| FILE DATE |
JOB # |
DOC # |
JOB TYPE |
JOB STATUS |
STATUS DATE |
LIC # |
APPLICANT |
IN AUDIT |
ZONING APPROVAL |
| 04/19/2022 |
240318296 |
01 |
A3 |
X SIGNED OFF |
08/06/2025 |
0094480 PE |
GEORGOPO |
|
NOT APPLICABLE
|
|
BPP APPLICATION FILED HEREWITH IN CONJUNCTION WITH NEW BUILDING JOB #X0070
|
|
Work on Floor(s): OSP
|
| 10/27/2020 |
220733473 |
02 |
DM |
X SIGNED OFF |
09/14/2021 |
0074354 PE |
WANG |
|
NOT APPLICABLE
|
|
INSTALLATION OF CHUTE TO LOWER DEBRIS FROM FLOOR TO FLOOR
|
|
Work on Floor(s): BSM 001 thru 003
|
| 10/14/2020 |
220733473 |
01 |
DM |
X SIGNED OFF |
09/14/2021 |
0074354 PE |
WANG |
|
NOT APPLICABLE
|
|
FULL DEMOLITION OF THREE STORY STRUCTURE, USING HAND HELD EQUIPMENT AND
|
|
Work on Floor(s): BSM 001 thru 003
|