| FILE DATE |
JOB # |
DOC # |
JOB TYPE |
JOB STATUS |
STATUS DATE |
LIC # |
APPLICANT |
IN AUDIT |
ZONING APPROVAL |
| 12/08/2005 |
200903095 |
01 |
A2 |
X SIGNED OFF |
05/22/2006 |
0061356 PE |
MOORE |
|
NOT APPLICABLE
|
|
MINOR PARTITION AND PLUMBING WORK ON FIRST FLOOR. COMBINE TWO APARTMENTS (
|
|
Work on Floor(s): 001
|
| 11/09/2005 |
200801908 |
04 |
A1 |
P APPROVED |
11/21/2005 |
0613561 PE |
Moore Jr |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL 001 thru 005
|
| 01/28/2005 |
200927177 |
02 |
A2 |
X SIGNED OFF |
08/19/2005 |
0613561 PE |
Moore Jr |
|
NOT APPLICABLE
|
|
Fuel Burning & Storage in conjunction with boiler installation as shown on
|
|
Work on Floor(s): CEL
|
| 01/06/2005 |
200927177 |
01 |
A2 |
X SIGNED OFF |
08/19/2005 |
0613561 PE |
Moore Jr |
|
NOT APPLICABLE
|
|
Installation of boiler. Boiler and Plumbing connection for boiler work wa
|
|
Work on Floor(s): CEL
|
| 11/12/2004 |
200801908 |
03 |
A1 |
P APPROVED |
12/10/2004 |
0613561 PE |
Moore Jr |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL 001 thru 005
|
| 04/30/2004 |
200853594 |
01 |
A3 |
X SIGNED OFF |
06/29/2005 |
0613561 PE |
MOORE |
|
NOT APPLICABLE
|
|
Install sidewalk shed 40ft long at 1082 Southern Blvd-inconjunction with
|
|
Work on Floor(s): OSP
|
| 10/28/2003 |
200801908 |
02 |
A1 |
X SIGNED OFF |
11/29/2005 |
0613561 PE |
Moore Jr |
|
NOT APPLICABLE
|
|
Install temporary plywood construction fence no more than 3' from the prop
|
|
Work on Floor(s): 001
|
| 08/07/2003 |
200801908 |
01 |
A1 |
X SIGNED OFF |
11/29/2005 |
0613561 PE |
Moore Jr |
|
NOT APPLICABLE
|
|
Gut rehabilitation of existing five story building to include joist replac
|
|
Work on Floor(s): CEL 001 thru 005
|
| 03/10/1998 |
200502946 |
01 |
A3 |
X SIGNED OFF |
05/26/1998 |
0062079 PE |
Ferraro |
|
NOT APPLICABLE
|
|
Replace Steel stairs and exit door leading to the north yard. No changes t
|
|
Work on Floor(s): 001
|
| 03/26/1993 |
200252715 |
01 |
A3 |
R PERMIT-ENTIRE |
05/05/1993 |
0063907 PE |
MALLIARO |
|
NOT APPLICABLE
|
|
JOB WITHDRAWN 03/15/2005 INSTALL CONSTRUCTION EQUIPMENT (SIDEWALK BRIDGE)
|
|
Work on Floor(s): GRN
|
| 03/17/1993 |
200251495 |
01 |
A2 |
X SIGNED OFF |
03/07/1996 |
0015015 RA |
NICHOLSO |
|
NOT APPLICABLE
|
|
NEW WATER METER FOR BLDG. & NEW HOT AND- COLD DISTRIBUTION LINES. NEW GA
|
|
Work on Floor(s): CEL,5
|
| 03/09/1993 |
200250646 |
01 |
A3 |
X SIGNED OFF |
04/24/1995 |
0063907 PE |
MALLIARO |
|
NOT APPLICABLE
|
|
INTERIOR & EXTERIOR RECONSTRUCTION OF - EXIST' BLDG. AS PER SUBMITTED
|
|
Work on Floor(s): 1 thru 5
|
| 12/17/1992 |
200232140 |
01 |
A3 |
R PERMIT-ENTIRE |
02/08/1993 |
|
BHATTI |
|
NOT APPLICABLE
|
|
JOB WITHDRAWN 03/15/2005 ERECT SIDEWALK SHED. NO CHANGE IN USE EGRESS OR O
|
|
Work on Floor(s): 1
|
| 11/01/1989 |
200015492 |
01 |
A2 |
Q PERMIT-PARTIAL |
11/28/1989 |
0036071 PE |
WEINER |
|
NOT APPLICABLE
|
|
JOB WITHDRAWN 03/31/2005 REPLACE EXISTING BOILER & BURNER, IN- STALLATION
|
|
Work on Floor(s): CEL
|