| FILE DATE |
JOB # |
DOC # |
JOB TYPE |
JOB STATUS |
STATUS DATE |
LIC # |
APPLICANT |
IN AUDIT |
ZONING APPROVAL |
| 06/24/2025 |
210181033 |
05 |
A1 |
P APPROVED |
09/12/2025 |
|
GOUDAS |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): 001 thru 002
|
| 06/12/2024 |
210181033 |
04 |
A1 |
P APPROVED |
03/20/2025 |
|
GOUDAS |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): 001 thru 002
|
| 02/25/2022 |
240290010 |
02 |
A3 |
P APPROVED |
04/27/2022 |
|
GOUDAS |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): OSP
|
| 02/25/2022 |
210181033 |
03 |
A1 |
P APPROVED |
04/05/2022 |
|
GOUDAS |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): 001 thru 002
|
| 03/02/2021 |
210181033 |
02 |
A1 |
P APPROVED |
06/09/2021 |
0041807 RA |
GOUDAS |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): 001 thru 002
|
| 12/21/2020 |
240290010 |
01 |
A3 |
X SIGNED OFF |
11/01/2024 |
0041807 RA |
GOUDAS |
|
NOT APPLICABLE
|
|
BPP - BUILDERS PAVING PLAN IN CONJUNCTION WITH ALT I 210181033.
|
|
Work on Floor(s): OSP
|
| 03/24/2020 |
210181033 |
01 |
A1 |
R PERMIT-ENTIRE |
01/06/2021 |
0041807 RA |
GOUDAS |
|
NOT APPLICABLE
|
|
CONVERT EXISTING TWO STORY FACTORY BUILDING TO TRANSIENT HOTEL, UG 5A.
|
|
Work on Floor(s): 001 thru 002
|
| 10/21/2016 |
200247483 |
02 |
A2 |
P APPROVED |
10/21/2016 |
0014928 RA |
DUPUY |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): 1
|
| 09/08/2003 |
200805842 |
01 |
A2 |
R PERMIT-ENTIRE |
09/18/2003 |
0050579 PE |
RUDIKOFF |
|
NOT APPLICABLE
|
|
INSTALL GAS HIGH PRESSURE BOILER IN NEW BOILER ROOM ENCLOSURE. NO CHANGE
|
|
Work on Floor(s): 001,ROF
|
| 08/25/1994 |
200247483 |
01 |
A2 |
X SIGNED OFF |
04/24/2018 |
0014928 RA |
DUPUY |
|
NOT APPLICABLE
|
|
REPLACE EXIST' BOILER WITH NEW BOILER &- BURNER. RECONNECT EXIST' GAS
|
|
Work on Floor(s): 1
|