| FILE DATE |
JOB # |
DOC # |
JOB TYPE |
JOB STATUS |
STATUS DATE |
LIC # |
APPLICANT |
IN AUDIT |
ZONING APPROVAL |
| 08/09/2011 |
220098515 |
03 |
A2 |
P APPROVED |
08/22/2011 |
|
CLEMENTS |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,ROF 001 thru 006
|
| 05/16/2011 |
220118888 |
01 |
A2 |
X SIGNED OFF |
01/18/2012 |
0087678 PE |
BAZINI |
|
NOT APPLICABLE
|
|
REPLACE BOILER AND OIL BURNER. CHANGE GRADE OF OIL FROM #4 TO #2. NO CHANG
|
|
Work on Floor(s): CEL
|
| 04/07/2011 |
220112018 |
01 |
A2 |
X SIGNED OFF |
02/02/2012 |
0027638 PE |
GRAMMAS |
|
NOT APPLICABLE
|
|
PROPOSE TO FILE FOR THE INSTALLATION OF NEW AUTOMATIC SMOKE/HEAT DETECTION
|
|
Work on Floor(s): CEL,ROF 001 thru 006
|
| 12/29/2010 |
220098515 |
01 |
A2 |
X SIGNED OFF |
02/06/2012 |
0018844 RA |
CLEMENTS |
|
NOT APPLICABLE
|
|
MODERATE REHABILITATION TO ENTIRE BUILDING WITH NEW ROOFING,REPLACEMENT OF
|
|
Work on Floor(s): CEL,ROF 001 thru 006
|
| 12/29/2010 |
220098515 |
02 |
A2 |
X SIGNED OFF |
02/06/2012 |
0018844 RA |
CLEMENTS |
|
NOT APPLICABLE
|
|
INSTALLATION OF NEW TRASH COMPACTOR UNIT AT CELLAR AS PER PLANS FILED. NO
|
|
Work on Floor(s): CEL
|
| 10/26/2010 |
210079500 |
02 |
A3 |
P APPROVED |
11/03/2010 |
0072827 PE |
PITERA |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): OSP
|
| 04/14/2010 |
220056793 |
01 |
A3 |
X SIGNED OFF |
12/30/2011 |
0072827 PE |
PITERA |
|
NOT APPLICABLE
|
|
INSTALLATION OF 213 FOOT LONG SIDEWALK SHED AS PER PLANS SUBMITTED HEREWIT
|
|
Work on Floor(s): OSP
|
| 11/19/2008 |
210079500 |
01 |
A3 |
X SIGNED OFF |
12/08/2011 |
0072827 PE |
PITERA |
|
NOT APPLICABLE
|
|
INSTALLATION OF 213 FOOT LONG LIGHT DUTY SIDEWALK SHED AS PER PLANS SUBMIT
|
|
Work on Floor(s): OSP
|