| FILE DATE |
JOB # |
DOC # |
JOB TYPE |
JOB STATUS |
STATUS DATE |
LIC # |
APPLICANT |
IN AUDIT |
ZONING APPROVAL |
| 05/15/2019 |
240250606 |
01 |
A2 |
X SIGNED OFF |
04/17/2020 |
0081461 PE |
DELIC |
|
NOT APPLICABLE
|
|
REPAIR THE BUILDING FACADE DETERIORATED COMPONENTS AND MATERIAL ELEMENTS A
|
|
Work on Floor(s): FAC
|
| 07/22/2016 |
220542615 |
01 |
A2 |
J P/E DISAPPROVED |
07/22/2016 |
0010254 RA |
FERRARA |
|
NOT APPLICABLE
|
|
FILING TO REMOVE AND RESTORE EXISTING CONCRETE STAIR AND PAVING AT THE FRO
|
|
Work on Floor(s): OSP,001
|
| 09/04/2012 |
220223960 |
01 |
A3 |
R PERMIT-ENTIRE |
04/05/2013 |
0066791 PE |
PARIHAR |
|
NOT APPLICABLE
|
|
PROPOSED INSTALLATION OF HEAVY DUTY SIDEWALK SHED FILED FOR REMEDIAL REPAI
|
|
Work on Floor(s): OSP
|
| 01/12/2012 |
220164756 |
01 |
A2 |
R PERMIT-ENTIRE |
05/18/2015 |
0038991 PE |
JOSELOW |
|
NOT APPLICABLE
|
|
REPLACE EXISITNG HEATING AND HOT WATER HEATER SYSTEM IN THE BUILDING, REP
|
|
Work on Floor(s): CEL,001,TO, 006
|
| 01/03/2012 |
220156408 |
02 |
A2 |
G PAA FEE DUE |
01/03/2012 |
|
FERRARA |
|
NOT APPLICABLE
|
|
POST APPROVAL AMENDMENT FOR 01
|
|
Work on Floor(s): CEL 001 thru 006
|
| 11/21/2011 |
220156408 |
01 |
A2 |
R PERMIT-ENTIRE |
05/18/2015 |
0010254 RA |
FERRARA |
|
NOT APPLICABLE
|
|
RENOVATE ALL THE KITCHENETTES, INSTALL NEW CABINETS AND REPLACE ALL SINKS,
|
|
Work on Floor(s): CEL 001 thru 006
|
| 08/10/2011 |
220134263 |
01 |
A2 |
X SIGNED OFF |
01/14/2016 |
0010254 RA |
FERRARA |
|
NOT APPLICABLE
|
|
CUT AND POINT MORTAR JOINTS ON ALL ELEVATIONS,INSTALL NEW DOUBLE HUNG ALUM
|
|
Work on Floor(s): 001 thru 006
|
| 05/13/2011 |
220118619 |
01 |
A3 |
X SIGNED OFF |
10/24/2011 |
0064004 PE |
WALSH |
|
NOT APPLICABLE
|
|
ERECT A TOTAL OF 27 LINEAR FEET BY 8 FEET APPROXIMATE HIGH HEAVY DUTY SIDE
|
|
Work on Floor(s): OSP
|
| 03/21/2011 |
220109166 |
01 |
A2 |
X SIGNED OFF |
02/04/2016 |
0010254 RA |
FERRARA |
|
NOT APPLICABLE
|
|
REMOVE AND INSTALL NEW ROOF AT THE GARAGE AND BUILDING
|
|
Work on Floor(s): 001 thru 006
|
| 03/18/2002 |
200720201 |
01 |
A2 |
P APPROVED |
03/19/2002 |
0070051 PE |
Marchese |
|
NOT APPLICABLE
|
|
General construction associated with combination of apartments on 1st, 4th
|
|
Work on Floor(s): 001,004,006
|
| 04/19/2001 |
200667750 |
01 |
A2 |
R PERMIT-ENTIRE |
04/24/2001 |
0074939 PE |
HOCKMAN |
|
NOT APPLICABLE
|
|
REPLACE (1) NEW 5,000 GALLON F/O TANK IN 3 HR FIRE RATED MASONARY TANK V
|
|
Work on Floor(s): CEL
|
| 10/09/1998 |
200534298 |
01 |
A2 |
R PERMIT-ENTIRE |
10/21/1998 |
0069119 PE |
CADER |
|
NOT APPLICABLE
|
|
ROOF AND PARAPET WALL AS PER PLANS. NO USE EGRESS OR OCCUPANCY
|
|
Work on Floor(s): PAR,ROF
|
| 07/09/1998 |
200518902 |
01 |
A2 |
R PERMIT-ENTIRE |
09/30/1998 |
0038313 PE |
CHIARO |
|
NOT APPLICABLE
|
|
(2) BURNER REPLACEMENTS ONLY NO CHANGE IN EGRESS OR OCCUPANCY
|
|
Work on Floor(s): CEL
|
| 02/06/1998 |
200499692 |
01 |
A3 |
R PERMIT-ENTIRE |
02/17/1998 |
0065430 PE |
HICKEY |
|
NOT APPLICABLE
|
|
INSTALLATION OF SHED 113'DURING FACADE R EPAIR,NO CHANGE IN USE,EGRESS O
|
|
Work on Floor(s): OSP
|
| 06/03/1997 |
200424353 |
01 |
A2 |
R PERMIT-ENTIRE |
06/11/1997 |
0050579 PE |
RUDIKOFF |
|
NOT APPLICABLE
|
|
CHANGE GRADE OF OIL FROM #6 TO #4 REMOVE 2 OIL PREHEATERS AND INSTALL 2
|
|
Work on Floor(s): CEL
|