| FILE DATE |
JOB # |
DOC # |
JOB TYPE |
JOB STATUS |
STATUS DATE |
LIC # |
APPLICANT |
IN AUDIT |
ZONING APPROVAL |
| 02/10/2025 |
201102840 |
07 |
A1 |
P APPROVED |
06/24/2025 |
|
INFANTE |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL 001 thru 011
|
| 01/05/2024 |
201102840 |
06 |
A1 |
P APPROVED |
09/23/2024 |
0029013 RA |
INFANTE |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01 VERTICAL ENLARGEMENT OF 2 STORIES TO THIS E
|
|
Work on Floor(s): CEL 001 thru 011
|
| 04/04/2023 |
220742105 |
01 |
SI |
U COMPLETED |
04/07/2023 |
0015020 RA |
PANETTIE |
|
NOT APPLICABLE
|
|
EXISTING LOT 62 WITH IMPROVED PROPERTY FILING TWO SEPARATE TAX LOTS 61,62
|
|
Work on Floor(s): OSP
|
| 07/10/2020 |
220523404 |
04 |
A2 |
P APPROVED |
08/13/2020 |
0096214 PE |
SHUVO |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): OSP
|
| 04/03/2019 |
220523404 |
03 |
A2 |
P APPROVED |
04/03/2019 |
|
NACAMULI |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): OSP
|
| 04/02/2019 |
220523404 |
02 |
A2 |
P APPROVED |
04/02/2019 |
|
NACAMULI |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): OSP
|
| 03/29/2019 |
220012830 |
02 |
A3 |
P APPROVED |
04/03/2019 |
|
SARACCO |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): OSP
|
| 03/29/2019 |
201102840 |
05 |
A1 |
P APPROVED |
05/06/2019 |
|
SARACCO |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,BAS 001 thru 012
|
| 03/28/2016 |
220523404 |
01 |
A2 |
R PERMIT-ENTIRE |
05/18/2020 |
0096214 PE |
SHUVO |
|
NOT APPLICABLE
|
|
SUPPORT OF EXCAVATION IN CONJUNCTION WITH ALT-1 APPLICATION 201102840. NO
|
|
Work on Floor(s): OSP
|
| 01/07/2015 |
220226100 |
04 |
A2 |
P APPROVED |
01/07/2015 |
|
LEE |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,001,006
|
| 08/22/2014 |
240070016 |
01 |
A2 |
X SIGNED OFF |
05/19/2015 |
0088892 PE |
MESZAROS |
|
NOT APPLICABLE
|
|
INSTALLATION OF NEW CHIMNEY AND HYDRONIC PIPING IN BUILDING.
|
|
Work on Floor(s): CEL
|
| 04/17/2014 |
240049513 |
01 |
A2 |
X SIGNED OFF |
10/01/2015 |
0066182 PE |
PACIFICO |
|
NOT APPLICABLE
|
|
INSTALLATION OF SOLAR ENERGY SYSTEM
|
|
Work on Floor(s): ROF
|
| 06/05/2013 |
220129821 |
04 |
A2 |
P APPROVED |
07/11/2013 |
|
LEE |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL 001 thru 006
|
| 01/31/2013 |
220129821 |
03 |
A2 |
P APPROVED |
02/25/2013 |
|
LEE |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL 001 thru 006
|
| 01/31/2013 |
220226100 |
03 |
A2 |
P APPROVED |
02/25/2013 |
|
LEE |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,001,006
|
| 10/09/2012 |
220226100 |
02 |
A2 |
P APPROVED |
10/10/2012 |
|
LEE |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,001,006
|
| 09/28/2012 |
220129821 |
02 |
A2 |
P APPROVED |
09/28/2012 |
|
LEE |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL 001 thru 006
|
| 08/07/2012 |
220226100 |
01 |
A2 |
X SIGNED OFF |
04/24/2015 |
0029274 RA |
LEE |
|
NOT APPLICABLE
|
|
WATER LINES AND RADIATORS IN CONJUNCTION WITH BOILER APPLICATION 220129821
|
|
Work on Floor(s): CEL,001,006
|
| 10/25/2011 |
201102840 |
04 |
A1 |
P APPROVED |
09/15/2014 |
0018356 RA |
SARACCO |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,BAS 001 thru 012
|
| 07/19/2011 |
220129821 |
01 |
A2 |
X SIGNED OFF |
05/14/2015 |
0029274 RA |
LEE |
|
NOT APPLICABLE
|
|
REPLACEMENT OF EXISTING BOILER WITH 2 NEW GAS FIRED HOT WATER BOILER. NO C
|
|
Work on Floor(s): CEL 001 thru 006
|
| 03/25/2009 |
220012830 |
01 |
A3 |
X SIGNED OFF |
01/12/2021 |
0018356 RA |
SARACCO |
|
NOT APPLICABLE
|
|
HEREWITH FILING FOR A TEMPORARY CONSTRUCTION FENCE TO BE FILED IN CONJUNTI
|
|
Work on Floor(s): OSP
|
| 11/12/2008 |
210078011 |
01 |
A2 |
P APPROVED |
11/26/2008 |
0018356 RA |
SARACCO |
|
NOT APPLICABLE
|
|
FILING FOR ADDITIONAL SPRINKLER HEADS IN CONJUNCTION WITH ALT 1 JOB #20110
|
|
Work on Floor(s): CEL 001 thru 007
|
| 10/14/2008 |
210073105 |
01 |
A3 |
R PERMIT-ENTIRE |
10/14/2008 |
0018356 RA |
SARACCO |
|
NOT APPLICABLE
|
|
HEREWITH FILING FOR A BUILDER PAVEMENT PLAN SHOWING 130.92 LINEAR FEET ON
|
|
Work on Floor(s): OSP
|
| 05/22/2008 |
210051263 |
01 |
A2 |
X SIGNED OFF |
08/28/2008 |
0029274 RA |
LEE |
|
NOT APPLICABLE
|
|
INSTALLATION OF 49 GAS METERS IN CELLAR METER ROOM OFF EXISTING 2" GAS MAI
|
|
Work on Floor(s): CEL 001 thru 006
|
| 04/02/2008 |
201102840 |
03 |
A1 |
R PERMIT-ENTIRE |
02/02/2010 |
0018356 RA |
SARACCO |
|
NOT APPLICABLE
|
|
HEREWITH FILING FOR PLUMBING AND MECHANICAL WORK AS INDICATED ON THE ATTAC
|
|
Work on Floor(s): C, R 1 thru 11
|
| 04/02/2008 |
201102840 |
02 |
A1 |
R PERMIT-ENTIRE |
04/28/2009 |
0045040 PE |
SHIH |
|
NOT APPLICABLE
|
|
HEREWITH FILING FOR STRUCTURAL WORK AS INDICATED ON THE ATTACHED PLANS.
|
|
Work on Floor(s): C, R 1 thru 11
|
| 01/25/2007 |
201102840 |
01 |
A1 |
R PERMIT-ENTIRE |
09/15/2025 |
0029013 RA |
INFANTE |
|
NOT APPLICABLE
|
|
VERTICAL ENLARGEMENT OF 2 STORIES TO THIS EXISTING 6 STORY BUILDING FOR TO
|
|
Work on Floor(s): CEL 001 thru 011
|
| 06/28/2006 |
201059781 |
01 |
NB |
J P/E DISAPPROVED |
07/05/2006 |
0018356 RA |
SARACCO |
|
NOT APPLICABLE
|
|
JOB WITHDRAWN 09/07/2007
|
|
Work on Floor(s): 001
|