Premises: 1511 RHINELANDER AVENUE BRONX BIN: 2047109    Block: 4222    Lot: 5

To start overview at new date, select Month:   Day:   Year:  

         

FILE DATE JOB # DOC # JOB TYPE JOB STATUS STATUS DATE LIC # APPLICANT IN AUDIT ZONING APPROVAL
06/27/2018 220148178 02 PA P APPROVED 07/12/2018 HEUBERGE NOT APPLICABLE
 POST APPROVAL AMENDMENT FOR 01
 Work on Floor(s): BAS

06/27/2018 220148169 04 PA P APPROVED 07/30/2018 HEUBERGE NOT APPLICABLE
 POST APPROVAL AMENDMENT FOR 01
 Work on Floor(s): CEL

06/04/2015 220460702 03 A2 X SIGNED OFF 04/14/2016 0066684 PE GOOD NOT APPLICABLE
 INTERIOR TO INCLUDE SELECTIVE DEMOLITION OF EXISTING SLAB AND CONSTRUCTION
 Work on Floor(s): CEL

05/29/2015 220460702 02 A2 X SIGNED OFF 04/14/2016 0065040 PE RODKIN NOT APPLICABLE
 PLUMBING WORK AS SHOWN ON PLANS FILED HERE WITH
 Work on Floor(s): CEL

05/29/2015 220460702 01 A2 X SIGNED OFF 04/14/2016 0020310 RA DOBAN NOT APPLICABLE
 INTERIOR RENOVATION TO INCLUDE DEMOLITION OF EXISTING AND CONSTRUCTION OF
 Work on Floor(s): CEL

02/24/2015 220419866 02 A2 P APPROVED 02/24/2015 RODKIN NOT APPLICABLE
 POST APPROVAL AMENDMENT FOR 01
 Work on Floor(s): ROF

12/10/2014 220419866 01 A2 X SIGNED OFF 04/22/2015 0065040 PE RODKIN NOT APPLICABLE
 NO WORK APPLICATION FILED IN ORDER TO OBTAIN EUP CARDS FOR UNITS PREVIOUSL
 Work on Floor(s): ROF

04/14/2014 220092094 16 A1 P APPROVED 06/03/2014 HEUBERGE AMENDED 04/29/2011
 POST APPROVAL AMENDMENT FOR 01
 Work on Floor(s): CEL,BAS 001 thru 003

04/01/2014 220100502 03 A3 P APPROVED 04/15/2014 GIUDICI NOT APPLICABLE
 POST APPROVAL AMENDMENT FOR 01
 Work on Floor(s): OSP

11/20/2013 220100502 02 A3 P APPROVED 02/10/2014 GIUDICI NOT APPLICABLE
 POST APPROVAL AMENDMENT FOR 01
 Work on Floor(s): OSP

11/20/2013 220161759 05 A2 P APPROVED 01/09/2014 RODKIN NOT APPLICABLE
 POST APPROVAL AMENDMENT FOR 01
 Work on Floor(s): 002,003,ROF

10/18/2013 220245866 02 A2 P APPROVED 12/06/2013 RODKIN NOT APPLICABLE
 POST APPROVAL AMENDMENT FOR 01
 Work on Floor(s): BAS

07/10/2013 220324423 01 A2 X SIGNED OFF 10/31/2013 0043167 PE VACHRIS NOT APPLICABLE
 FILING SUPPORT OF EXCAVATION FILING FOR THE REMOVAL OF TANK AND CONTAMINAT
 Work on Floor(s): OSP

07/08/2013 220161759 04 A2 P APPROVED 10/17/2013 0065040 PE RODKIN NOT APPLICABLE
 POST APPROVAL AMENDMENT FOR 01
 Work on Floor(s): 002,003,ROF

06/19/2013 220104438 10 A2 P APPROVED 06/20/2013 0065040 PE RODKIN NOT APPLICABLE
 POST APPROVAL AMENDMENT FOR 01 MECHANICAL & PLUMBING AND BOILER FILED IN C
 Work on Floor(s): CEL,BAS,ROF 001 thru 002

06/14/2013 220307825 01 A2 X SIGNED OFF 01/23/2014 0065040 PE RODKIN NOT APPLICABLE
 FUEL STORAGE FILED IN CONJUNCTION WITH GENERATOR FILED UNDER SEPARATE
 Work on Floor(s): OSP

06/04/2013 220161759 03 A2 P APPROVED 06/17/2013 0065040 PE RODKIN NOT APPLICABLE
 POST APPROVAL AMENDMENT FOR 01
 Work on Floor(s): 002,003,ROF

05/29/2013 220148169 03 PA P APPROVED 07/01/2013 HEUBERGE NOT APPLICABLE
 POST APPROVAL AMENDMENT FOR 01
 Work on Floor(s): CEL

05/17/2013 220092094 15 A1 P APPROVED 06/06/2013 HEUBERGE AMENDED 04/29/2011
 POST APPROVAL AMENDMENT FOR 01
 Work on Floor(s): CEL,BAS 001 thru 003

04/05/2013 220092094 14 A1 P APPROVED 04/08/2013 HEUBERGE AMENDED 04/29/2011
 POST APPROVAL AMENDMENT FOR 01 SEE SECTION 24.
 Work on Floor(s): CEL,BAS 001 thru 003

03/26/2013 220259789 01 A2 X SIGNED OFF 12/17/2013 0025147 PE HEUBERGE NOT APPLICABLE
 INTERIOR DEMOLITION WORK IN BASEMENT OF EXISTING BUILDING AS SHOWN ON PLAN
 Work on Floor(s): BAS

01/03/2013 220246516 01 A2 X SIGNED OFF 02/20/2014 0065040 PE RODKIN NOT APPLICABLE
 MECHANICAL AND PLUMBING WORK FILED AT CELLAR AND BASEMENT IN CONJUNCTION W
 Work on Floor(s): CEL,BAS

12/27/2012 220092094 13 A1 P APPROVED 02/13/2013 0025147 RA HEUBERGE AMENDED 04/29/2011
 POST APPROVAL AMENDMENT FOR 01 SEE SECTION 24.
 Work on Floor(s): CEL,BAS 001 thru 003

12/27/2012 220245875 01 A2 X SIGNED OFF 03/06/2014 0082402 PE HIGGINS NOT APPLICABLE
 SPRINKLER MODIFICATIONS AT BASEMENT LEVEL IN CONJUNCTION WITH CHANGE OF C.
 Work on Floor(s): BAS

12/27/2012 220245866 01 A2 X SIGNED OFF 02/24/2014 0065040 PE RODKIN NOT APPLICABLE
 ADDITIONS/MODIFICATIONS TO EXISTING SYSTEM
 Work on Floor(s): BAS

11/29/2012 220092094 12 A1 P APPROVED 12/11/2012 0025147 RA HEUBERGE AMENDED 04/29/2011
 POST APPROVAL AMENDMENT FOR 01
 Work on Floor(s): CEL,BAS 001 thru 003

10/19/2012 220092094 11 A1 P APPROVED 11/13/2012 0067018 PE TORTOREL AMENDED 04/29/2011
 POST APPROVAL AMENDMENT FOR 01
 Work on Floor(s): CEL,BAS 001 thru 003

10/10/2012 220104438 09 A2 P APPROVED 10/11/2012 RODKIN NOT APPLICABLE
 POST APPROVAL AMENDMENT FOR 01
 Work on Floor(s): CEL,BAS,ROF 001 thru 002

09/28/2012 220092094 10 A1 G PAA FEE DUE 09/28/2012 0067018 PE TORTOREL AMENDED 04/29/2011
 DOC WITHDRAWN 10/12/2012
 Work on Floor(s): CEL,BAS,ROF 001 thru 003

09/15/2012 220104438 08 A2 P APPROVED 09/24/2012 RODKIN NOT APPLICABLE
 POST APPROVAL AMENDMENT FOR 01
 Work on Floor(s): CEL,BAS,ROF 001 thru 002

09/14/2012 220161759 02 A2 P APPROVED 09/27/2012 RODKIN NOT APPLICABLE
 POST APPROVAL AMENDMENT FOR 01
 Work on Floor(s): 002,003,ROF

08/30/2012 220148169 02 PA P APPROVED 08/31/2012 HEUBERGE NOT APPLICABLE
 POST APPROVAL AMENDMENT FOR 01
 Work on Floor(s): CEL

08/30/2012 220092094 09 A1 P APPROVED 09/07/2012 HEUBERGE AMENDED 04/29/2011
 POST APPROVAL AMENDMENT FOR 01
 Work on Floor(s): CEL,BAS 001 thru 003

08/14/2012 220104438 07 A2 P APPROVED 08/16/2012 RODKIN NOT APPLICABLE
 POST APPROVAL AMENDMENT FOR 01
 Work on Floor(s): CEL,BAS,ROF 001 thru 002

08/01/2012 220104438 06 A2 P APPROVED 08/14/2012 RODKIN NOT APPLICABLE
 POST APPROVAL AMENDMENT FOR 01
 Work on Floor(s): CEL,BAS,ROF 001 thru 002

07/16/2012 220197588 01 A2 P APPROVED 07/16/2012 0059739 PE SIDDIQUE NOT APPLICABLE
 JOB WITHDRAWN 07/24/2012 TO FILE APPLICATION FOR PARTIAL DEMOLITION OF ROO
 Work on Floor(s): ROO

07/11/2012 220160796 02 A2 P APPROVED 08/16/2012 0065040 PE RODKIN NOT APPLICABLE
 POST APPROVAL AMENDMENT FOR 01 SEE SECTION 24
 Work on Floor(s): CEL,002,003,ROF

06/26/2012 220092094 08 A1 P APPROVED 07/03/2012 HEUBERGE AMENDED 04/29/2011
 POST APPROVAL AMENDMENT FOR 01
 Work on Floor(s): CEL,BAS 001 thru 003

06/20/2012 220104438 05 A2 P APPROVED 06/25/2012 RODKIN NOT APPLICABLE
 POST APPROVAL AMENDMENT FOR 01
 Work on Floor(s): CEL,BAS,ROF 001 thru 002

05/15/2012 220202180 01 A3 X SIGNED OFF 08/27/2012 0072827 PE PITERA NOT APPLICABLE
 INSTALLATION OF SCAFFOLD AS PER DRAWINGS. SCAFFOLD SHALL COMPLY WITH CHAPT
 Work on Floor(s): OSP