| FILE DATE |
JOB # |
DOC # |
JOB TYPE |
JOB STATUS |
STATUS DATE |
LIC # |
APPLICANT |
IN AUDIT |
ZONING APPROVAL |
| 04/16/2025 |
220633223 |
07 |
A1 |
P APPROVED |
04/21/2025 |
|
BAKSA |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,ROF 001 thru 007
|
| 06/08/2022 |
220633223 |
06 |
A1 |
P APPROVED |
05/11/2023 |
|
BAKSA |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,ROF 001 thru 007
|
| 04/06/2022 |
220633223 |
05 |
A1 |
P APPROVED |
04/06/2022 |
|
BAKSA |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,ROF 001 thru 007
|
| 03/17/2022 |
220633223 |
04 |
A1 |
P APPROVED |
03/24/2022 |
|
BAKSA |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,ROF 001 thru 007
|
| 02/23/2022 |
220633223 |
03 |
A1 |
P APPROVED |
02/24/2022 |
|
BAKSA |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,ROF 001 thru 007
|
| 07/02/2021 |
220633223 |
02 |
A1 |
P APPROVED |
07/16/2021 |
|
BAKSA |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,ROF 001 thru 007
|
| 05/07/2021 |
240295658 |
03 |
A2 |
P APPROVED |
05/12/2021 |
|
RABKIN |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL
|
| 02/19/2021 |
240295658 |
02 |
A2 |
P APPROVED |
03/28/2021 |
0072225 PE |
RABKIN |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL
|
| 12/04/2020 |
240295658 |
01 |
A2 |
X SIGNED OFF |
05/11/2023 |
0072225 PE |
RABKIN |
|
NOT APPLICABLE
|
|
SUPPORT OF EXCAVATION IN CONJUNCTION WITH ALT-1 #220633223 AND DOB NOW
|
|
Work on Floor(s): CEL
|
| 12/03/2020 |
240295239 |
01 |
A2 |
D A/P ENTIRE |
12/03/2020 |
0088621 PE |
AUYEUNG |
|
NOT APPLICABLE
|
|
JOB WITHDRAWN 12/09/2020 SUPPORT OF EXCAVATION IN CONJUNCTION WITH ALT-1 #
|
|
Work on Floor(s): CEL
|
| 11/06/2020 |
220512728 |
02 |
A2 |
P APPROVED |
12/10/2020 |
|
BAKSA |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01 REMOVAL WORK AT CELLAR, 1ST-7TH FLOOR. NO C
|
|
Work on Floor(s): CEL 001 thru 007
|
| 05/20/2020 |
220633223 |
01 |
A1 |
R PERMIT-ENTIRE |
04/09/2021 |
0016325 RA |
BAKSA |
|
NOT APPLICABLE
|
|
THIS APPLICATION IS FOR A USE CHANGE TO PHILANTHROPIC INSTITUTION WITH SLE
|
|
Work on Floor(s): CEL,ROF 001 thru 007
|
| 02/18/2020 |
220512728 |
01 |
A2 |
X SIGNED OFF |
10/04/2022 |
0016325 RA |
BAKSA |
|
NOT APPLICABLE
|
|
REMOVAL WORK AT CELLAR, 1ST-7TH FLOOR. NO CHANGE TO USE, EGRESS OR OCCUPAN
|
|
Work on Floor(s): CEL 001 thru 007
|
| 09/20/2016 |
240155531 |
01 |
A2 |
X SIGNED OFF |
12/16/2016 |
0026031 RA |
LENAHAN |
|
NOT APPLICABLE
|
|
EXTERIOR FACADE REPAIR TO COMPLY WITH LL11 ITEMS. BRICK REPLACEMENT, POINT
|
|
Work on Floor(s): 001 thru 007
|
| 09/05/2016 |
240155522 |
01 |
A2 |
H P/E IN PROCESS |
09/05/2016 |
0026031 RA |
LENAHAN |
|
NOT APPLICABLE
|
|
JOB WITHDRAWN 09/05/2016 EXTERIOR FACADE REPAIR TO COMPLY WITH LL11 ITEMS.
|
|
Work on Floor(s): 001 thru 007
|
| 02/04/2016 |
220515226 |
01 |
A3 |
R PERMIT-ENTIRE |
05/18/2017 |
0078603 PE |
CHASSE |
|
NOT APPLICABLE
|
|
REPLACEMENT OF TELECOMMUNICATION ANTENNAS ON ROOF. REPLACEMENT OF RRH UNIT
|
|
Work on Floor(s): ROF
|
| 04/22/2015 |
220452748 |
01 |
A3 |
X SIGNED OFF |
08/31/2020 |
0075700 PE |
BOHLINGE |
|
NOT APPLICABLE
|
|
MODIFICATION TO EXISTING TELECOMMUNICATIONS SITE. INSTALLATION OF
|
|
Work on Floor(s): ROF
|
| 02/04/2014 |
220353524 |
01 |
A3 |
X SIGNED OFF |
05/21/2015 |
0078603 PE |
CHASSE |
|
NOT APPLICABLE
|
|
REPLACEMENT OF ANTENNAS ON THE ROOF. INSTALLATION OF ANTENNA COMPONENTS ON
|
|
Work on Floor(s): ROF,6TH
|
| 12/13/2012 |
220238268 |
01 |
A2 |
X SIGNED OFF |
04/19/2013 |
0019529 RA |
GALEA |
|
NOT APPLICABLE
|
|
FACADE MAINTENANCE
|
|
Work on Floor(s): 001 thru 006
|
| 09/13/2012 |
220229018 |
01 |
A3 |
X SIGNED OFF |
06/06/2013 |
0082770 PE |
BAILEY |
|
NOT APPLICABLE
|
|
PROPOSED INSTALLATION OF SIDEWALK SHED AS PER PLANS. NO CHANGE IN USE, EGR
|
|
Work on Floor(s): OSP
|
| 08/31/2007 |
210002049 |
01 |
A2 |
X SIGNED OFF |
05/16/2008 |
0057411 PE |
ANTONUCC |
|
NOT APPLICABLE
|
|
PROPOSED FACADE REPAIRS AS INDICATEDON PLANS AND APPLICATIONS. THERE
|
|
Work on Floor(s): 001 thru 006
|
| 07/05/2007 |
210003315 |
01 |
A3 |
R PERMIT-ENTIRE |
07/06/2007 |
0020419 RA |
Hulme |
|
NOT APPLICABLE
|
|
JOB WITHDRAWN 03/28/2023 INSTALL HEAVY DUTY SIDEWALK BRIDGE 50 FT LONG AT
|
|
Work on Floor(s): 001
|
| 05/17/2006 |
201053643 |
01 |
A2 |
X SIGNED OFF |
02/02/2007 |
0071429 PE |
GUALTIER |
|
NOT APPLICABLE
|
|
INSTALLING A GAS FIRED GENERATORON THEROOF, RELATED PLUMBING ON ROOF
|
|
Work on Floor(s): 001
|
| 08/09/2005 |
200989626 |
01 |
A3 |
X SIGNED OFF |
12/01/2023 |
0071249 PE |
GUALTIER |
|
NOT APPLICABLE
|
|
INSTALLING TELECOMM. ANTENNAS ON ROOFIN CONFORMANCE WITH TPPN#5/98
|
|
Work on Floor(s): ROF
|
| 04/05/2005 |
200942212 |
01 |
A2 |
X SIGNED OFF |
10/18/2005 |
0057146 PE |
ROBBEN |
|
NOT APPLICABLE
|
|
INSTALLING TELECOMMUNICATIONS CABINETS WITH RELATED DUNNAGE AND
|
|
Work on Floor(s): ROF
|
| 01/27/1993 |
200235815 |
01 |
A2 |
J P/E DISAPPROVED |
02/04/1993 |
0634651 PE |
JOHNSON |
|
NOT APPLICABLE
|
|
JOB WITHDRAWN 08/22/2022 INSTALL HALON SYSTEM ON PART OF 6 FLOOR- NO CHANG
|
|
Work on Floor(s): 6
|
| 12/03/1991 |
200169593 |
02 |
A2 |
P APPROVED |
12/13/1991 |
0061023 PE |
BEATY |
|
NOT APPLICABLE
|
|
MECHANICAL VENTILATION CHANGES ON PART OF 6TH FLOOR TO ACCOMMODATE EQUI
|
|
Work on Floor(s): 6, ROF
|
| 12/03/1991 |
200169593 |
01 |
A2 |
X SIGNED OFF |
07/14/1992 |
0050650 PE |
PARRELLO |
|
NOT APPLICABLE
|
|
PARTITION, CHANGES ON PART OF THE 6TH FL OOR TO ACCOMMODATE EQUIPMENT RM
|
|
Work on Floor(s): 6, ROF
|