| FILE DATE |
JOB # |
DOC # |
JOB TYPE |
JOB STATUS |
STATUS DATE |
LIC # |
APPLICANT |
IN AUDIT |
ZONING APPROVAL |
| 09/21/2016 |
201193537 |
02 |
A2 |
P APPROVED |
09/21/2016 |
0069395 PE |
ISLAM |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01 FILING HEREWITH ENERGY ANALYSIS ASSOCAITED
|
|
Work on Floor(s): 001 thru 002
|
| 12/29/2014 |
201193537 |
01 |
A2 |
X SIGNED OFF |
03/28/2017 |
0069395 PE |
ISLAM |
|
NOT APPLICABLE
|
|
FILING HEREWITH ENERGY ANALYSIS ASSOCAITED WITH THE ELECTRICAL LIGTHING
|
|
Work on Floor(s): 001 thru 002
|
| 10/31/2014 |
240078474 |
01 |
A3 |
X SIGNED OFF |
01/12/2015 |
0084178 PE |
ALI |
|
NOT APPLICABLE
|
|
REPLACE EXISTING ROOF MEMBRANE AS PER PLAN. NO CHANGE IN USE EGRESS OR
|
|
Work on Floor(s): ROF
|
| 10/23/2014 |
240077368 |
01 |
A3 |
H P/E IN PROCESS |
10/23/2014 |
0084178 PE |
ALI |
|
NOT APPLICABLE
|
|
JOB WITHDRAWN 10/23/2014 REPLACE EXISTING ROOF MEMBRANE
|
|
Work on Floor(s): ALL 001 thru 008
|
| 03/17/2010 |
220052225 |
01 |
A3 |
X SIGNED OFF |
07/11/2014 |
0080123 PE |
SYED-NAQ |
|
NOT APPLICABLE
|
|
PROPOSED INSTALLATION OF HEAVYDUTY SIDEWALK SHED FILED FOR REMIDIAL REPAIR
|
|
Work on Floor(s): OSP
|
| 01/20/2010 |
220045706 |
01 |
A2 |
R PERMIT-ENTIRE |
03/07/2014 |
0050579 PE |
RUDIKOFF |
|
NOT APPLICABLE
|
|
REPLACE (2) GAS BOILERS (NYC BOILER NO. MD70093-01, 02) WITH (3) GAS BOILE
|
|
Work on Floor(s): CEL
|
| 01/21/2004 |
200824965 |
01 |
A2 |
X SIGNED OFF |
09/20/2004 |
0050579 PE |
RUDIKOFF |
|
NOT APPLICABLE
|
|
INSTALL ONE 5 TON INDIRECT FIRED GAS HEATING UNIT AND DUCTWORK PER PLANS.
|
|
Work on Floor(s): CEL,ROF
|
| 01/19/2001 |
200655610 |
01 |
A2 |
X SIGNED OFF |
05/21/2002 |
0022158 RA |
ELISSIO |
|
NOT APPLICABLE
|
|
MASONRY FACADE REPAIRS- REMOVE EXISTING PARAPET AND REPLACE WITH CHAIN FE
|
|
Work on Floor(s): ROF
|
| 11/08/2000 |
200609449 |
01 |
A3 |
R PERMIT-ENTIRE |
12/12/2000 |
0065430 PE |
HICKEY |
|
NOT APPLICABLE
|
|
INSTALL HEAVY DUTY SIDEWALK 120' DURING FACADE REPAIR. NO CHANGE TO USE
|
|
Work on Floor(s): GRD
|
| 04/23/1996 |
200368681 |
01 |
A2 |
X SIGNED OFF |
09/30/1996 |
0052592 PE |
KAUFMAN |
|
NOT APPLICABLE
|
|
INSTALLATION OF NEW FIRE SUPPRESSIONN SY SYSTEM. IN CONJUNCTION WITH
|
|
Work on Floor(s): 2
|
| 01/10/1995 |
200232612 |
07 |
NB |
P APPROVED |
04/25/1995 |
0010627 RA |
NAPIER |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,ROF 1 thru 8
|
| 12/06/1993 |
200232612 |
06 |
NB |
X SIGNED OFF |
09/30/1996 |
0060946 PE |
SPRING |
|
NOT APPLICABLE
|
|
FIRE ALARM SYSTEM
|
|
Work on Floor(s): CEL,ROF 1 thru 8
|
| 12/03/1993 |
200276192 |
01 |
A3 |
X SIGNED OFF |
09/07/1995 |
0060597 PE |
SHAPIRO |
|
NOT APPLICABLE
|
|
ERECT MATERIAL HOIST IN CONJUNCTION WITH APPL. 200232612 N.B. NO CHANGE
|
|
Work on Floor(s): 8
|
| 05/11/1993 |
200232612 |
05 |
NB |
X SIGNED OFF |
09/30/1996 |
0010627 RA |
SPRING |
|
NOT APPLICABLE
|
|
INSTALLATION OF SPRINKLER AND STANDPIPE SYSTEM.
|
|
Work on Floor(s): CEL,ROF 1 thru 8
|
| 05/11/1993 |
200232612 |
04 |
NB |
X SIGNED OFF |
09/30/1996 |
0060946 PE |
SPRING |
|
NOT APPLICABLE
|
|
INSTALLATION OF MECHANICAL AND PLUMBING SYSTEMS. INSTALLATION OF BOILER.
|
|
Work on Floor(s): CEL,ROF 1 thru 8
|
| 05/11/1993 |
200232612 |
03 |
NB |
X SIGNED OFF |
09/30/1996 |
0060005 PE |
WEXLER |
|
NOT APPLICABLE
|
|
STRUCTURAL WORK.
|
|
Work on Floor(s): CEL,ROF 1 thru 8
|
| 04/02/1993 |
200232612 |
02 |
NB |
X SIGNED OFF |
09/30/1996 |
0010627 RA |
NAPIER |
|
NOT APPLICABLE
|
|
FOUNDATION & FOOTING CONSTRUCTION.
|
|
Work on Floor(s): CEL,ROF 1 thru 8
|
| 03/29/1993 |
200252895 |
01 |
A2 |
X SIGNED OFF |
01/24/1996 |
0010627 RA |
NAPIER |
|
NOT APPLICABLE
|
|
SITE CLEARING & CONSTRUCTION FENCE. - FILED IN CONJ. W/200232612.
|
|
Work on Floor(s): 1
|
| 12/28/1992 |
200232612 |
01 |
NB |
X SIGNED OFF |
09/30/1996 |
0010627 RA |
NAPIER |
|
NOT APPLICABLE
|
|
Work on Floor(s): CEL,ROF 1 thru 8
|