| 10/05/2020 |
220649305 |
11 |
A1 |
P APPROVED |
10/08/2020 |
|
BERGER |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,ROF 001 thru 004
|
| 11/07/2019 |
220649305 |
10 |
A1 |
P APPROVED |
11/13/2019 |
|
BERGER |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,ROF 001 thru 004
|
| 07/31/2019 |
220649305 |
09 |
A1 |
P APPROVED |
08/05/2019 |
0075954 PE |
SIMONIEL |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 04
|
|
Work on Floor(s): CEL,ROF 001 thru 004
|
| 05/22/2019 |
220649305 |
08 |
A1 |
P APPROVED |
05/24/2019 |
0075954 PE |
SIMONIEL |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 04 PROPOSED TO RENOVATE & CONVERT EXISTING BUI
|
|
Work on Floor(s): CEL,ROF 001 thru 004
|
| 03/27/2019 |
240205416 |
03 |
A2 |
P APPROVED |
03/27/2019 |
|
BERGER |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01 IT IS PROPOSED TO THE REMOVE INTERIOR NON-L
|
|
Work on Floor(s): CEL 001 thru 004
|
| 03/13/2019 |
220649305 |
07 |
A1 |
P APPROVED |
03/20/2019 |
0075954 PE |
SIMONIEL |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 02
|
|
Work on Floor(s): CEL,ROF 001 thru 004
|
| 03/13/2019 |
220649305 |
06 |
A1 |
P APPROVED |
03/20/2019 |
0075954 PE |
SIMONIEL |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 04
|
|
Work on Floor(s): CEL,ROF 001 thru 004
|
| 02/19/2019 |
220690562 |
01 |
A2 |
X SIGNED OFF |
11/04/2019 |
0075814 PE |
RITIENI |
|
NOT APPLICABLE
|
|
INSTALLATION OF NEW, MANUAL AND AUTOMATIC, SMOKE/CO DETECTION, SPRINKLER F
|
|
Work on Floor(s): CEL 001 thru 004
|
| 12/20/2018 |
220649305 |
05 |
A1 |
P APPROVED |
01/17/2019 |
0075954 PE |
SIMONIEL |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 04
|
|
Work on Floor(s): CEL,ROF 001 thru 004
|
| 12/06/2018 |
240205416 |
02 |
A2 |
P APPROVED |
12/20/2018 |
0042038 PE |
BERGER |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01 IT IS PROPOSED TO THE REMOVE INTERIOR NON-L
|
|
Work on Floor(s): CEL 001 thru 004
|
| 10/22/2018 |
220649305 |
03 |
A1 |
X SIGNED OFF |
10/15/2020 |
0093345 PE |
WEINSTEI |
|
NOT APPLICABLE
|
|
SUBSEQUENT FILING OF STRUCTURAL WORK AS SHOWN ON PLANS.
|
|
Work on Floor(s): CEL,ROF 001 thru 004
|
| 08/01/2018 |
220649305 |
04 |
A1 |
X SIGNED OFF |
10/15/2020 |
0075954 PE |
SIMONIEL |
|
NOT APPLICABLE
|
|
PROPOSED TO RENOVATE & CONVERT EXISTING BUILDING TO A NON-PROFIT INSTITUTI
|
|
Work on Floor(s): CEL,ROF 001 thru 004
|
| 08/01/2018 |
220649305 |
02 |
A1 |
X SIGNED OFF |
10/15/2020 |
0075954 PE |
SIMONIEL |
|
NOT APPLICABLE
|
|
SUBSEQUENT FILING OF SPRINKLER WORK AS SHOWN ON PLANS.
|
|
Work on Floor(s): CEL,ROF 001 thru 004
|
| 07/23/2018 |
220649305 |
01 |
A1 |
X SIGNED OFF |
10/15/2020 |
0042038 PE |
BERGER |
|
NOT APPLICABLE
|
|
PROPOSED TO RENOVATE & CONVERT EXISTING BUILDING TO A NON-PROFIT INSTITUTI
|
|
Work on Floor(s): CEL,ROF 001 thru 004
|
| 11/09/2017 |
240205416 |
01 |
A2 |
X SIGNED OFF |
07/25/2019 |
0042038 PE |
BERGER |
|
NOT APPLICABLE
|
|
IT IS PROPOSED TO THE REMOVE INTERIOR NON-LOAD BEARING PARTITIONS,AND FINI
|
|
Work on Floor(s): CEL 001 thru 004
|
| 11/06/2017 |
240205149 |
01 |
A2 |
H P/E IN PROCESS |
11/06/2017 |
0039316 RA |
AKERMAN |
|
NOT APPLICABLE
|
|
JOB WITHDRAWN 11/08/2017 INTERIOR RENOVATIONS AS PER PLANS FILED HEREWITH.
|
|
Work on Floor(s): CEL 001 thru 004
|
| 02/10/2015 |
240089364 |
01 |
A2 |
R PERMIT-ENTIRE |
06/01/2017 |
0051702 PE |
DELORENZ |
|
NOT APPLICABLE
|
|
JOB WITHDRAWN 07/11/2019 INSTALL NEW WATER SERVICE FOR NEW SPRINKLER SYSTE
|
|
Work on Floor(s): CEL,ROF 001 thru 004
|
| 08/02/2006 |
201068478 |
01 |
A2 |
X SIGNED OFF |
12/21/2006 |
0068760 PE |
Apostolo |
|
NOT APPLICABLE
|
|
Filing for the replacement of existing oil storage tank with two new 275 g
|
|
Work on Floor(s): CEL
|