| FILE DATE |
JOB # |
DOC # |
JOB TYPE |
JOB STATUS |
STATUS DATE |
LIC # |
APPLICANT |
IN AUDIT |
ZONING APPROVAL |
| 01/15/2019 |
220111206 |
09 |
A1 |
P APPROVED |
02/03/2020 |
|
MONTOYA |
|
AMENDED 10/10/2019
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,001,002
|
| 06/01/2017 |
240185456 |
01 |
A3 |
R PERMIT-ENTIRE |
06/06/2017 |
0035839 RA |
O'CONNOR |
|
NOT APPLICABLE
|
|
PROPOSED INSTALLATION OF HEAVY DUTY SIDEWALK SHED FOR REMEDIAL REPAIRS AS
|
|
Work on Floor(s): OSP
|
| 11/09/2016 |
220544436 |
01 |
PA |
J P/E DISAPPROVED |
02/21/2017 |
0016966 RA |
GALO |
|
NOT APPLICABLE
|
|
Work on Floor(s): 002
|
| 11/09/2016 |
220544445 |
01 |
PA |
J P/E DISAPPROVED |
02/21/2017 |
0016966 RA |
GALLO |
|
NOT APPLICABLE
|
|
Work on Floor(s): 001
|
| 09/28/2016 |
220111206 |
08 |
A1 |
P APPROVED |
10/20/2016 |
|
MONTOYA |
|
AMENDED 10/10/2019
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,001,002
|
| 06/01/2016 |
220111206 |
06 |
A1 |
P APPROVED |
06/21/2016 |
|
MONTOYA |
|
AMENDED 10/10/2019
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,001,002
|
| 12/17/2013 |
220111206 |
05 |
A1 |
P APPROVED |
10/08/2014 |
|
MONTOYA |
|
AMENDED 10/10/2019
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,001,002
|
| 03/16/2012 |
220111206 |
04 |
A1 |
P APPROVED |
04/05/2012 |
|
MONTOYA |
|
AMENDED 10/10/2019
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,001,002
|
| 03/05/2012 |
220111206 |
03 |
A1 |
P APPROVED |
03/08/2012 |
|
MONTOYA |
|
AMENDED 10/10/2019
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL,001,002
|
| 07/18/2011 |
220111206 |
02 |
A1 |
R PERMIT-ENTIRE |
05/30/2012 |
0018684 RA |
MONTOYA |
|
AMENDED 10/10/2019
|
|
SPRINKLER WORK
|
|
Work on Floor(s): CEL
|
| 04/07/2011 |
220111206 |
01 |
A1 |
R PERMIT-ENTIRE |
08/30/2016 |
0018684 RA |
MONTOYA |
|
AMENDED 10/10/2019
|
|
CONVERT EXISTING COMMERCIAL BUILDING TO PLACE OF WORSHIP.
|
|
Work on Floor(s): CEL,001,002
|
| 07/22/2008 |
210037994 |
02 |
A2 |
D A/P ENTIRE |
07/25/2008 |
|
SABAHA |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01 NATURAL GAS PIPING FOR DOMESTIC GAS FIRED H
|
|
Work on Floor(s): 01 thru 02
|
| 03/03/2008 |
210037994 |
01 |
A2 |
Q PERMIT-PARTIAL |
07/10/2008 |
0082264 PE |
SABAHA |
Y |
NOT APPLICABLE
|
|
MODIFICATION PLUMBING WATER SUPPLY AND SEWER WASTE PIPING TO ACCOMMODATE C
|
|
Work on Floor(s): 01 thru 02
|
| 09/05/2006 |
200826561 |
02 |
A1 |
P APPROVED |
09/13/2006 |
0082264 PE |
SABAHA |
|
NOT APPLICABLE
|
|
DOC WITHDRAWN 06/06/2012
|
|
Work on Floor(s): 001 thru 003
|
| 07/14/2006 |
200808340 |
03 |
A2 |
G PAA FEE DUE |
07/14/2006 |
0028533 RA |
ELLIS |
|
NOT APPLICABLE
|
|
DOC WITHDRAWN 06/06/2012
|
|
Work on Floor(s): 001 thru 002
|
| 06/08/2006 |
200808340 |
02 |
A2 |
P APPROVED |
06/16/2006 |
0028533 RA |
ELLIS |
|
NOT APPLICABLE
|
|
DOC WITHDRAWN 06/06/2012
|
|
Work on Floor(s): 001 thru 002
|
| 03/25/2005 |
200939985 |
01 |
PA |
J P/E DISAPPROVED |
03/29/2005 |
0028533 RA |
ELLIS |
|
NOT APPLICABLE
|
|
Work on Floor(s): 002
|
| 03/04/2005 |
200933990 |
01 |
PA |
J P/E DISAPPROVED |
04/21/2005 |
0028533 RA |
ELLIS |
|
NOT APPLICABLE
|
|
JOB WITHDRAWN 10/27/2016
|
|
Work on Floor(s): 002
|
| 02/05/2004 |
200826561 |
01 |
A1 |
P APPROVED |
08/29/2006 |
0028533 RA |
ELLIS |
|
NOT APPLICABLE
|
|
JOB WITHDRAWN 06/06/2012 1.NO WORK TO BE PERFORMED UNDER THISAPPLICATION 2
|
|
Work on Floor(s): 001 thru 003
|
| 10/02/2003 |
200808340 |
01 |
A2 |
R PERMIT-ENTIRE |
06/11/2008 |
0028533 RA |
ELLIS |
|
NOT APPLICABLE
|
|
JOB WITHDRAWN 06/06/2012 REPAIR EXISTING STAIRS, ADD NEW STAIRS & RAMP, R
|
|
Work on Floor(s): 001 thru 002
|
|
220111206 |
07 |
A1 |
A PRE-FILED |
09/28/2016 |
|
MONTOYA |
|
AMENDED 10/10/2019
|
|
DOC WITHDRAWN 09/17/2019
|
|
Work on Floor(s): CEL,001,002
|