| FILE DATE |
JOB # |
DOC # |
JOB TYPE |
JOB STATUS |
STATUS DATE |
LIC # |
APPLICANT |
IN AUDIT |
ZONING APPROVAL |
|
220720806 |
01 |
A1 |
A PRE-FILED |
11/26/2019 |
0057210 PE |
WAPNER |
|
NOT APPLICABLE
|
|
JOB WITHDRAWN 03/09/2023 FILING APPLICATION TO ACCOMMODATE NYC HUMAN RESOU
|
|
Work on Floor(s): 001 thru 004
|
|
220651792 |
01 |
A1 |
A PRE-FILED |
05/25/2018 |
0032813 PE |
PARMET |
|
NOT APPLICABLE
|
|
JOB WITHDRAWN 11/08/2019 FILING TO OBTAIN A NEW CERTIFICATE OF OCCUPANCY F
|
|
Work on Floor(s): BAS,ROF 001 thru 004
|
| 04/20/2016 |
220150716 |
03 |
A2 |
P APPROVED |
05/10/2016 |
|
BARROS |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,PEN 001 thru 004
|
| 06/16/2015 |
220150716 |
02 |
A2 |
P APPROVED |
07/22/2015 |
|
BARROS |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,PEN 001 thru 004
|
| 04/15/2015 |
220150967 |
02 |
NB |
P APPROVED |
07/14/2015 |
|
BARROS |
|
GRANTED 06/19/2013
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL 001 thru 004
|
| 06/16/2014 |
220150725 |
02 |
A2 |
P APPROVED |
10/23/2014 |
|
BARROS |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL 001 thru 004
|
| 05/17/2013 |
220150725 |
01 |
A2 |
X SIGNED OFF |
07/07/2016 |
0090206 PE |
BARROS |
|
NOT APPLICABLE
|
|
PROPOSE TO FILE FOR A SMOKE/SPRINKLER ALARM SYSTEM WITH CENTRAL OFFICE
|
|
Work on Floor(s): CEL 001 thru 004
|
| 05/17/2013 |
220150716 |
01 |
A2 |
X SIGNED OFF |
07/07/2016 |
0090206 PE |
BARROS |
|
NOT APPLICABLE
|
|
PLUMBING AND SPRINKLER PLANS TO BE FILED IN CONJUNCTION WITH NEW BUILDING
|
|
Work on Floor(s): CEL,PEN 001 thru 004
|
| 05/14/2013 |
220210607 |
01 |
A3 |
X SIGNED OFF |
06/08/2016 |
0090206 PE |
BARROS |
|
NOT APPLICABLE
|
|
IN CONJUNCTION WITH NEW BUILDING APPLICATION. 70FT ON THE EAST SIDE OF MON
|
|
Work on Floor(s): OSP
|
| 02/01/2013 |
220150967 |
01 |
NB |
X SIGNED OFF |
07/07/2016 |
0090206 PE |
BARROS |
|
GRANTED 06/19/2013
|
|
ERECTION OF NEW RESIDENTIAL 4 STORY BUILDING.
|
|
Work on Floor(s): CEL 001 thru 004
|