| FILE DATE |
JOB # |
DOC # |
JOB TYPE |
JOB STATUS |
STATUS DATE |
LIC # |
APPLICANT |
IN AUDIT |
ZONING APPROVAL |
| 05/21/2019 |
240254540 |
01 |
A2 |
R PERMIT-ENTIRE |
06/04/2019 |
0095511 PE |
JOHNSON |
|
NOT APPLICABLE
|
|
FACADE REPAIRS AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR
|
|
Work on Floor(s): FAC
|
| 09/19/2003 |
200568938 |
10 |
NB |
P APPROVED |
01/20/2004 |
0046664 PE |
Franzese |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL 001 thru 008
|
| 11/19/2002 |
200724234 |
04 |
A2 |
G PAA FEE DUE |
11/19/2002 |
0025546 RA |
Ernst |
|
NOT APPLICABLE
|
|
DOC WITHDRAWN 12/12/2002
|
|
Work on Floor(s): 001 001 thru 001
|
| 11/08/2002 |
200761069 |
01 |
A3 |
X SIGNED OFF |
04/14/2003 |
0046664 PE |
FRANZESE |
|
NOT APPLICABLE
|
| 10/11/2002 |
200568938 |
09 |
NB |
P APPROVED |
10/24/2002 |
0046664 PE |
Franzese |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL 001 thru 008
|
| 07/09/2002 |
200724234 |
02 |
A2 |
P APPROVED |
12/12/2002 |
0025546 RA |
Ernst |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): 001 001 thru 001
|
| 04/19/2002 |
200724234 |
01 |
A2 |
X SIGNED OFF |
04/03/2003 |
0025546 RA |
Ernst |
|
NOT APPLICABLE
|
|
Physical Therapy Clinic-Install gypsum board partitions, split type air
|
|
Work on Floor(s): 001 001 thru 001
|
| 02/22/2002 |
200568938 |
08 |
NB |
P APPROVED |
02/25/2002 |
0046664 PE |
Franzese |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL 001 thru 008
|
| 12/21/2001 |
200684214 |
02 |
A2 |
P APPROVED |
12/27/2001 |
0038991 PE |
Joselow |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL 001 thru 008
|
| 12/11/2001 |
200568938 |
06 |
NB |
P APPROVED |
12/11/2001 |
0038991 PE |
JOSELOW |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 04
|
|
Work on Floor(s): CEL 001 thru 008
|
| 08/09/2001 |
200684214 |
01 |
A2 |
X SIGNED OFF |
09/18/2002 |
0038991 PE |
Joselow |
|
NOT APPLICABLE
|
|
Installation of Sprinkler and Standpipe systems in conjunction with New
|
|
Work on Floor(s): CEL 001 thru 008
|
| 10/18/2000 |
200642849 |
01 |
A3 |
X SIGNED OFF |
05/08/2002 |
OT |
Nagan |
|
NOT APPLICABLE
|
|
Erect sidewalk shed in conjunction with new building application #20056893
|
|
Work on Floor(s): OSP
|
| 04/04/2000 |
200616878 |
01 |
A3 |
X SIGNED OFF |
04/02/2003 |
0046664 PE |
FRANSEZE |
|
NOT APPLICABLE
|
|
BPP 323 LF
|
|
Work on Floor(s): CEL 001 thru 008
|
| 03/17/2000 |
200568938 |
04 |
NB |
X SIGNED OFF |
01/29/2004 |
0038991 PE |
JOSELOW |
|
NOT APPLICABLE
|
|
FILING FOR SP, PL, SD, MECH, BOILER AND FB
|
|
Work on Floor(s): CEL 001 thru 008
|
| 11/03/1999 |
200568938 |
03 |
NB |
X SIGNED OFF |
01/29/2004 |
0046161 PE |
KAPLAN |
|
NOT APPLICABLE
|
|
FOUNDATION DWGS FOR FOUNDATION APPROVAL
|
|
Work on Floor(s): 001 thru 008
|
| 10/20/1999 |
200594883 |
01 |
A3 |
X SIGNED OFF |
05/08/2002 |
OT |
Nagan |
|
NOT APPLICABLE
|
|
Erect temporary construction fence around job site in conjunction with New
|
|
Work on Floor(s): OSP
|
| 10/13/1999 |
200568938 |
02 |
NB |
X SIGNED OFF |
01/29/2004 |
0046161 PE |
KAPLAN |
|
NOT APPLICABLE
|
|
STRUCTURAL DWGS FOR ABOVE PREMISES
|
|
Work on Floor(s): 00C 001 thru 008
|
| 08/26/1999 |
200587908 |
01 |
A2 |
X SIGNED OFF |
01/12/2000 |
0021706 RA |
McIntosh |
|
NOT APPLICABLE
|
|
Clear and grade site level with adjoining sidewalk. No change to egress,
|
|
Work on Floor(s): OSP
|
| 03/01/1999 |
200568938 |
01 |
NB |
X SIGNED OFF |
01/29/2004 |
0046664 PE |
Franzese |
|
NOT APPLICABLE
|
|
Work on Floor(s): CEL 001 thru 008
|
|
200724234 |
03 |
A2 |
A PRE-FILED |
11/19/2002 |
0025546 RA |
Ernst |
|
NOT APPLICABLE
|
|
DOC WITHDRAWN 11/19/2002
|
|
Work on Floor(s): 001 001 thru 001
|
|
200568938 |
07 |
NB |
A PRE-FILED |
02/22/2002 |
0038991 PE |
JOSELOW |
|
NOT APPLICABLE
|
|
DOC WITHDRAWN 03/26/2002
|
|
Work on Floor(s): CEL 001 thru 008
|
|
200568938 |
05 |
NB |
A PRE-FILED |
12/10/2001 |
0038991 PE |
JOSELOW |
|
NOT APPLICABLE
|
|
DOC WITHDRAWN 12/11/2001
|
|
Work on Floor(s): CEL 001 thru 008
|