| FILE DATE |
JOB # |
DOC # |
JOB TYPE |
JOB STATUS |
STATUS DATE |
LIC # |
APPLICANT |
IN AUDIT |
ZONING APPROVAL |
| 11/17/2021 |
220649378 |
04 |
A2 |
P APPROVED |
11/29/2021 |
|
WONG |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 02
|
|
Work on Floor(s): CEL 001 thru 005
|
| 07/19/2018 |
220649378 |
03 |
A2 |
P APPROVED |
07/19/2018 |
0091835 PE |
WONG |
|
NOT APPLICABLE
|
|
DOC WITHDRAWN 10/18/2021 WITHDRAWN AS NO BOILER WORK DONE UNDER THIS DOCUM
|
|
Work on Floor(s): CEL 001 thru 005
|
| 05/18/2018 |
220649378 |
02 |
A2 |
X SIGNED OFF |
08/04/2022 |
0091835 PE |
WONG |
|
NOT APPLICABLE
|
|
DIRECT REPLACEMENT OF KITCHEN AND BATHROOM FIXTURES ON EXISTING ROUGHING.
|
|
Work on Floor(s): CEL 001 thru 005
|
| 05/18/2018 |
220649378 |
01 |
A2 |
X SIGNED OFF |
08/04/2022 |
0032789 RA |
AUFGANG |
|
NOT APPLICABLE
|
|
MODERATE REHABILITATION OF KITCHENS & BATHROOMS, COMMON AREAS, ROOF, AND
|
|
Work on Floor(s): CEL,ROF 001 thru 005
|
| 01/29/2015 |
240077135 |
02 |
A2 |
D A/P ENTIRE |
01/29/2015 |
|
MESZAROS |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL
|
| 10/21/2014 |
240077135 |
01 |
A2 |
P APPROVED |
10/22/2014 |
0088892 PE |
MESZAROS |
|
NOT APPLICABLE
|
|
NATURAL GAS CONVERSION AND INSTALLATION OF NEW BOILER/BURNER. #2 OIL TO RE
|
|
Work on Floor(s): CEL
|
| 04/15/2014 |
240054935 |
01 |
A3 |
R PERMIT-ENTIRE |
07/17/2014 |
0084178 PE |
ALI |
Y |
NOT APPLICABLE
|
|
INTERIOR RENOVATION 1ST,2ND,3RD,4TH AND 5TH FLOOR BATHROOM & KITCHEN FLOOR
|
|
Work on Floor(s): 001,002,003,004,005
|
| 04/01/2014 |
240053295 |
01 |
A3 |
R PERMIT-ENTIRE |
07/18/2014 |
0084178 PE |
ALI |
Y |
NOT APPLICABLE
|
|
FRONT ELEVATION PARAPET WALL REBUILD,WINDOW SILL REPLACE,GRINDING AND POIN
|
|
Work on Floor(s): OSP,ROF
|
| 03/30/2014 |
240052955 |
01 |
A3 |
R PERMIT-ENTIRE |
04/01/2014 |
0066791 PE |
PARIHAR |
|
NOT APPLICABLE
|
|
PROPOSED INSTALLATION OF HEAVY DUTY SIDEWALK SHED FILED FOR REMEDIAL REPAI
|
|
Work on Floor(s): OSP
|