| FILE DATE |
JOB # |
DOC # |
JOB TYPE |
JOB STATUS |
STATUS DATE |
LIC # |
APPLICANT |
IN AUDIT |
ZONING APPROVAL |
| 11/14/2016 |
201066489 |
22 |
NB |
P APPROVED |
11/22/2016 |
|
MEHTA |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,ROF 001 thru 009
|
| 11/09/2016 |
201066489 |
21 |
NB |
P APPROVED |
11/22/2016 |
|
MEHTA |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,ROF 001 thru 009
|
| 11/07/2016 |
201066489 |
20 |
NB |
P APPROVED |
11/10/2016 |
|
MEHTA |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,ROF 001 thru 009
|
| 11/01/2016 |
201066489 |
19 |
NB |
G PAA FEE DUE |
11/01/2016 |
|
MEHTA |
|
NOT APPLICABLE
|
|
DOC WITHDRAWN 11/03/2016
|
|
Work on Floor(s): CEL,ROF 001 thru 009
|
| 10/04/2016 |
201066489 |
18 |
NB |
G PAA FEE DUE |
10/04/2016 |
|
MEHTA |
|
NOT APPLICABLE
|
|
DOC WITHDRAWN 10/26/2016
|
|
Work on Floor(s): CEL,ROF 001 thru 009
|
| 02/20/2015 |
201066489 |
17 |
NB |
P APPROVED |
03/03/2015 |
0038991 PE |
JOSELOW |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 05
|
|
Work on Floor(s): CEL,ROF 001 thru 009
|
| 11/11/2014 |
201066489 |
16 |
NB |
P APPROVED |
11/24/2014 |
0038991 PE |
JOSELOW |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 05
|
|
Work on Floor(s): CEL,ROF 001 thru 009
|
| 11/11/2014 |
201066489 |
15 |
NB |
P APPROVED |
11/26/2014 |
0024554 RA |
MEHTA |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01 NEW BUILDING, AND MERGING OF LOTS 40 & 41
|
|
Work on Floor(s): CEL,ROF 001 thru 009
|
| 05/27/2014 |
201066489 |
14 |
NB |
P APPROVED |
06/10/2014 |
0038991 PE |
JOSELOW |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 05
|
|
Work on Floor(s): CEL,ROF 001 thru 009
|
| 11/14/2013 |
201066489 |
13 |
NB |
P APPROVED |
11/20/2013 |
0060005 PE |
WEXLER |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 02
|
|
Work on Floor(s): CEL,ROF 001 thru 009
|
| 11/13/2013 |
201066489 |
12 |
NB |
P APPROVED |
11/20/2013 |
0038991 PE |
JOSELOW |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 05
|
|
Work on Floor(s): CEL,ROF 001 thru 009
|
| 11/13/2013 |
201066489 |
11 |
NB |
P APPROVED |
11/18/2013 |
|
MEHTA |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01 NEW BUILDING AND MERGING LOTS 40 AND 41
|
|
Work on Floor(s): CEL,ROF 001 thru 009
|
| 11/01/2013 |
201066489 |
10 |
NB |
P APPROVED |
11/20/2013 |
0038991 PE |
JOSELOW |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 04
|
|
Work on Floor(s): CEL,ROF 001 thru 009
|
| 11/01/2013 |
201066489 |
09 |
NB |
P APPROVED |
11/12/2013 |
0038991 PE |
JOSELOW |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 03
|
|
Work on Floor(s): CEL,ROF 001 thru 009
|
| 07/18/2013 |
220325501 |
01 |
A3 |
X SIGNED OFF |
08/04/2016 |
0024554 RA |
MEHTA |
|
NOT APPLICABLE
|
|
FIRE PROTECTION PLAN FILED IN CONJUNCTION TO NB APPLICATION 201066489. NO
|
|
Work on Floor(s): CEL,ROF 001 thru 009
|
| 07/12/2013 |
220322078 |
01 |
A2 |
X SIGNED OFF |
09/08/2016 |
0028318 RA |
KAMBANIS |
|
NOT APPLICABLE
|
|
WORK UNDER THIS APPLICATION INCLUDES NEW TEMPORARY STANDPIPE
|
|
Work on Floor(s): CEL
|
| 11/19/2012 |
220230774 |
01 |
A3 |
X SIGNED OFF |
07/06/2015 |
0083278 PE |
HOQUE |
|
NOT APPLICABLE
|
|
INSTALLATION OF SCAFFOLD AS PER DRAWINGS. SCAFFOLD SHALL COMPLY WITH CHAPT
|
|
Work on Floor(s): OSP
|
| 12/07/2011 |
220159922 |
01 |
A3 |
X SIGNED OFF |
04/25/2017 |
0024554 RA |
MEHTA |
|
NOT APPLICABLE
|
|
BPP FILING FOR NB#201066489, TOTAL FRONTAGE IS 45'
|
|
Work on Floor(s): OSP
|
| 11/22/2011 |
220156827 |
01 |
A3 |
X SIGNED OFF |
07/26/2016 |
0070976 PE |
LANGER |
|
NOT APPLICABLE
|
|
THIS APPLICATION IS FILED TO DO SHORING IN CONJUNCTION W/ DOB JOB NO. #201
|
|
Work on Floor(s): CEL 001 thru 009
|
| 11/15/2011 |
220149514 |
01 |
A2 |
X SIGNED OFF |
02/24/2017 |
0038991 PE |
JOSELOW |
|
NOT APPLICABLE
|
|
AUTOMATIC SMOKE/HEAT DETECTION/SPRINKLER ALARM SYSTEM.
|
|
Work on Floor(s): 001 thru 009
|
| 10/13/2011 |
201066489 |
08 |
NB |
P APPROVED |
11/09/2011 |
0038991 PE |
JOSELOW |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 03
|
|
Work on Floor(s): CEL,ROF 001 thru 011
|
| 10/13/2011 |
201066489 |
07 |
NB |
P APPROVED |
11/09/2011 |
0038991 PE |
JOSELOW |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 05
|
|
Work on Floor(s): CEL,ROF 001 thru 010
|
| 02/12/2009 |
201066489 |
06 |
NB |
P APPROVED |
03/28/2011 |
0024554 RA |
MEHTA |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL 001 thru 010
|
| 01/25/2007 |
201103769 |
01 |
A3 |
J P/E DISAPPROVED |
01/26/2007 |
0024554 RA |
Mehta |
|
NOT APPLICABLE
|
|
JOB WITHDRAWN 01/10/2012 BPP FILING FOR NB# 201066489, TOTAL FRONTAGE IS 4
|
|
Work on Floor(s): OSP
|
| 10/18/2006 |
201066489 |
04 |
NB |
X SIGNED OFF |
07/20/2017 |
0038991 PE |
JOSELOW |
|
NOT APPLICABLE
|
|
Work on Floor(s): CEL,ROF 001 thru 009
|
| 10/18/2006 |
201066489 |
05 |
NB |
X SIGNED OFF |
07/20/2017 |
0079477 PE |
MCSHANE |
|
NOT APPLICABLE
|
|
Work on Floor(s): CEL,ROF 001 thru 009
|
| 10/18/2006 |
201066489 |
03 |
NB |
X SIGNED OFF |
07/20/2017 |
0038991 PE |
JOSELOW |
|
NOT APPLICABLE
|
|
Work on Floor(s): CEL,ROF 001 thru 009
|
| 10/18/2006 |
201066489 |
02 |
NB |
X SIGNED OFF |
07/20/2017 |
0060005 PE |
WEXLER |
|
NOT APPLICABLE
|
|
Work on Floor(s): CEL,ROF 001 thru 009
|
| 07/21/2006 |
201066489 |
01 |
NB |
X SIGNED OFF |
07/20/2017 |
0024554 RA |
MEHTA |
|
NOT APPLICABLE
|
|
NEW BUILDING, AND MERGING OF LOTS 40 & 41
|
|
Work on Floor(s): CEL,ROF 001 thru 009
|
| 11/10/2005 |
201007926 |
01 |
A2 |
J P/E DISAPPROVED |
12/16/2005 |
0068130 PE |
CHIFFERT |
|
NOT APPLICABLE
|
|
JOB WITHDRAWN 06/22/2015 INSTALL SPRINKLER SYSTEM FOR THE ENTIRE BUILDING.
|
|
Work on Floor(s): CEL 001 thru 006
|
| 09/19/2005 |
200997519 |
01 |
A2 |
R PERMIT-ENTIRE |
09/20/2005 |
0068130 PE |
CHIFFERT |
|
NOT APPLICABLE
|
|
JOB WITHDRAWN 07/02/2015 EXCAVATION AND ROCK REMOVAL IN CONJUNCTION WITH N
|
|
Work on Floor(s): 001
|
| 01/26/2005 |
200930047 |
01 |
NB |
J P/E DISAPPROVED |
05/03/2006 |
0024554 RA |
MEHTA |
|
NOT APPLICABLE
|
|
JOB WITHDRAWN 07/14/2006
|
|
Work on Floor(s): CEL 001 thru 011
|