| FILE DATE |
JOB # |
DOC # |
JOB TYPE |
JOB STATUS |
STATUS DATE |
LIC # |
APPLICANT |
IN AUDIT |
ZONING APPROVAL |
| 06/19/2019 |
240253373 |
01 |
A2 |
X SIGNED OFF |
11/01/2021 |
0095511 PE |
JOHNSON |
|
NOT APPLICABLE
|
|
FACADE REPAIRS AS PER PLANS FILED HEREWITH. NO CHANGE IN USE, EGRESS OR
|
|
Work on Floor(s): FAC
|
| 06/04/2007 |
201129260 |
01 |
A3 |
R PERMIT-ENTIRE |
08/15/2007 |
0075376 PE |
SCHERER |
|
NOT APPLICABLE
|
|
INSTALLING A TELECOMMUNITIONS SHELTERWITH HVAC, RELATED DUNNAGE &
|
|
Work on Floor(s): ROF,BAS
|
| 04/28/1995 |
200232408 |
05 |
A1 |
X SIGNED OFF |
04/28/1995 |
0019542 RA |
GROSS |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,1, 2, 3, 4, 5
|
| 02/06/1995 |
200232408 |
04 |
A1 |
X SIGNED OFF |
04/28/1995 |
0019542 RA |
GROSS |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,1, 2, 3, 4, 5
|
| 10/17/1994 |
200293949 |
01 |
A2 |
X SIGNED OFF |
01/11/2017 |
0047135 PE |
GERMAIN |
|
NOT APPLICABLE
|
|
REPL. 1 NEW COMBINATION GAS/OIL BOILER/B BURNER. REPL 1 NEW 3000 GALLOM
|
|
Work on Floor(s): BAS
|
| 01/11/1994 |
200232408 |
03 |
A1 |
X SIGNED OFF |
04/28/1995 |
0019542 RA |
GROSS |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01 GUT REHABILITATION OF EXISTING 5 STORY BUIL
|
|
Work on Floor(s): CEL,1, 2, 3, 4, 5
|
| 12/24/1992 |
200232408 |
02 |
A1 |
X SIGNED OFF |
04/28/1995 |
0058601 PE |
ASHKENAZ |
|
NOT APPLICABLE
|
|
GUT REHABILITATION OF EXISTING 5 STORY BUILDING
|
|
Work on Floor(s): CEL 1 thru 5
|
| 12/24/1992 |
200232408 |
01 |
A1 |
X SIGNED OFF |
04/28/1995 |
0019542 RA |
GROSS |
|
NOT APPLICABLE
|
|
GUT REHABILITATION OF EXISTING 5 STORY BUILDING. IN THE CELLAR THE EXI
|
|
Work on Floor(s): CEL,1, 2, 3, 4, 5
|