
NOT APPLICABLE
|
|
INSTALLATION OF TEMPORARY ROOF PROTECTION AS PER PLANS. NO CHANGE IN USE,
|
|
Work on Floor(s): OSP,ROF
|
| 02/13/2020 |
240268697 |
02 |
A3 |
P APPROVED |
02/13/2020 |
|
DOOLING |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01 INSTALLATION OF TEMPORARY PERSONNEL MATERIA
|
|
Work on Floor(s): OSP
|
| 02/12/2020 |
240268928 |
01 |
A3 |
X SIGNED OFF |
06/16/2021 |
0019131 RA |
DOOLING |
|
NOT APPLICABLE
|
|
INSTALLATION OF TEMPORARY PLYWOOD ENCLOSURE AS PER PLANS. NO CHANGE IN USE
|
|
Work on Floor(s): OSP
|
| 02/11/2020 |
240268900 |
01 |
A3 |
X SIGNED OFF |
06/16/2021 |
0019131 RA |
DOOLING |
|
NOT APPLICABLE
|
|
INSTALLATION OF NEEDLE BEAM AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCU
|
|
Work on Floor(s): OSP,003
|
| 02/10/2020 |
240268697 |
01 |
A3 |
X SIGNED OFF |
03/01/2021 |
0019131 RA |
DOOLING |
|
NOT APPLICABLE
|
|
INSTALLATION OF TEMPORARY PERSONNEL MATERIAL HOIST AS PER PLANS. HOIST AND
|
|
Work on Floor(s): OSP
|
| 07/26/2019 |
210177841 |
06 |
NB |
P APPROVED |
08/05/2019 |
|
YAKAS |
|
GRANTED 06/18/2019
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,ROF 001 thru 010
|
| 05/14/2019 |
240253970 |
01 |
A2 |
X SIGNED OFF |
08/03/2021 |
0068464 PE |
RINI |
|
NOT APPLICABLE
|
|
INSTALLATION OF TEMPORARY AIR PRESSURIZED ALARM SYSTEM FOR DRY STANDPIPE S
|
|
Work on Floor(s): CEL,ROF 001 thru 010
|
| 05/14/2019 |
240253872 |
01 |
A3 |
X SIGNED OFF |
08/09/2022 |
0081064 PE |
MENZER |
|
NOT APPLICABLE
|
|
BUILDERS PAVEMENT PLAN IN CONJUNCTION WITH NB# 210177841
|
|
Work on Floor(s): OSP
|
| 03/25/2019 |
210177841 |
05 |
NB |
X SIGNED OFF |
12/28/2022 |
0068605 PE |
PILLORI |
|
GRANTED 06/18/2019
|
|
SOE WORK IN CONJUNCTION WITH NB
|
|
Work on Floor(s): CEL,OSP,001
|
| 03/25/2019 |
210177841 |
04 |
NB |
X SIGNED OFF |
12/28/2022 |
0060272 PE |
DE NARDI |
|
GRANTED 06/18/2019
|
|
STRUCTURAL SUPERSTRUCTURE WORK AS SHOWN ON PLANS
|
|
Work on Floor(s): CEL,ROF 001 thru 011
|
| 03/21/2019 |
220693471 |
01 |
A2 |
X SIGNED OFF |
08/01/2022 |
0068464 PE |
RINI |
|
NOT APPLICABLE
|
|
INSTALLATION OF AUTOMATIC SMOKE/HEAT DETECTION AND SPRINKLER ALARM.
|
|
Work on Floor(s): CEL,ROF 001 thru 010
|
| 03/21/2019 |
220695629 |
01 |
A2 |
X SIGNED OFF |
12/13/2022 |
0028321 PE |
WHELAN |
|
NOT APPLICABLE
|
|
INSTALLATION OF REPEATER AUXILIARY RADIO COMMUNICATION SYSTEM WITH PASSIVE
|
|
Work on Floor(s): CEL,ROF 001 thru 010
|
| 02/22/2019 |
210177841 |
03 |
NB |
X SIGNED OFF |
12/28/2022 |
0068464 PE |
RINI |
|
GRANTED 06/18/2019
|
|
MECHANICAL AND PLUMBING WORK FOR NB AS SHOWN ON PLANS
|
|
Work on Floor(s): CEL,ROF 001 thru 011
|
| 02/21/2019 |
210177841 |
02 |
NB |
X SIGNED OFF |
12/28/2022 |
0060272 PE |
DE NARDI |
|
GRANTED 06/18/2019
|
|
FOUNDATION WORK AS SHOWN ON PLANS
|
|
Work on Floor(s): CEL,OSP,001
|
| 03/28/2019 |
240248941 |
01 |
A2 |
X SIGNED OFF |
07/20/2022 |
0068464 PE |
RINI |
|
NOT APPLICABLE
|
|
INSTALL NEW SPRINKLER AND STANDPIPE SYSTEM FOR NB# 210177841 AS SHOWN ON P
|
|
Work on Floor(s): CEL,ROF 001 thru 010
|
| 02/15/2019 |
210177841 |
01 |
NB |
X SIGNED OFF |
12/28/2022 |
0018047 RA |
YAKAS |
|
GRANTED 06/18/2019
|
|
ERECT AN 10 STORY NEW BUILDING
|
|
Work on Floor(s): CEL,ROF 001 thru 010
|
| 11/08/2017 |
240205363 |
01 |
A2 |
D A/P ENTIRE |
11/08/2017 |
0071681 PE |
TUCCI |
|
NOT APPLICABLE
|
|
JOB WITHDRAWN 11/08/2017 INSTALLATION OF TEMPORARY AIR PRESSURIZED ALARM S
|
|
Work on Floor(s): CEL,ROF 001 thru 011
|